Professional Documents
Culture Documents
Program Evaluation Review Technique (PERT) : Project Planning, Scheduling, and Control
Program Evaluation Review Technique (PERT) : Project Planning, Scheduling, and Control
ENMG 632
The estimates for the various activities in a project form the basis on which the success
of the schedule relies.
It has been so far assumed in CPM that the estimates of activity durations were
accurate and assigned to activities with confidence.
PERT was developed in the late 1950s in collaboration between the U.S. Navy, Booz-
Allen Hamilton, and Lockheed Corporation for the creation of the Polaris missile
program.
PERT was originally used in research and development (R&D), or other undertakings
where insufficient experience or historical data were available for estimating the
durations of individual activities in a project.
Like CPM, PERT uses logic networks to calculate the completion date of a project or
the date of any other event in the schedule.
This probability depends on uncertainty in the durations of the activities that lead to
the desired event (e.g., project completion).
This time range is defined by three values: (1) the activity’s most likely duration or the
mode (Tm), (2) the activity’s most pessimistic duration (Tp), and (3) the activity’s most
optimistic duration(T0).
For these time estimates, probability distributions can be used that are either
symmetrical (the normal distribution) or asymmetrical (the beta distribution).
Because pessimistic and optimistic values are estimated at the 95% confidence level
from either end of the distribution, they will cancel each other out, leaving the most
likely value as the mean or expected duration time for the activity (Te).
Tm /Mean= Te
The asymmetry of the probability distribution suggests we recognize that certain events
are less likely to occur than others.
Mean= Te
Duration= Mean+X*SD
X= Duration-Mean/SD
= 30-24/8= 0.75
P(D<30)=P(X<0.75)
=0.7734
Normal Distribution Showing the Probability of Completing the Excavation Work in Less than 30 days
𝟒𝟎−𝟐𝟒
P(D<40)=P(X< )
𝟖
= P ( X <2)
= 0.9772
Normal Distribution Showing the Probability of Completing the Excavation Work in Less than 40 days
= 1- 0.9155= 0.0845
Normal Distribution Showing the Probability of Completing an Activity in More than 100 Days
P(D<55)= P(X<-1.09)
=P(D>72.34)
= 1- P( D< 72.34)
𝟕𝟐.𝟑𝟒−𝟔𝟑.𝟔𝟕
= 1- P ( X<
𝟕.𝟗𝟑
)
= 1-P (X<1.09)
This single number assignment of a duration makes it easy to perform CPM network
calculations.
Duration assignments are guesses and that considerable uncertainty may actually
exist in the value used the errors of overestimation and underestimation will
cancel out each other.
Despite being less commonly used in the construction industry than CPM, it is
worthwhile to have a good understanding of the PERT technique.
PERT makes it possible for the scheduler to make more informed decisions about the
probability of achieving stated project durations and can thereby help in keeping
schedules more realistic.