Scope:
In our world one out of five people are lacking access to clean, safe and affordable electricity. At this scenario we are introducing miniature
version of airborne powerplants. Which only consumes lesser space for implementing and has a larger economic benefit. It is mainly
designed for domestic purpose . It is the first time this technology is been introduced to the domestic level.
Application
Provide electricity in a sustainable way and in affordable price
It can be used in heavily populated areas, Since less space consuming
Implementation is possible even if the house roof top is not that much rigid
Will work in Day time as well as in night time
Key Characteristics
Work even in night time
Can implemented even if the roof top is made of sheets
Roof top shape is not a problem for implementation
Since the kite will be in high altitude the availability of wind also increases
Principle of product Operation
The basic working principle is traction and retraction. In traction the kite is flown in a cross-wind figure of eight pattern
to achieve a high pulling force in order to reel out the cable from the winch in the ground station. And in retraction, when the
maximum line length is reached, the kite's profile is adjusted in order to reel-in the cable with low force using a small fraction
of energy generated in the previous phase. And while this time the generator connected to the system rotates and power is produced
Performance Characteristics
Physical Characteristics
Electrical Specifications
Environmenntal specifications
Safety Specifications
Criteria Target
Target Product Cost 75000
Target Operating Cost 4000 per year
Target waranty Cost 7500
Requirement Target
Packaging type Carboard box
Package size 100cm×150cm×200cm
Package weight 40kg
Package matterial,label Printed
No of parts per box 8
STD Features and options Energy management system, Off gird solution with airborne wind power plant
STD Elements from Market Control Pod,Automatic Kite String Reeler-Inner,Generator,Battery & Controller
Configured Features and Options Parachute & Magnus balloon
Crating 100cm×150cm×200cm
Shipping By road and Ship
Storeage Company warehouse
Installation Technical service team
In-house Testing
Requirement Description
Functional testing Tested for strenght and used for 4hr for finding whether requirement is reached
Performance testing Average produced power is calculated
Quality Specifications
Requirement Description
Product performance rating 99
Failure rate 1
Waranty Specifications
Requirement Description
Cable 1 year
Generator, Parachute 2 year Replacement + 3 year Survice
Other Specifications
Requirement Description
Review prints & current gage list - request any add'l gages needed (specificly moved to Lance to followup on gage req approval in MX - due 2/10; Linda to followup
3 Engr to ID critical areas of plating buildup) 1/23/2004 Troy 01/30/04 immediate rail with Troy on request of add'l/new gages - due 2/10.
10 Quality Decide on VICG plan for 3rd party finishers. 1/29/2004 Erika 02/02/04 Yes Per Tamer 1/30 e-mail, VICG is required for 3rd Party platers.
11 Sourcing Share our deviation process with Suppliers 1/29/2004 Debbie 02/05/04 Yes Will send to Pathline 2/5.
Create & Keep Master file of deviation by part by supplier. (To be entered into moved to NOTE: team agrees it is acceptable to have master file & then to enter in
12 Quality the Lotus Notes system after returning from travel.) 1/29/2004 Hector 02/05/04 immediate rail Lotus Notes database after resource constraint of Feb travel is over.
Ask all knob suppliers if there will be issues if we change knob ID per Omar's
14 Sourcing request 2/2/2004 Debbie 02/03/04 Yes .803/.805 will not be able to hold at production volumes.
Followup with Norman on impact to Tecate if we don't change knob ID per Per 2/9 call with Norman, we will keep the knob print at .801/.805 ID & Tecate
15 PM Omar's request 2/2/2004 Linda 02/03/04 Yes will order new polishing tooling.
Request deviations from suppliers on knob hardness - (until DVT can be cmplt
16 Sourcing & print change if no issues) 2/2/2004 Debbie 02/13/04 Yes
Engr Complete Product Spec Troy 10/6/2003 Sent to Mark & Minu for review.
Engr Release Trim Drawings Jon 10/16/2003 All preliminary prints released but thumbturn rose.
Sourcing Quote Trim Debbie/Danny/Erick 10/23/2003 All but thumbturn rose will be out for quote by 10/27.
Sourcing Approve Quote/Confirm Supplier Selection Debbie/Danny/Erick 10/27/2003
Sourcing Place Tooling PO Debbie/Danny/Erick 10/30/2003