Balance of Work (Elevation & Stair 1 & 2)
Balance of Work (Elevation & Stair 1 & 2)
Balance of Work (Elevation & Stair 1 & 2)
Front Elevation
Balance of work
1.Rectify painting works near
2 balcony, unit 16
2. Apply paint at pipe of
plumbing
2
2 3. scaffolding at sky garden
4.sky garden for water proofing
(17th, 16th, 10th floor)
5.tiling works at sky garden (12th
floor).
2
3
Rear side
1. Dismantling of Alimax
2. Sky garden with
scaffolding
3. Uninstalled window
from 16th- 19th floor
4. Uninstalled plastic
groove from 7th -3rd floor
5. Primer paint only from
7th floor – 3rd floor
6. Balcony railing not yet
primer paint from14th –
19th floor
Left Side Elevation
1. Groove not yet align
2. Rectfy paint at roof deck
3. Pvc pipe to paint at unit 23
4.
Right side Elevation
1. Indian tears paint on going
to application
2. Some balcony for primer
application
3. Plastic groove at fire wall
for verification.
Balance of work at stair 1
1. Concrete poring at pipe of fire pro (19th, 12th, 8th, 9th, 10th)
2. On going skim coating from 9th floor
3. Plastering works at header at fire exit 1 from 18th -9th floor
4. Primer paint of stair railing