Professional Documents
Culture Documents
Ra 077 78
Ra 077 78
Ra 077 78
Cm t1 t 2 t 3 t 4
Where,
Cm=Cycle time
t1=Excavating Time
t2=Swing Time (Loaded)
t3=Dumping Time
t4=Swing Time (Empty)
std
Cm C m * F( s )
60 * 60
Q 0.58 * 0.54 45 .64 cum / hr
24 .70
1 1
T 0.022(hr / cum)
Q 45.64
Fuel Consumption l/hr for PC-200 Excavator= 12.00
Fuel Consumption ltr/cum for PC-200 Excavato 0.264
Rate Analysis
Labour
Unskilled md 0.00469 750.00 3.51
Sub-Total 3.51
Materials
Disel ltr 0.264 85.40 22.54
Lubricant 0.22
Sub-Total 22.76
Equipments
Excavator hr 0.022 3581.85 78.80
Sub-Total 78.80
Grand Total 105.07 per cum
Road way excavation including disposal upto 10m and lift upto 1.5 m
etc. all complete as per specification.
1 All type of Soil Percentag Rate Amount
Mannually Excavation 5 646.84 32.34
Machine Excavation 95 68.27 64.85
Total(With OH) 111.00 per cum
17) Water 1000 lit 0.00 0.10 0.01 1.50 0.00 0.12 0.50 0.06 0.00
18) Petrol / Diesel / Kerosene 1000 lit 0.00 0.10 0.01 1.50 0.00 0.12 0.50 0.06 0.00
Fuel =Total Travel Time (T)*Fuel Coefficient
Truck, Hr.=Truck Coefficient *(Total Travel Time (T)+Load / Unload Time)
Total Transportation Cost per unit = Labour, md. * Labour Rate + Fuel, Ltr.* Fuel Rate + Truck, Hr.* Truck Rate
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting
2 2.4i 202 the dismantled Material, disposal of unserviceable Material and stacking the serviceable Material with m3 1477.18
all lifts and lead of 1000 meters
Lime /Cement Concrete, By Manual Means( Lime Concrete, cement concrete grade M-10 and below)
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting
3 2.4ii 202 the dismantled Material, disposal of unserviceable Material and stacking the serviceable Material with m3 1735.93
all lifts and lead of 1000 meters
Lime /Cement Concrete, By Manual Means( Cement Concrete Grade M-15 & M-20 )
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting
the dismantled Material, disposal of unserviceable Material and stacking the serviceable Material with
4 2.4iii 202 all lifts and lead of 1000 meters
m3 3827.20
Lime /Cement Concrete, By Mechanical Means( Pre-stressed / Reinforced cement concrete grade M-
20 & above )
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting
5 2.4II,i 202 the dismantled Material, disposal of unserviceable Material and stacking the serviceable Material with m3 2392.07
all lifts and lead of 1000 meters
Lime /Cement Concrete, By Mechanical Means( Cement Concrete Grade M-15 & M-20 )
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting
the dismantled Material, disposal of unserviceable Material and stacking the serviceable Material with
6 2.4II,ii 202 all lifts and lead of 1000 meters
m3 2855.52
Lime /Cement Concrete, By Mechanical Means( Pre-stressed / Reinforced cement concrete grade M-
20 & above )
7 2.4III,B 202 Dismantling Stone Masonry, Rubble stone masonry in cement mortar m3 1746.85
Removal of Telephone / Electric Poles and Lines Removal of telephone / Electric poles including
excavation and dismantling of foundation concrete and lines under the supervision of concerned
8 2.14 202 department, disposal with all lifts and up to a lead of 1000 metres and stacking the serviceable and
No 805.00
unserviceable Material separately
B PIPE DRAINS, PIPE CULVERTS AND CONCRETE CHANNELS
Providing, jointing and laying HDPE pipes with or without collar etc. complete in place as per Drawing
9 7.1 A 701 and Technical Specifications. a) 200 mm outer dia.
m 2464.31
Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying
Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2
10 7.2 A 701 m 4515.60
as per Drawing and Technical Specifications. 300 mm internal dia(with socket system).
Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying
11 7.2B 701 Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 m 6498.94
as per Drawing and Technical Specifications. 450 mm internal dia(with socket system).
Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying
12 7.2 C 701 Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 m 8791.56
as per Drawing and Technical Specifications. 600 mm internal dia (with socket system).
Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying
13 7.2 D 701 Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 m 16633.94
as per Drawing and Technical Specifications. 900 mm internal dia (with socket system).
Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying
14 7.2 E 701 Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 m 18599.06
as per Drawing and Technical Specifications. 1000 mm internal dia (with socket system).
Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying
15 7.2 F 701 Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 m 20091.85
as per Drawing and Technical Specifications. 1200 mm internal dia (with socket system).
Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying
16 7.2 701 Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 m 3606.78
as per Drawing and Technical Specifications. 200 mm internal dia.
C EARTHWORKS
Roadway Excavation in all types of soil by Manual Means as per drawing and technical specification,
17 9.1.I A 905 including removal of stumps and other deleterious matter, with all lifts and lead as per Drawing and m3 693.92
instruction of the Engineer.
Road way Excavation in all types of soil by Mechanical Means as per Drawing and technical
18 9.1.I B 905 specifications including removal of stumps and other deleterious matter, all lifts and lead as per m3 73.34
Drawing and instruction of the Engineer.
Earth work in excavation of foundation of structures, including construction of shoring and bracing,
19 9.4.I.A.i 907 removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing m3 808.45
and Technical Specifications. Ordinary soil by Manual means upto 3m depth.
Earth work in excavation of foundation of structures, including construction of shoring and bracing,
removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing
21 9.4.II.A i 907 and Technical Specifications. Ordinary Rock (not requiring blasting) by Manual means upto 3m depth
m3 980.95
Earth work in excavation of foundation of structures, including construction of shoring and bracing,
removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing
22 9.4.II.A ii 907 and Technical Specifications. Ordinary rock (not requiring blasting) by Mechanical means upto 3m
m3 316.52
depth.
Preparation and surface treatment of Formation by removing mud and slurry, watering to the extent
needed to maintain desired moisture content ,compacting all complete as per Drawing and Technical
23 9.7 A 909, 910 Specifications.
m3 9.03
Construction of Embankment with Material obtained from Borrow pits Providing, laying, spreading and
24 9.8 909, 910 compacting embankment with borrow material as per Drawing and Technical Specifications. m3 484.76
Construction of Embankment with Material Deposited from Roadway Cutting Providing, laying,
spreading and compacting embankment with roadway cutting material and compact to the required
25 9.09 B 909, 910 density as per Drawing and Technical Specifications. (With machine)
m3 376.38
Providing suitable material and Back filling with Granular Material behind abutment, wing wall and
26 9.11 A 908 return wall complete as per Drawing and Technical Specifications. m3 1213.51
Backfilling in layers in foundation pits, trenches with locally available material etc. including compaction
27 9.11-C 908 and watering etc all complete (908 ) .
m3 866.95
D ACTIVITY GROUP 10 : SUB GRADES
Scarifying the existing granular road surface by Mannual means to a depth of 50 mm and disposal of
28 10.1 B 1003 scarified Material with all lifts and leads within Right of way as per Drawing and Technical m2 19.22
Specifications.
Scarifying the existing road surface to a depth of 50 mm and disposal of scarified Material with in all
29 10.2 A 1003 lifts and lead as per Drawing and Technical Specifications. Lead upto 30m. m2 23.38
Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified Material
30 10.2 B 1003 with in all lifts and lead as per Drawing and Technical Specifications. m2 14.57
Compacting original ground supporting sub-grade. Loosening of the ground upto a level of 500 mm m3 142.02
31 10.4 I 1003 below the sub-grade level, watered, graded and compacted in layers as per drawwings and technical
specifications. m2 35.51
Providing and laying of hand pack Stone soling with 150 to 200 mm thick stones and packing with
32 10.8 1006 smaller stone on prepared surface as per Drawing and Technical Specifications. m3 6996.82
.
E SUB-BASE, BASE
Providing and laying granular sub-base on prepared surface, mixing at OMC, and compacting to
achieve the desired density, complete as per Drawing and Technical Specifications. By mechanical
33 12.1 A 1201 means.
m3 2900.17
Providing and laying granular sub-base on prepared surface, mixing at OMC, and compacting to
34 12.1 B 1201 achieve the desired density, complete as per Drawing and Technical Specifications. By manual means. m3 2986.55
Crusher Run Macadam sub-base. Providing and laying Crusher Run Macadam on a prepared surface,
35 12.7 A i 1204 spreading and mixing , watering and compacting to form a layer of sub-base/Base course as per m3 3564.44
Drawing and Technical Specifications. By Mix in palce method. ii) for 63mm maximum size
Crusher Run Macadam Base. Providing and laying Crusher Run Macadam on a prepared surface,
36 12.7 A ii 1204 spreading and mixing , watering and compacting to form a layer of sub-base/Base course as per m3 4468.91
Drawing and Technical Specifications. By Mix in palce method. ii) for 45mm maximum size
F BITUMINOUS SURFACE AND BASE COURSE
Providing and applying tack coat with hot Bitumen By Mechanical Means at specified rate on the
37 13.2 i 1301, 1302 prepared non-bituminous surfaces including cleaning as per Technical Speciation .
Ltr 108.85
Providing and applying tack coat with hot Bitumen by Manual Means at the specified rate the prepared
38 13.2 ii 1301, 1302 surfaces including cleaning as per Technical Speciation . Ltr 156.75
Providing and applying prime coat with hot bitumen MC 30/70 (including cutter)on prepared surface of
39 13.1 i 1301, 1302 granular base including cleaning of road surface and spraying at specified rate by mechanical means Ltr 119.79
as per Technical specification.
Providing and applying prime coat with hot bitumen MC 30/70 (including cutter)on prepared surface of
40 13.1 ii 1301, 1302 granular base including cleaning of road surface and spraying at specified rate by manual means as per Ltr 211.49
Technical specification.
Providing and laying Bituminous concrete/ Asphalt concrete using crushed aggregates of specified
1307,1308, grading, premixed with bituminous binder and filler as per Drawing and Technical Specifications
41 13.6 m3 22614.38
1309
Providing and laying 'Dense Bituminous Macadam' using crushed aggregates(40 mm nominal sze) of
42 13.5 1308 specified grading, premixed with bituminous binder as filler as per Drawing and Technical m3 19114.06
Specifications (SS 1308).
Providing and laying open-graded premix carpet of 20mm thickness of 13.2mm to 5.6mm aggregate as
43 13.9 1311 wearing course (Manually) on a previously prepared base as per Drawing and Technical Specifications m3 15161.73
(SS 1311).
Providing and laying open-graded premix carpet of 20mm thickness of 13.2mm to 5.6mm aggregate as
44 13.9 1311 wearing course (Mechanically) on a previously prepared base as per Drawing and Technical m3 13228.18
Specifications (SS 1311).
✘
Providing and laying of M20 precast cement concrete Kerb 38cm * 20 cm * 25 cm ( H*B*L) with 12 mm
thick 1:3 Cement sand mortar bedding and joints including foundation excavation levelling but excluding
43 14.1 1401 foundation concrete for foundation or sand gravel material, all complete as per Drawing and Technical m 1383.13
Specifications.
Providing and laying of precast / cast in situ 50 mm (M20/20) thick cement concrete interlocking block
44 14.2 1401 on 12 mm thick 1: 3 cement sand mortar over the prepared base, all complete as per Drawing and m2 1352.138
Technical Specifications.
Providing and laying brick on edge over 60 mm thick sand bed in footpath including excavation sand
45 14.5,A 1403 bedding all complete as per Drawing and Technical Specifications. Unit = sqm (For 10 sqm) (1403)
m2 1777.603
Providing and laying flat brick over 60 mm thick sand bed in footpath including excavation sand
46 14.5,B 1403 bedding all complete as per specification. Unit = sqm (For 20 sqm) (1403)
m2 865.0875
H TRAFFIC SIGN, ROAD MARKING , ROAD
Painting Two Coats on Concrete Surfaces, Providing and Painting two coats after filling the surface with
synthetic enamel paint in all shades on concrete /plaster surfaces as per Drawing and Technical
47 15.4 1501 Specifications.
m2 928.29
Painting on Steel Surfaces, Providing and applying two coats of ready mix paint of approved brand on
48 15.5 1501 steel surface after through cleaning of surface to give an even shade as per Drawing and Technical m2 185.03
Specifications.
Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on
Bituminous Surface On smooth surface (similar to Asphalt concrete and rigid pavement) Providing and
49 15.9 i 1504 laying of hot applied thermoplastic compound at least 2 mm thick including reflectorizing glass beads m2 1577.11
as per DOR Traffic sign manual/ Specifications .The finished surface to be level, uniform and free from
streaks and holes.
Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on
Bituminous Surface On rough surface ( similar to surface dressing) Providing and laying of hot applied
50 15.9 ii 1504 thermoplastic compound at least 2 mm thick including reflectorizing glass beads as per DOR Traffic
m2 2013.37
sign manual/ Specifications .The finished surface to be level, uniform and free from streaks and holes.
Providing and lettering new letter and figures of any shade with synthetic enamel paint black or any
51 15.12 1507 other approved color to give an even shade cm letter
Metal Beam Crash Barrier || Type - A, "W" : Metal Beam Crash Barrier || Providing and erecting a "W"
metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above
road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m center to
15.14 A 1509 center, 1.8 m high, 1.1 m below ground/road level metal beam rail to be fixed on the vertical post with a
RM 8093.10975
spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per Drawing and Technical
Specifications.
Metal Beam Crash Barrier || Type - B, "THRIE" : Metal Beam Crash Barrier || Providing and erecting a
"Thrie" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm
above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m
15.14 B 1509 center to center, 2.1 m high with 1.3 m below ground level, metal beam rail to be fixed on the vertical
RM 10724.6565
post with a space of channel section 150 x 75 x 5 mm, 546 mm long complete as per Drawing and
Technical specifications.
I FASLEWORK, FORMWORK & SURFACE FINISH FOR CONCRETE STRUCTURES
Providing , Preparing and Installing form work including necessary supports and removing after
52 18.1 a 1804, 1805 completion for foundation and footings.(Class F1 Finish) Using timber (soft wood ) m2 403.51
Providing , Preparing and Installing form work including necessary supports and removing after
53 18.1 b 1804, 1805 completion for foundation and footings. (Class F1 Finish) Using steel
m2 8981.57
Using timber (soft wood ), Providing , Preparing and Installing form work including necessary supports
54 18.2a.i 1804, 1805 and removing after completion for walls.(Class F2 Finish), vertical plain surface Height upto 3 m
m2 577.20
Using timber (soft wood ), Providing , Preparing and Installing form work including necessary supports
55 18.2 a. ii 1804, 1805 and removing after completion for walls.(Class F2 Finish), vertical plain surface Height above 3 m to 6 m2 934.91
m
Using timber (soft wood ),Providing , Preparing and Installing form work including necessary supports
56 18.2 a. iii 1804, 1805 and removing after completion for walls.(Class F2 Finish), vertical plain surface Height above 6 m to 9 m2 1166.64
m
Using timber (soft wood ) Providing , Preparing and Installing form work including necessary supports
57 18.2 a. iv 1804, 1805 and removing after completion for walls.(Class F2 Finish), vertical plain surface m2 1283.30
Height above 9 m to 10
Using Steel,Providing , Preparing and Installing form work including necessary supports and removing
58 18.2. b .i 1804, 1805 after completion for walls. (Class F2 Finish), vertical plain surface Height above 3 m to 6 m m2 718.41
Using Steel,Providing , Preparing and Installing form work including necessary supports and removing
59 18.2. b ii 1804, 1805 after completion for walls. (Class F2 Finish), vertical plain surface Height above 3 m to 6 m m2 851.87
Using Steel, Providing , Preparing and Installing form work including necessary supports and removing
after completion for walls. (Class F2 Finish), vertical plain surface
60 18.2. b. iii 1804, 1805 Height above 6 m to 9 m
m2 1066.61
Using Steel, Providing , Preparing and Installing form work including necessary supports and removing
61 18.2.b .iv 1804, 1805 after completion for walls. (Class F2 Finish), vertical plain surface m2 1173.27
Height above 9 m to 10m
Providing , Preparing and Installing form work including necessary supports and removing after
62 18.7 c 1803 completion for slab & beam structure.Class F2 Finish, False work not included Using shuttering Ply
m2 893.85
Providing and assembling in position falsework for the construction of RCC superstructure and
63 18.11 i 1803 removing after completion including design & drawings as per specification, for RCC Beam Bridge m2 2674.39
Using steel,Height upto 3 m
Providing and assembling in position falsework for the construction of RCC superstructure and
64 18.11 ii 1803 removing after completion including design & drawings as per specification,for RCC Beam Bridge Using m2 5593.21
steel,Height above 3 m to 6m
Providing and assembling in position falsework for the construction of RCC superstructure and
65 18.11 iii 1803 removing after completion including design & drawings as per specification, for RCC Beam Bridge m2 8719.90
Using steel,Height above 6 m to 9m
Providing and assembling in position falsework for the construction of RCC superstructure and
removing after completion including design & drawings as per specification, for RCC Beam Bridge
66 18.11 iv 1803 Using steel, Height above 9 m
m2 9591.89
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing
74 20.2 G 2000 and Technical Specifications. RCC Grade M30
m3 15572.76
75 20.2 H 2000 Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing m3 15798.40
and Technical Specifications. RCC Grade M 35
Providing and laying , fitting and placing un-coated Mild steel / HYSD reinforcement complete in
76 20.3 2000 foundation as per drawing and technical specification
mt 122136.9
Providing and laying ,fitting and placing Mild steel reinforcement complete in sub-structure as per
77 20.6 2000 drawing and Technical Specification.
mt 125405.20
Providing and laying, fitting and placing HYSD bar reinforcement in super-structure complete as per
78 20.9 2000 Drawing and Technical Specification (SS 2014).
mt 115869.40
L BRICKWORKS FOR STRUCTURES
Providing and laying Brick Masonry Work in Cement mortar in Foundation / structure complete
79 25.1 C 2500 excluding Pointing and Plastering, as per Drawing and Technical Specifications.Cement sand mortar m3 15234.29
(1:4)
Providing and laying Brick masonry work in superstructure/sub-structure complete excluding pointing
80 25.2 C 2500 and plastering, as per drawing and Technical Specifications Cement Mortar 1:4 (1 cement : 4 sand)
m3 16607.00
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work structure as per
81 25.4C 2500 Technical Specifications Cement Mortar 1:4 (1 cement : 4 sand)
m2 3858.06
M MASONRY WORK FOR STRUCTURES
2602, Providing and laying of Stone Masonry Work in Cement Mortar 1:4 in Foundation complete as per
82 26.3 B m3 11208.13
2603,2607 Drawing and Technical Specifications.
2602, Providing and laying of Stone Masonry Work in Cement Mortar 1:6 in Foundation complete as per
83 26.3 C m3 10585.81
2603,2607 Drawing and Technical Specifications..
Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete as per Drawing
84 26.5 A 2600 and Technical Specifications Random Rubble Masonry m3 12877.77
Providing and lying Stone Masonry work in cement mortar 1:6 in structure complete as per Drawing
85 26.6 A 2600 and Technical Specifications Random Rubble Masonry
m3 12251.45
Providing and Pointing with cement mortar on masonry work structure as per Technical Specifications
86 26.7 2600 cement mortar (1:3 )
m2 264.19
87 26.1 2600 Providing and laying dry stone masonry work as per drawing and technical specification.(2600) m3 5686.96
N Construction of Manhole/Catchpit
Providing and fixing cover of C.I. Grating (Medium duty) with frame at requird level including
88 1 dismentalling, concreting nut bolting etc. all complete as per drawing and specification.(size; as per no 3292.5075
site) (2710 )
Providing and fixing C.I. Rounded Manhole cover of 22'' dia.(outer) Heavy class including square frame
89 2 (208kg) all complete
no 37199.05
92 24.6 2403,2404 Providing and Laying and fixing of geo-membrane all complete as per specification (SS 2404,2403). m2 118.7183333
Providing and Laying of geotextile filter between pitching and embankment slopes as per Drawing and
93 24.5 2404 Technical Specification (SS 2404).
m2 118.7183333
Providing and laying Plum concrete (Boulder Mixed Concrete-Machine Mix 60% M 15 concrete and
94 24.21 2421 40% boulders/stones) as per Drawing and Specifications (SS 2421).
m3 10916.11
Providing and laying weep holes in Brick dry/Plain/Reinforced concrete abutment, wing wall/return wall
95 with 110mm dia HDPE Pipe, extending through the full width of the structure with slope of 1V:20H rm 697.5708333
towards drawing face Complete as per Drawing and Technical Specifications (SS 3109).
Providing and laying Gabion structure for retaining earth with diaphgram including rolling, cutting
weaving, placing, laying side and dipahgrams with binding wire and filling boulders all complete. Mesh
96 24.1-A(i) 2401 wire 10swg(0.0615kg/m), selvadge wire 8 swg (0.1057kg/m), binding wire 12swg (0.0409kg/m) m3 6,454.81
Hexagonal mesh Type 100mmx120mm: Box 3x1x1, as per Drawing and Technical Specifications (SS
2401).
Description of works: Providing and Pointing with cement mortar on masonry work structure as per Technical Specifications cement mortar (1:3 ) Unit :
Spec. cl. No: 2600
100sqm
Labour (A) Material (B) Equipment (C)
Norms No.26.7A
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled md 9.00 1030.00 9270.00 Cement t 0.310 16500.00 5115.00
Unskilled md 9.00 750.00 6750.00 Sand m3 0.630 2896.32 1824.68
water KL 0.050 260 13.00
Sub total of A = 16020.00 Sub total of B = 6952.68 Sub total of C = 0.00
Sub total of A +B + C = 22972.68 Contractor's overhead expenses 15% = 3445.90 Unit Rate = 26418.58
Ra per sqm 264.19
Description of works: Providing and laying dry stone masonry work as per drawing and technical specification.
Unit : 5cum
Spec. cl. No: 2600
Labour (A) Material (B) Equipment (C)
Norms No.26.1
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled md 4.00 1030.00 4120.00 stone m3 5.750 2540.16 14605.92
Unskilled md 8.00 750.00 6000.00
District Rate:Materials
S.No. Details Unit Rate Remarks
1 Unskilled Labour Md. 750.00
2 Skilled Labour Md. 1030.00
3 Semi-Skilled Labour Md. 845.00
4 Operator/Mhecanics/ Md. 698.00
5 Foreman Md. 690.00
6 Sub engineer/Draft man/Omin Md. 908.00
7 Engineer Md. 1081.00
8 Granular soil for capping layer m3 510.00
9 Gravel (River bed) for subbase m3 2019.43
10 Gravel (Quarry) for subbase m3 1766.00
11 Granular sub base material (63mm down crusher run) m3 2225.16
12 Base course material (Crushed)(40 mm down size) m3 2578.36
13 Base course (WBM) material (Mix soling) m3 2802.20 79.3375
14 Stone dust m3 1165.56
15 Brick (Local) per 1000 14300.00 14 per brick
16 Brick (Machine made) per 1000 15300.00 15.3 per brick
17 Stone (River) m3 3139.92
18 Stone (Quarry) m3 2540.16
19 Flag stone for paving 25mm thick m2 818.14
20 Flag stone for paving 50mm thick m2 1108.80
21 Sand (River) m3 2896.32
22 Sand (Quarry) m3 2896.32
23 Filter material (40% aggregates & 60% sand) m3 2857.40
24 Cement (OPC)-Nepali Mt 16500.00 825 per Bag
25 Cement (Others) PPC-Nepali Mt 14500.00 725 per Bag
26 Micro-concrete (sikrep 4 or similar) bag 1650.00
27 Cement Admixture( Silica cement Admixture) Kg. 330.00
28 coarse agg,(6-10mm) m3 2787.12
29 coarse agg,(10-20mm) m3 2963.52
30 coarse agg,(20-40mm) m3 2778.30
31 key agg.(6mm down) m3 2667.17
32 Stone chips/River (5~20 mm) m3 2878.66 1515.08 per t.
33 Wood m3 44452.80 1260.00 per cft.
34 Local wood for form work m3 44452.80 1260.00 per cft.
35 Ply wood 8 mm (Commercial) m2 505.25
36 Ply wood 12 mm (Commercial) m2 752.50
37 Nails (different sizes) Kg. 112.00
38 Nut& Bolts nos 28.00
39 Jute Kg. 34.00
40 Gabion wire 8 Gauge (Heavy duty) Kg. 105.00
41 Gabion wire 10 Gauge (Heavy duty) Kg. 105.00
42 Gabion wire 12 Gauge (Heavy duty) Kg. 105.00
43 (a)Reinforcement (dia. Upto 8 mm), TOR Steel Mt 82000.00 82 per kg
44 (b)Reinforcement (dia. 10mm~25 mm), TOR Steel Mt 79000.00 79 per kg
45 (c)Reinforcement (dia. 28mm~32 mm), TOR Steel Mt 82000.00 82 per kg
46 (a)Reinforcement (dia. 8 mm), TMTSteel Mt 86000.00 86 per kg
47 (b)Reinforcement (dia. 10mm~22 mm), TMTSteel Mt 84000.00 84 per kg
48 (c)Reinforcement (dia. 25mm~32 mm), TMT Steel Mt 85000.00 85 per kg
49 Binding Wire Kg. 92.00
50 Bitumen (80/100 grade) Kg. 78.00
51 Bitumen Emulsion(MS 60) Kg. 69.00
52 Hi-seal Readymix Kg. 98.00
53 Petrol lit. 108.00 95.58 ex VAT
54 Diesel lit. 96.50 85.40 ex VAT
55 Kerosene lit. 96.50 85.40 ex VAT
56 Water (more than 3km transport) KL 260.00 0
98
GI pipe(HC) 40 mm dia. r.m. 503.00
99
GI pipe(HC) 50 mm dia. r.m. 740.00
100
GI pipe(HC) 100 mm dia. r.m. 1676.00
101 C.I. Rounded Manhole cover of 600 mm dia.(outer) heavy with 15%
class including square frame (IS:1726) Nos 10917.00 12554.55 overhead
102 C.I. Rounded Manhole cover of 650 mm dia.(outer) with 15%
medium class including square frame (IS:1726) Nos 13261.00 15250.15 overhead
103 C.I. Rounded Manhole cover of 22'' dia. heavy class with 15%
including square frame (208kg) (IS:1726) nos 32347.00 37199.05 overhead
121
Geo-textile (Indian) Sqm 79.00
122
Geo-textile (Malesiyan) Sqm 98.00
123 Geo-grid fibre glass with tensile strength(di-axial)
(50KN*50KN) Sqm 58.62
Providing and fixing cover of C.I. Grating (Medium duty) with frame at requird level including dismentalling, concreting nut
Item no. misc-1 Description:-
bolting etc. all complete as per drawing and specification.(size; as per site) (2710 )
Unit no
Item No. Labour Material Equipment
Type Unit Qty Rate Amount Type Unit Qty Rate Amount Type Unit Qty Rate Amount
C.I. Grating medium (sizno 1 2863.05 2863.05
Item no. 24.2 Description:- Providing and Laying HDPE pipe with perforations including joining series IV ,HDPE pipe 200mm. (2400)
Unit 100 m
Item No. Labour Material Equipment
24.5 Type Unit Qty Rate Amount Type Unit Qty Rate Amount Type Unit Qty Rate Amount
Skilled md 3 1030 3090 HDPE pipe 200mm m 110 2014.00 221540 Generator hr 24 117.48 2819.52
Unskilled md 10 750 7500 Screw Jack hr 18 15 270
Electric heating
Semi-skilled md 2 845 1690 plate hr 18 25 450
Electric hand
driller hr 12 20 240
Total Labour(A) NRs. 12280 Material(B)NRs. 221540 Equipment(C) NRs. 3779.52
Approved By:
Prepared By: Checked By:
Item no. 24.5 Providing and Laying of geotextile filter between pitching and embankment slopes as per Drawing and Technical Specification
Description:-
(SS 2404).
Unit 300 sqm
Item No. Labour Material Equipment
24.5 Type Unit Qty Rate Amount Type Unit Qty Rate Amount Type Unit Qty Rate Amount
Skilled md 1 1030 1030 Geotextile sqm 360 79.00 28440
Unskilled md 2 750 1500
Item no. 24.16 Description:- Providing and Laying Filter material underneath pitching in slopes complete as per drawings and technical specification.
Unit 1 cum
Item No. Labour Material Equipment
24.16 Type Unit Qty Rate Amount Type Unit Qty Rate Amount Type Unit Qty Rate Amount
Graded stone
aggregate of required
Skilled md 1 1030 1030 size cum 1.2 2857.40 3428.88
Unskilled md 3 750 2250
Item no. 24.21-A(I) Description:- Providing and laying Plum concrete (Boulder Mixed Concrete-Machine Mix 60% M 15 concrete and 40% boulders/stones) as per
Unit Cu.m. Analyzed f 10 Cu.m. Drawing and Specifications (SS 2421).
Item No. Labour Material Equipment Remarks
Type Unit Qty Rate Amount Type Unit Qty Rate Amount Type Unit Qty Rate Amount
24.21-A(I) Skilled md. 3 1030 3090 Cement MT 1.7 16500 28050 Concrete Mixer hr. 6 767.02 4602.12
Concrete
Unskilled md. 30 750 22500 Aggregates 40-20mm Cu.m. 3.45 2778.3 9585.13 Vibrator hr. 6 100 600
Aggregates 20-10mm Cu.m. 1.56 2963.52 4623.09
Approved By:
Prepared By: Checked By:
Item no. 20.7 Description:-
Providing and laying weep holes in Brick dry/Plain/Reinforced concrete abutment, wing wall/return wall with 110mm dia HDPE Pipe,
extending through the full width of the structure with slope of 1V:20H towards drawing face Complete as per Drawing and Technical
Unit RM Analyzed f 30 RM Specifications (SS 3109).
Item No. Labour Material Equipment Remarks
Type Unit Qty Rate Amount Type Unit Qty Rate Amount Type Unit Qty Rate Amount
Skilled
20.7 (Blacksmith) md. 1 1030 1030 HDPE Pipe 110mm dia. meter 31.5 545 17167.5
Unskilled md. 1 750 750 MS Clamp nos. 30 30
Collar of AC Pipe nos. 10 100
Cement Mortar 1:3 tonne 0.025
Sand cum 0.052 2790.359
Item no. 24.1-A(i) Description:- Providing and laying Gabion structure for retaining earth with diaphgram including rolling, cutting weaving, placing, laying side and dipahgrams with
binding wire and filling boulders all complete. Mesh wire 10swg(0.0615kg/m), selvadge wire 8 swg (0.1057kg/m), binding wire 12swg (0.0409kg/m)
Hexagonal mesh Type 100mmx120mm: Box 3x1x1, as per Drawing and Technical Specifications (SS 2401).
2 F.Y. 0
Item no. 24.1-A(iii) Description:- Providing and laying Gabion structure for retaining earth with diaphgram including rolling, cutting weaving, placing, laying side and dipahgrams with
binding wire and filling boulders all complete. Mesh wire 10swg(0.0615kg/m), selvadge wire 8 swg (0.1057kg/m), binding wire 12swg (0.0409kg/m)
Hexagonal mesh Type 100mmx120mm: Box 1.5x1x1, as per Drawing and Technical Specifications (SS 2401).
Unit Cu.m. Analyzed for (1.5x1x1) -4 box
Labour Material Equipment
Item No. Remarks
Type Unit Qty Rate Amount Type Unit Qty Rate Amount Type Unit Qty Rate Amount
24.1-A(iii) Skilled md. 3.00 1030.00 3,090.00 Mesh wire kg 79.00 105.00 8,295.00
Unskilled md. 8.00 750.00 6,000.00 Selvedge wire kg 10.80 105.00 1,134.00
Binding wire kg 5.00 105.00 525.00
Boulder/stone cum 6.60 2540.16 16,765.06
Approved By:
Prepared By: Checked By:
3 F.Y. 0
Item no. 24.1-A(iv) Description:- Providing and laying Gabion structure for retaining earth with diaphgram including rolling, cutting weaving, placing, laying side and dipahgrams with
binding wire and filling boulders all complete. Mesh wire 10swg(0.0615kg/m), selvadge wire 8 swg (0.1057kg/m), binding wire 12swg (0.0409kg/m)
Hexagonal mesh Type 100mmx120mm: Box 1x1x1, as per Drawing and Technical Specifications (SS 2401).
Unit Cu.m. Analyzed for (1x1x1) -6 box
Labour Material Equipment
Item No. Remarks
Type Unit Qty Rate Amount Type Unit Qty Rate Amount Type Unit Qty Rate Amount
24.1-A(iv) Skilled md. 3.00 1030.00 3,090.00 Mesh wire kg 78.96 105.00 8,290.80
Unskilled md. 8.00 750.00 6,000.00 Selvedge wire kg 12.01 105.00 1,261.05
Binding wire kg 4.56 105.00 478.80
Boulder/stone cum 6.60 2540.16 16,765.06
4 F.Y. 0
Item no. 24.1-A(viii) Description:- Providing and laying Gabion structure for retaining earth with diaphgram including rolling, cutting weaving, placing, laying side and dipahgrams with
binding wire and filling boulders all complete. Mesh wire 10swg(0.0615kg/m), selvadge wire 8 swg (0.1057kg/m), binding wire 12swg (0.0409kg/m)
Hexagonal mesh Type 100mmx120mm: Box 3x1x0.50, as per Drawing and Technical Specifications (SS 2401).
Unit Cu.m. Analyzed for (3x1x0.5) -4 box
Labour Material Equipment
Item No. Remarks
Type Unit Qty Rate Amount Type Unit Qty Rate Amount Type Unit Qty Rate Amount
24.1-A(viii) Skilled md. 3.00 1030.00 3,090.00 Mesh wire kg 113.60 105.00 11,928.00
Unskilled md. 9.00 750.00 6,750.00 Selvedge wire kg 13.11 105.00 1,376.55
Binding wire kg 5.44 105.00 571.20
Boulder/stone cum 6.60 2540.16 16,765.06
Approved By:
Prepared By: Checked By:
2500 BRICKWORKS Page 1 of 81
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Err:509
Err:509
Description of works: Providing and laying Brick Masonry Work in Cement mortar in Foundation / structure complete excluding Pointing and Plastering, as
per Drawing and Technical Specifications.Cement sand mortar (1:4) Unit : 5 m3
Spec. cl. No: 2500
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
25.1C Skilled md 6.00 1030.00 6180.00 Bricks 1st class no 2800 14.00 39200.00 Tools and Plants 0.00
Unskilled md 12.00 750.00 9000.00 Cement t 0.48 16500.00 7920.00
Sand m3 1.35 2896.32 3910.03
water KL 0.1 260.00 26.00
Sub total of A = 15180.00 Sub total of B = 51056.03 Sub total of C = 0.00
Sub total of A +B + C = 66236.03 Contractor's overhead expenses 15% = 9935.40 Unit Rate = 76171.43
Rate/cum 15234.29
Description of works: Providing and laying Brick masonry work in superstructure/sub-structure complete excluding pointing and plastering, as per drawing
and Technical Specifications Cement Mortar 1:4 (1 cement : 4 sand) Unit : 5 m3
Spec. cl. No: 2500
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Add 5% of cost of
Skilled md 7.00 1030.00 7210.00 Bricks 1st class no 2800 14.00 39200.00 Labour and material 3438.30
25.2C for scafolding
Unskilled md 14.00 750.00 10500.00 Cement t 0.48 16500.00 7920.00
Sand m3 1.35 2896.32 3910.03
water KL 0.1 260.00 26.00
Sub total of A = 17710.00 Sub total of B = 51056.03 Sub total of C = 3438.30
Sub total of A +B + C = 72204.33 Contractor's overhead expenses 15% = 10830.65 Unit Rate = 83034.98
Rate /cum 16607.00
Description of works: Providing and applying 12.5 mm thick Plaster with cement mortar on brick work structure as per Technical Specifications Cement
Mortar 1:4 (1 cement : 4 sand) Unit : 10 m2
Spec. cl. No: 2500
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
25.4 c Skilled md 10.00 1030.00 10300.00 Cement t 0.58 16500.00 9570.00
Unskilled md 12.00 750.00 9000.00 Sand m3 1.6 2896.32 4634.11
Cost of water KL 0.17 260.00 44.20
Sub total of A = 19300.00 Sub total of B = 14248.31 Sub total of C = 0.00
Sub total of A +B + C = 33548.31 Contractor's overhead expenses 15% = 5032.25 Unit Rate = 38580.56
Rate(1m2) = 3858.06
Description of works: Providing and laying of Plain Cement Concrete M 10 ( or1:3:6 for nominal mix) in Foundation complete as per Drawing and Technical Specifications.
Unit : 15 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.1 Skilled md 2.00 1030.00 2060.00 cement mt 3.450 16500.00 56925.00 Concrete mixer hr 6.00 767.02 4602.12
Unskilled md 22.00 750.00 16500.00 40 mm Aggregate m3 13.500 2778.30 37507.05 Generator hr 6.00 937.37 5624.22
coarse sand m3 6.750 2896.32 19550.16
water KL 2.000 260.00 520.00
Sub total of A = 18560.00 Sub total of B = 114502.21 Sub total of C = 10226.34
Sub total of A +B + C = 143288.55 Contractor's overhead expenses 15% = 21493.28 Unit Rate = 164781.83
rate per cum 10985.46
Description of works: Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications. PCC Grade M 15
Unit : 15m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.2A Skilled md 3.00 1030.00 3090.00 cement mt 4.130 16500.00 68145.00 Concrete mixer hr 6.00 767.02 4602.12
Unskilled md 30.00 750.00 22500.00 40mm aggregate m3 8.100 2778.30 22504.23 Generator hr 6.00 937.37 5624.22
20mm aggregate m3 4.050 2963.52 12002.25 Formwork @4per cent on cost of
concrete i.e. cost of material, labour 4.00% of total cost 6492.02
10mm aggregate m3 1.350 2787.12 3762.61 and equipment
Coarse Sand m 3
6.750 2896.32 19550.16
Cost of water KL 2.000 260.00 520.00
Sub total of A = 25590.00 Sub total of B = 126484.25 Sub total of C = 16718.36
Sub total of A +B + C = 168792.61 Contractor's overhead expenses 15% = 25318.89 Unit Rate = 194111.50
rate per cum 12940.77
Description of works: Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications. PCC Grade M 20
Unit : 15m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.2B Skilled md 3.00 1030.00 3090.00 cement mt 5.160 16500.00 85140.00 Concrete mixer hr 6.00 767.02 4602.12
Unskilled md 30.00 750.00 22500.00 40mm aggregate m3 5.400 2778.30 15002.82 Generator hr 6.00 937.37 5624.22
20mm aggregate m3 5.400 2963.52 16003.00 Formwork @4per cent on cost of
concrete i.e. cost of material, labour 4.00% of total cost 7187.50
10mm aggregate m3 2.700 2787.12 7525.22 and equipment
Coarse Sand m 3
6.75 2896.32 19550.16
Cost of water KL 2.500 260.00 650.00
Sub total of A = 25590.00 Sub total of B = 143871.20 Sub total of C = 17413.84
Sub total of A +B + C = 186875.04 Contractor's overhead expenses 15% = 28031.26 Unit Rate = 214906.30
rate per cum 14327.09
Description of works: Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications. RCC Grade M 20
Unit : 15m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.2C Skilled md 3.00 1030.00 3090.00 cement mt 5.210 16500.00 85965.00 Concrete mixer hr 6.00 767.02 4602.12
Unskilled md 30.00 750.00 22500.00 20mm aggregate m3 8.100 2963.52 24004.51 Generator hr 6.00 937.37 5624.22
10mm aggregate m3 5.400 2787.12 15050.44 Formwork @4per cent on cost of
concrete i.e. cost of material, labour 4.00% of total cost 7241.45
Coarse Sand m3 6.750 2896.32 19550.16 and equipment
Cost of water KL 2.500 260.00 650.00
Sub total of A = 25590.00 Sub total of B = 145220.11 Sub total of C = 17467.79
Sub total of A +B + C = 188277.90 Contractor's overhead expenses 15% = 28241.69 Unit Rate = 216519.59
rate per cum 14434.64
Description of works: Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications. PCC Grade M 25
Unit : 15m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.2D Skilled md 3.00 1030.00 3090.00 cement mt 5.990 16500.00 98835.00 Concrete mixer hr 6.00 767.02 4602.12
Unskilled md 30.00 750.00 22500.00 40mm aggregate m3 5.400 2778.30 15002.82 Generator hr 6.00 937.37 5624.22
20mm aggregate m3 5.400 2963.52 16003.00 Formwork @3.75per cent on cost of
concrete i.e. cost of material, labour 3.75% of total cost 7271.54
10mm aggregate m3 2.700 2787.12 7525.22 and equipment
Coarse Sand m 3
6.750 2896.32 19550.16
Cost of water KL 3.000 260.00 780.00
Admixture @ 0.4 per cent of
395.34
cement/ as per mix design
Sub total of A = 25590.00 Sub total of B = 158091.54 Sub total of C = 17497.88
Sub total of A +B + C = 201179.42 Contractor's overhead expenses 15% = 30176.91 Unit Rate = 231356.33
rate per cum 15423.76
Description of works: Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications. RCC Grade M 25
Unit : 15m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.2E Skilled md 3.00 1030.00 3090.00 cement mt 6.050 16500.00 99825.00 Concrete mixer hr 6.00 767.02 4602.12
Unskilled md 30.00 750.00 22500.00 20mm aggregate m3 8.100 2963.52 24004.51 Generator hr 6.00 937.37 5624.22
10mm aggregate m3 5.400 15050.44 Formwork @3.75%per cent on cost of
2787.12 concrete i.e. cost of material, labour 3.75% of total cost 7328.46
Coarse Sand m3 6.750 2896.32 19550.16 and equipment
Cost of water KL 3.000 260.00 780.00
Admixture @ 0.4 per cent of
kg 399.30
cement/ as per mix design kg
Sub total of A = 25590.00 Sub total of B = 159609.41 Sub total of C = 17554.80
Sub total of A +B + C = 202754.21 Contractor's overhead expenses 15% = 30413.13 Unit Rate = 233167.34
rate per cum 15544.49
Description of works: Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications. PCC Grade M 30
Unit : 15m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.2F Skilled md 3.00 1030.00 3090.00 cement mt 6.080 16500.00 100320.00 Concrete mixer hr 6.00 767.02 4602.12
Unskilled md 30.00 750.00 22500.00 40mm aggregate m3 5.400 2778.30 15002.82 Generator hr 6.00 937.37 5624.22
20mm aggregate m3 5.400 2963.52 16003.00 Formwork @3.5per cent on cost of
concrete i.e. cost of material, labour 3.50% of total cost 6838.95
10mm aggregate m3 2.700 2787.12 7525.22 and equipment
Coarse Sand m 3
6.750 2896.32 19550.16
Cost of water KL 3.000 260.00 780.00
Admixture @ 0.4 per cent of
kg 401.28
cement/ as per mix design
Sub total of A = 25590.00 Sub total of B = 159582.48 Sub total of C = 17065.29
Sub total of A +B + C = 202237.77 Contractor's overhead expenses 15% = 30335.67 Unit Rate = 232573.44
rate per cum 15504.90
Description of works: Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications. RCC Grade M30
Unit : 15m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.2G Skilled md 3.00 1030.00 3090.00 cement mt 6.100 16500.00 100650.00 Concrete mixer hr 6.00 767.02 4602.12
Unskilled md 30.00 750.00 22500.00 20mm aggregate m3 8.100 2963.52 24004.51 Generator hr 6.00 937.37 5624.22
10mm aggregate m3 5.400 2787.12 15050.44 Formwork @3.5%per cent on cost of
concrete i.e. cost of material, labour 3.50% of total cost 6868.89
Coarse Sand m3 6.750 2896.32 19550.16 and equipment
Cost of water KL 3.000 260.00 780.00
Admixture @ 0.4 per cent of
402.60
cement/ as per mix design kg
Sub total of A = 25590.00 Sub total of B = 160437.71 Sub total of C = 17095.23
Sub total of A +B + C = 203122.94 Contractor's overhead expenses 15% = 30468.44 Unit Rate = 233591.38
rate per cum 15572.76
Description of works: Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications. RCC Grade M 35
Unit : 15m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.2H Skilled md 3.00 1030.00 3090.00 cement mt 6.330 16500.00 104445.00 Concrete mixer hr 6.00 767.02 4602.12
Unskilled md 30.00 750.00 22500.00 20mm aggregate m3 8.100 2963.52 24004.51 Generator hr 6.00 937.37 5624.22
10mm aggregate m3 5.400 2787.12 15050.44 Formwork @3%per cent on cost of
concrete i.e. cost of material, labour 3.00% of total cost 6001.92
Coarse Sand m3 6.750 2896.32 19550.16 and equipment
Cost of water KL 3.000 260.00 780.00
Admixture @ 0.4 per cent of
kg 417.78
cement/ as per mix design kg
Sub total of A = 25590.00 Sub total of B = 164247.89 Sub total of C = 16228.26
Sub total of A +B + C = 206066.15 Contractor's overhead expenses 15% = 30909.92 Unit Rate = 236976.07
rate per cum 15798.40
Description of works: Providing and laying ,fitting and placing Mild steel reinforcement complete in sub-structure as per drawing and Technical Specification.
Unit : 1 mt.
Spec. cl. No: 2014
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.60 Skilled md 4.00 1030.00 4120.00 Reinforcement t 1.150 84000.00 96600.00
Unskilled md 10.00 750.00 7500.00 Binding wire kg 9.000 92.00 828.00
11620.00 97428.00
Sub total of A = Sub total of B = Sub total of C = 0.00
Sub total of A +B + C = 109048.00 Contractor's overhead expenses 15% = 16357.20 Unit Rate = 125405.20
Description of works: Providing and laying ,fitting and placing Mild steel reinforcement complete in sub-structure as per drawing and Technical Specification.
Unit : 1 mt.
Spec. cl. No: 2014
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.60 Skilled md 4.00 1030.00 4120.00 Reinforcement t 1.150 84000.00 96600.00
Unskilled md 10.00 750.00 7500.00 Binding wire kg 9.000 92.00 828.00
Sub total of A = 11620.00 Sub total of B = 97428.00 Sub total of C = 0.00
Sub total of A +B + C = 109048.00 Contractor's overhead expenses 15% = 16357.20 Unit Rate = 125405.20
Description of works: Providing and laying, fitting and placing HYSD bar reinforcement in super-structure complete as per Drawing and Technical Specification (SS 2014).
Unit : 1 mt.
Spec. cl. No: 2014
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.90 Skilled md 4.00 1030.00 4120.00 Reinforcement t 1.100 79000.00 86900.00
Unskilled md 12.00 750.00 9000.00 Binding wire kg 8.000 92.00 736.00
Sub total of A = 13120.00 Sub total of B = 87636.00 Sub total of C = 0.00
Sub total of A +B + C = 100756.00 Contractor's overhead expenses 15% = 15113.40 Unit Rate = 115869.40
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings.(Class
F1 Finish) Using timber (soft wood ) Unit : 10 m2
Spec. cl. No: 1804,1805
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
18.1,a Skilled md 1.50 1030.00 1545.00 Planks 38mm thick. m3 0.42 700.00 294.00
Unskilled md 2.00 750.00 1500.00 struts, ballies, etc. m3 0.18 320.83 57.74
Nails,spikes,etc. kg 1.00 112.00 112.00
Sub total of A = 3045.00 Sub total of B = 463.74 Sub total of C = 0.00
Sub total of A +B + C = 3508.74 Contractor's overhead expenses 15% = 526.31 Rate (10 m2) = 4035.05
Unit Rate (1 m2) = 403.51
Description of works: Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings.
(Class F1 Finish) Using steel
Unit : 10 m2
Spec. cl. No: 1804,1805
Description of works: Using timber (soft wood ), Providing , Preparing and Installing form work including necessary supports and removing after completion for
walls.(Class F2 Finish), vertical plain surface Height upto 3 m
Unit : 10 m2
Spec. cl. No: 1804,1805
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Using timber (soft wood ), Providing , Preparing and Installing form work including necessary supports and removing after completion for
walls.(Class F2 Finish), vertical plain surface Height above 3 m to 6 m Unit : 10 m2
Spec. cl. No: 1804,1805
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Using Steel,Providing , Preparing and Installing form work including necessary supports and removing after completion for walls.(Class F2
Finish), vertical plain surface Unit : 10 m2
Spec. cl. No: 1804,1805 Height upto 3m
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
MS sheet 14 gauge & angle
Skilled md 1.60 1030.00 1648.00 kg 530.00 2.32 1229.60
18.2 b i stiffners
Unskilled md 2.20 750.00 1650.00 MS pipes dia. 40 mm. m 70.00 5.64 394.80
Clamps nos 40.00 30.00 1200.00
Nuts & bolts 6 mm dia. ( @approx.
nos 178.00 0.70 124.60
2 kg per 100 nos)
Sub total of A = 3298.00 Sub total of B = 2949.00 Sub total of C = 0.00
Sub total of A +B + C = 6247.00 Contractor's overhead expenses 15% = 937.05 Unit Rate : 7184.05
Unit Rate (1 m2) = 718.41
Description of works: Using Steel,Providing , Preparing and Installing form work including necessary supports and removing after completion for walls. (Class F2
Finish), vertical plain surface Height above 3 m to 6 m
Unit : 10 m2
Spec. cl. No: 1804,1805
Description of works: Using Steel, Providing , Preparing and Installing form work including necessary supports and removing after completion for walls. (Class F2
Finish), vertical plain surface Unit : 10 m2
Spec. cl. No: 1804,1805 Height above 6 m to 9 m
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
MS sheet 14 gauge & angle
Skilled md 2.30 1030.00 2369.00 kg 530.00 2.32 1229.60
18.2 b iii stiffners
Unskilled md 4.00 750.00 3000.00 MS pipes dia. 40 mm. m 112.00 5.64 631.68
Clamps nos 64.00 30.00 1920.00
Nuts & bolts 6 mm dia. ( @approx.
nos 178.00 0.70 124.60
2 kg per 100 nos)
Sub total of A = 5369.00 Sub total of B = 3905.88 Sub total of C = 0.00
Sub total of A +B + C = 9274.88 Contractor's overhead expenses 15% = 1391.23 Unit Rate : 10666.11
Unit Rate (1 m2) = 1066.61
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Using Steel, Providing , Preparing and Installing form work including necessary supports and removing after completion for walls. (Class F2
Finish), vertical plain surface Unit : 10 m2
Spec. cl. No: 1804,1805 Height above 9 m to 10m
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Description of works: Providing , Preparing and Installing form work including necessary supports and removing after completion for slab & beam structure.Class
F2 Finish, False work not included Using shuttering Ply
Unit : 10 m2
Spec. cl. No: 1804,1805
Description of works: Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design &
drawings as per specification, for RCC Beam Bridge Using steel,Height upto 3 m
Unit : 10 m2
Spec. cl. No: 1803
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design &
drawings as per specification,for RCC Beam Bridge Using steel,Height above 3 m to 6m
Unit : 10 m2
Spec. cl. No: 1803
Description of works: Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design &
drawings as per specification, for RCC Beam Bridge Using steel,Height above 6 m to 9m
Unit : 10 m2
Spec. cl. No: 1803
Description of works: Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design &
drawings as per specification, for RCC Beam Bridge Using steel, Height above 9 m Unit : 10 m2
Spec. cl. No: 1803
Department of Roads
Lalitpur
0
0
Rate Analysis for Lalitpur District FY 077/78
Description of works:
Painting Two Coats on Concrete Surfaces, Providing and Painting two coats after filling the surface with synthetic enamel paint in all shades on Unit : 1 0
concrete /plaster surfaces as per Drawing and Technical Specifications. sqm.
Spec. cl. No: 1501
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.40 Skilled md 3.000 1030.00 3090.00 Paint lit 6.000 509.00 3054.00
Add for scaffolding @ 1 per cent of
Unskilled md 2.000 750.00 1500.00 Labour cost where 45.90
required
Add @ 5 per cent cost of Labour
and Materials to prepare the surface
by filling minutes roughness on the
surface and priming the surface
before laying 2 coats of painting. 382.20
Description of works: Painting on Steel Surfaces, Providing and applying two coats of ready mix paint of approved brand on steel surface after through cleaning of surface to Unit : 20
give an even shade as per Drawing and Technical Specifications. sqm.
Spec. cl. No: 1501
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.50 Skilled md 1.000 1030.00 1030.00 Enamel paint lit 2.500 509.00 1272.50
Add @ 1 per cent on cost of
Unskilled md 1.000 750.00 750.00 Material for scaffolding 12.72
Department of Roads
Lalitpur
0
0
Rate Analysis for Lalitpur District FY 077/78
Description of works: Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on Bituminous Surface On smooth surface (similar to Asphalt
concrete and rigid pavement) Providing and laying of hot applied thermoplastic compound at least 2 mm thick including reflectorizing glass beads as per
DOR Traffic sign manual/ Specifications .The finished surface to be level, uniform and free from streaks and holes. Unit : 400 m2
Spec. cl. No: 1504
Description of works: Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on Bituminous Surface On rough surface ( similar to surface
dressing) Providing and laying of hot applied thermoplastic compound at least 2 mm thick including reflectorizing glass beads as per DOR Traffic sign
manual/ Specifications .The finished surface to be level, uniform and free from streaks and holes. Unit : 400 m2
Spec. cl. No: 1504
Skilled md 2.000 1030.00 2060.00 Hot applied thermoplastic ltr 1200.000 562.00 674400.00
Road marking machine ( boiler
hr 10.00 1005.80 10058.00
15.9 ii compound + Applicator + Template)
Unskilled md 4.000 750.00 3000.00 Reflectorizing glass beads kg 150.000 0.00 0.00 Tractor-trolley hr 10.00 1078.30 10783.00
Unskilled md 1500.00
2.000 750.00
Sub total of A = 3560.00 Sub total of B = 254.50 Sub total of C = 0.00
Sub total of A +B + C = 3814.50 Contractor's overhead expenses 15% = 572.18 Unit Rate = 4386.68
Rate/cm 2.741
Department of Roads
Lalitpur
0
0
Rate Analysis for Lalitpur District FY 077/78
Description of works: Metal Beam Crash Barrier || Type - A, "W" : Metal Beam Crash Barrier || Providing and erecting a "W" metal beam crash barrier comprising of 3 mm
thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m center to
center, 1.8 m high, 1.1 m below ground/road level metal beam rail to be fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm Unit : 40 m
Spec. cl. No: 1509
long complete as per Drawing and Technical Specifications.
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.14.A Hot dip galvanized Corrugated 563.61 149.50 84259.70 0.075 1078.30 80.8725
Skilled md 2.000 1030.00 2060.00 thrie beam sheet 3 mm thick kg Tractor-trolley hour
Hot dip galvanized Channel post 695.52 149.50 103980.24
Unskilled md 2.000 750.00 1500.00 150 x 75 , 5 mm kg
Hot dip galvanized Spacer Channel
127.51 149.50 19062.75
150 x 75 x 5 mm , kg
M 20 grade concrete cum 0.99 14327.09 14183.82
E/W 25
Add excavation
per cent for postcost of
of the cum 0.99 808.45 800.37
Material for fabrication, nuts, bolts
and washers etc.) 55571.72
Department of Roads
Lalitpur
0
0
Rate Analysis for Lalitpur District FY 077/78
Description of works: Metal Beam Crash Barrier || Type - B, "THRIE" : Metal Beam Crash Barrier || Providing and erecting a "Thrie" metal beam crash barrier comprising of
3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m
center to center, 2.1 m high with 1.3 m below ground level, metal beam rail to be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, Unit : 40 m
Spec. cl. No: 1509
546 mm long complete as per Drawing and Technical specifications.
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.14.B Hot dip galvanized Corrugated 149.50 136521.91 0.075 1078.30 80.8725
Skilled md 2.000 1030.00 2060.00 thrie beam sheet 3 mm thick kg 913.190 Tractor-trolley hour
Hot dip galvanized Channel post 121310.28
Unskilled md 2.000 750.00 1500.00 150 x 75 , 5 mm kg 811.440 149.50
Hot dip galvanized Spacer Channel
20577.18
150 x 75 x 5 mm , kg 137.640 149.50
M 20 grade concrete cum 1.130 14327.09 16189.61
E/W 25
Add excavation
per cent for postcost of
of the cum 1.130 808.45 913.55
Material for fabrication, nuts, bolts
and washers etc.) 73878.13
14.10
Unskilled md 16.00 750.00 12000.00 coarse sand 30 percent m3 1.200 2896.32 3475.58 Concrete Mixer hr 12.000 767.02 9204.24
Cement mt 0.520 16500.00 8580.00
Water Kl 0.200 260.00 52.00
Sub total of A = 15090.00 Sub total of B = 447643.58 Sub total of C = 18355.62
Sub total of A +B + C = 481089.20 Contractor's overhead expenses 15% = 72163.38 Unit Rate = 553252.58
Rate/m 1383.13
Description of works: Providing and laying of precast / cast in situ 50 mm (M20/20) thick cement concrete interlocking block on 12 mm thick 1: 3 cement sand mortar over
the prepared base, all complete as per Drawing and Technical Specifications. Unit : 10m2
Spec. cl. No: 1401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Precast / cast in situ concrete block of M
20/20 ( 50 mm CC
Skilled md 1.50 1030.00 1545.00 Block) m2 11.000 516.00 5676.00 0.00
14.20
Unskilled md 4.00 750.00 3000.00 Cement mt 0.070 16500.00 1155.00 0.00
Coarse sand m3 0.130 2896.32 376.52 0.00
water Kl 0.020 260.00 5.20 0.00
Sub total of A = 4545.00 Sub total of B = 7212.72 Sub total of C = 0.00
Sub total of A +B + C = 11757.72 Contractor's overhead expenses 15% = 1763.66 Unit Rate = 13521.38
Rate/ sqm 1352.138
Description of works: Providing and laying flat brick over 60 mm thick sand bed in footpath including excavation sand bedding all complete as per specification. Unit =
sqm (For 20 sqm) (1403) Unit : 20m2
Spec. cl. No: 1403
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
14.5,B Skilled md 1.50 1030.00 1545.00 Bricks no 750.000 14.00 10500.00 0.00
Unskilled md 4.00 750.00 3000.00 Sand m3 1.400 2896.32 0.00
0.00
0.00
Sub total of A = 4545.00 Sub total of B = 10500.00 Sub total of C = 0.00
Sub total of A +B + C = 15045.00 Contractor's overhead expenses 15% = 2256.75 Unit Rate = 17301.75
Rate/ sqm 865.0875
Description of works: Providing and applying tack coat with hot Bitumen by Manual Means at the specified rate the prepared surfaces including cleaning as per Technical
Speciation . Unit : 1000lit.
Spec. cl. No: 1302,1302
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.2B Skilled md 3.0000 1030.00 3090.00 Bitumen Tonne 1.1000 69000.00 75900.00 Tractor hr 6.0000 1078.30 6469.80
Unskilled md 40.0000 750.00 30000.00 Bitumen sprayer hr 6.0000 982.71 5896.26
Boiler hr 8.0000 931.18 7449.44
Generator hr 8.0000 937.37 7498.96
Sub total of A = 33090.00 Sub total of B = 75900.00 Sub total of C = 27314.46
Sub total of A +B + C = 136304.46 Contractor's overhead expenses 15% = 20445.67 Unit Rate = 156750.13
Rate per liter 156.75
Description of works: Providing and applying prime coat with hot bitumen MC 30/70 (including cutter)on prepared surface of granular base including cleaning of road surface Unit : 5000
Spec. cl. No: 1302,1302
and spraying at specified rate by mechanical means as per Technical specification. lit.
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Bitumen
Skilled md 3.0000 1030.00 3090.00 Tonne 5.2500 78000.00 409500.00 Mechanical broom hr 8.0000 1984.25 15874.00
13.1A (MC30/MC70)
Unskilled md 50.0000 750.00 37500.00 cost of water KL 10.0000 260.00 2600.00 Air compresser hr 8.0000 1415.10 11320.80
Bitumen distributor hr 6.0000 4330.70 25984.20
Boiler hr 8.0000 931.18 7449.44
Generetor hr 8.0000 937.37 7498.96
Sub total of A = 40590.00 Sub total of B = 412100.00 Sub total of C = 68127.40
Sub total of A +B + C = 520817.40 Contractor's overhead expenses 15% = 78122.61 Unit Rate = 598940.01
Rate per ltr 119.79
Description of works: Providing and laying Bituminous concrete/ Asphalt concrete using crushed aggregates of specified grading, premixed with bituminous binder and filler as Unit : 95.5
per Drawing and Technical Specifications m3
Spec. cl. No: 1307,1308, 13
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.60 Skilled md 5.00 1030.00 5150.00 Bitumen tonne 12.940 78000.00 1009320.00 Batch mix HMP hr 6.000 64921.00 389526.00
Unskilled md 15.00 750.00 11250.00 aggregate I-19mm Paver hr 6.000 4733 28398.00
20-10mm m3 49.480 2963.52 146634.96 Generetor hr 6.000 937.37 5624.22
10-5mm m3 32.520 2787.12 90637.14 Smooth wheeled roller hr 12.000 1589.46 19073.52
5mm and below m3 56.550 2667.17 150828.46 Pneumatic roller hr 6.000 3245.43 19472.58
filler tonne 2.830 728.48 2061.59
Sub total of A = 16400.00 Sub total of B = 1399482.15 Sub total of C = 462094.32
Sub total of A +B + C = 1877976.47 Contractor's overhead expenses 15% = 281696.47 Unit Rate = 2159672.94
rate per m3 22614.38
Description of works: Providing and laying 'Dense Bituminous Macadam' using crushed aggregates of specified grading( Grading -I 40mm nominal size), premixed with Unit : 97.5
bituminous binder as filler as per Drawing and Technical Specifications (SS 1308). m3
Spec. cl. No: 1308
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.50 Skilled md 5.00 1030.00 5150.00 Bitumen tonne 9.560 78000.00 745680.00 Batch Mix HMP hr 6.000 64921.00 389526.00
Unskilled md 16.00 750.00 12000.00 aggregate I-19mm Paver finisher hr 6.000 4733 28398.00
37.5-25mm m3 31.600 2778.30 87794.28 Generator hr 6.000 937.37 5624.22
25-10mm m3 18.670 2963.52 55328.91 Pneumatic roller hr 6.000 3245.43 19472.58
10-4.75mm m3 27.290 2787.12 76060.50 Vibratory roller hr 6.000 2377.28 14263.68
4.75 below m3 63.200 2667.17 168565.14 Smooth wheeled tandom roller hr 6.000 1589.46 9536.76
filler tonne 4.310 728.48 3139.74
Sub total of A = 17150.00 Sub total of B = 1136568.57 Sub total of C = 466821.24
Sub total of A +B + C = 1620539.81 Contractor's overhead expenses 15% = 243080.97 Unit Rate = 1863620.78
rate per m3 19114.06
13.9 (A) Skiilled md 8.00 1030.00 8,240.00 Bitumen tonne. 0.73 78,000.00 56,940.00 Mixer hr. 4.00 1,000.00 4000
Total Labour(A) NRs. 23990.00 Material(B) NRs. 96,947.52 Equipment( C ) NRs. 10903.64
89 F.Y. 076/77
Item no. 13.9 -B(i) Description:- Providing and laying open-graded premix carpet of 20mm thickness of 13.2mm to 5.6mm aggregate as wearing course (Mechanically) on a previously prepared base as per Drawing and Technical Specifications
(SS 1311).
Unit Cu.m. Analyzed for 80 Cu.m.
Labour Material Equipment
Item No.
Type Unit Qty Rate Amount Type Unit Qty Rate Amount Type Unit Qty Rate Amount
13.9 -B(i) Skiilled md 5.00 1030.00 5,150.00 Bitumen tonne. 5.84 78,000.00 455,520.00 Hot mix plant hr. 6.00 14,122.00 84732
Total Labour(A) NRs. 16350.00 Material(B) NRs. 775580.16 Equipment( C ) NRs. 128290.98
Description of works: Providing and laying granular sub-base on prepared surface, mixing at OMC, and compacting to achieve the desired density, complete as per Drawing and
Spec. cl. No: 1201 Technical Specifications. By manual means. Unit : 200 m3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.1B Skilled md 2.0000 1030.00 2060.00 Sub base material S1 or S2 type cu.m. 256.00 1766.00 452096.00 Vibrator Roller hr 6.0000 2377.28 14263.68
Unskilled md 60.0000 750.00 45000.00 Cost of water KL 23.00 260.00 5980.00
Crusher Run Macadam sub-base. Providing and laying Crusher Run Macadam on a prepared surface, spreading and mixing , watering and compacting to form
a layer of sub-base/Base course as per Drawing and Technical Specifications. By Mix in palce method. ii) for 63mm maximum size Unit : 360 m3
Spec. cl. No: 1204
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.7 Aii Skilled md 3.00 1030.00 3090.00 63mm-45mm cu.m. 157.46 2225.16 350373.69 Vibrator Rolller hr 6.00 2377.28 14263.68
Unskilled md 14.00 750.00 10500.00 22.5mm-5.6mm cum 151.06 2225.16 336132.66 Motor Grader hr 6.00 3535.95 21215.70
below 5.6 cum 166.68 2225.16 370889.66
Cost of water KL 36.00 260.00 9360.00
Sub total of A = 13590.00 Sub total of B = 1066756.01 Sub total of C = 35479.38
Sub total of A +B + C = 1115825.39 Contractor's overhead expenses 15% = 167373.81 Unit Rate = 1283199.20
Rate /cum 3564.44
Description of works: Crusher Run Macadam Base. Providing and laying Crusher Run Macadam on a prepared surface, spreading and mixing , watering and compacting to form a
layer of sub-base/Base course as per Drawing and Technical Specifications. By Mix in palce method. ii) for 45mm maximum size Unit : 360 m3
Spec. cl. No: 1204
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.7 Aii Skilled md 3.00 1030.00 3090.00 45mm-22.5mm cu.m. 24.12 2778.30 67012.59 Vibrator Rolller hr 6.00 2377.28 14263.68
Unskilled md 14.00 750.00 10500.00 22.4 mm - 5.6mm cum 237.60 2963.52 704132.35 Motor Grader hr 6.00 3535.95 21215.70
below 5.6 cum 213.48 2667.17 569387.45
Cost of water KL 36.00 260.00 9360.00
Sub total of A = 13590.00 Sub total of B = 1349892.39 Sub total of C = 35479.38
Sub total of A +B + C = 1398961.77 Contractor's overhead expenses 15% = 209844.27 Unit Rate = 1608806.04
Rate /cum 4468.91
Description of works: Scarifying the existing granular road surface by Mannual means to a depth of 50 mm and disposal of scarified Material with all lifts and
leads within Right of way as per Drawing and Technical Specifications. Unit : 600m2
Spec. cl. No: 1003
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.1 B Skilled md 1.00 1030.00 1030.00
Unskilled md 12.00 750.00 9000.00
Remarks
In case Material is not to be reused at site, transportation cost catered above for disposal may be added.
Description of works: Scarifying the existing road surface to a depth of 50 mm and disposal of scarified Material with in all lifts and lead as per Drawing and
Technical Specifications. Lead upto 30m. Unit : 600m2
Spec. cl. No: 1003
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.2 A Skilled md 1.00 1030.00 1030.00 Tractor with ripper hr 6.00 1111.30 6667.80
Unskilled md 6.00 750.00 4500.00
Sub total of A = 5530.00 Sub total of B = 0.00 Sub total of C = 6667.80
Sub total of A +B + C = 12197.80 Contractor's overhead expenses 15% = 1829.67 Unit Rate = 14027.47
Rate per m2 23.38
Description of works: Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified Material with in all lifts and lead as per
Drawing and Technical Specifications. Unit : 3000m2
Spec. cl. No: 1003
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.2 B Skilled md 1.00 1030.00 1030.00 Tractor with ripper hr 6.00 1111.30 6667.80
Unskilled md 6.00 750.00 4500.00 Loader hr 6.00 2888.26 17329.56
Tipper hr 6.000 1415.26 8491.56
Sub total of A = 5530.00 Sub total of B = 0.00 Sub total of C = 32488.92
Sub total of A +B + C = 38018.92 Contractor's overhead expenses 15% = 5702.84 Unit Rate = 43721.76
Rate per m2 14.57
Description of works: Compacting original ground supporting sub-grade. Loosening of the ground upto a level of 500 mm below the sub-grade level, watered,
graded and compacted in layers as per drawwings and technical specifications. Unit : 600 m3
Spec. cl. No: 1003,1005
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.4 case I Skilled md 1.00 1030.00 1030.00 Water KL 24.00 260.00 6240.00 Motor Grader hr 6.00 3535.95 21215.70
Unskilled md 5.00 750.00 3750.00 Vibratory Roller hr 12.000 2377.28 28527.36
Tractor with ripper hr 12.00 1111.30 13335.60
Sub total of A = 4780.00 Sub total of B = 6240.00 Sub total of C = 63078.66
Sub total of A +B + C = 74098.66 Contractor's overhead expenses 15% = 11114.80 Unit Rate = 85213.46
Rate/cum 142.02
(avg. height taken of 50cm & 0cm) Rate/sqm 35.51
Description of works: Providing and laying of hand pack Stone soling with 150 to 200 mm thick stones and packing with smaller stone on prepared surface as per
Drawing and Technical Specifications. Unit : 5 m3
Spec. cl. No:
. Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.8 Skilled md 6.00 1030.00 6180.00 stone cum 6.00 2540.16 15240.96 0.00
Unskilled md 12.00 750.00 9000.00 0.00
0.00
Sub total of A = 15180.00 Sub total of B = 15240.96 Sub total of C = 0.00
Sub total of A +B + C = 30420.96 Contractor's overhead expenses 15% = 4563.14 Unit Rate = 34984.10
Rate/cum 6996.82
Description of works: Roadway Excavation in all types of soil by Manual Means as per drawing and technical specification, including removal of stumps and other
deleterious matter, with all lifts and lead as per Drawing and instruction of the Engineer. Unit : 12.0m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No. 9.1.I.A
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled md 1.000 1030.000 1030.00
Unskilled md 8.000 6000.00 Doko, Thunse etc. Tools and plant of L.C. 210.90
750.00 3.00%
Sub total of A = 7030.00 Sub total of B = 0.00 Sub total of C = 210.90
Sub total of A +B + C = 7240.90 Contractor's overhead expenses 15% = 1086.14 Unit Rate = 8327.04
Rate per m3 693.92
Description of works: Road way Excavation in all types of soil by Mechanical Means as per Drawing and technical specifications including removal of stumps and other Unit :
deleterious matter, all lifts and lead as per Drawing and instruction of the Engineer. 360.0m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No. 9.1.I.B
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled md 1.000 1030.000 1030.00
Unskilled md 3.000 750.00 2250.00 Hydraulic Excavator hr 6.00 3581.85 19680.00
Sub total of A = 3280.00 Sub total of B = 0.00 Sub total of C = 19680.00
Sub total of A +B + C = 22960.00 Contractor's overhead expenses 15% = 3444.00 Unit Rate = 26404.00
Rate per m3 73.34
Description of works: Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter
and backfilling with approved Material as per Drawing and Technical Specifications. Ordinary soil by Manual means upto 3m depth.
Unit : 10 m3
Spec. cl. No: 907
Description of works: Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter
and backfilling with approved Material as per Drawing and Technical Specifications. Ordinary Rock (not requiring blasting) by Manual means upto
3m depth Unit : 10 m3
Spec. cl. No: 907
Description of works: Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter
and backfilling with approved Material as per Drawing and Technical Specifications. Ordinary rock (not requiring blasting) by Mechanical means
Unit : 90 m3
Spec. cl. No: 907 upto 3m depth.
Description of works: Construction of Embankment with Material obtained from Borrow pits Providing, laying, spreading and compacting embankment with borrow
material as per Drawing and Technical Specifications. Unit : 300 m3
Spec. cl. No: 909, 910
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.8 Unskilled md 4.00 750.00 3000.00 Water KL 72.0 260.00 18720.00 Hydraulic excavator hr 6.000 3581.85 21491.10
Skilled md 1.00 1030.00 1030.00 Borrowpit material m3 360.00 73.34 26402.40 Tractor with rotavator hr 12.000 1101.3 13215.60
Dozer hr 3.000 5909.56 17728.68
Motor grader hr 3.000 3535.95 10607.85
Vibrator Roller hr 6.000 2377.28 14263.68
Sub total of A = 4030.00 Sub total of B = 45122.40 Sub total of C = 77306.91
Sub total of A +B + C = 126459.31 Contractor's overhead expenses 15% = 18968.90 Unit Rate = 145428.21
rate per cum 484.76
Description of works: Construction of Embankment with Material Deposited from Roadway Cutting Providing, laying, spreading and compacting embankment with
roadway cutting material and compact to the required density as per Drawing and Technical Specifications. (With machine)
Unit : 300 m3
Spec. cl. No: 909, 910
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.9 B Unskilled md 10.00 750.00 7500.00 Water KL 72.0 260.00 18720.00 Dozer hr 6.000 5909.56 35457.36
Skilled md 1.00 1030.00 1030.00 Motor grader hr 6.000 3535.95 21215.70
Vibrator Roller hr 6.000 2377.28 14263.68
Sub total of A = 8530.00 Sub total of B = 18720.00 Sub total of C = 70936.74
Sub total of A +B + C = 98186.74 Contractor's overhead expenses 15% = 14728.01 Unit Rate = 112914.75
rate per cum 376.38
Description of works: Providing suitable material and Back filling with Granular Material behind abutment, wing wall and return wall complete as per Drawing and
Technical Specifications. Unit : 10 m3
Spec. cl. No: 908
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.11 A Unskilled md 5.00 750.00 3750.00 Water KL 1.0 260.00 260.00 Plate Compactor/power rammer hr 2.500 290.51 726.27
Skilled md 0.20 1030.00 206.00 Granular material m3 11.00 510.00 5610.00
Description of works: Backfilling in layers in foundation pits, trenches with locally available material etc. including compaction and watering etc all complete (908 ) .
Unit : 10 m3
Spec. cl. No: 908
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.11 C Unskilled md 5.00 750.00 3750.00 Water KL 1.0 260.00 260.00 Tamping @3% of labor cost 118.68
compensation of
206.00 locally available m3 267.00 3204.00
Skilled md 0.20 1030.00 material 12.00
Description of works: Providing, jointing and laying HDPE pipes with or without collar etc. complete in place as per Drawing and Technical Specifications. a) Unit : 50
200 mm outer dia. m
Spec. cl. No: 701
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
HDPE pipe / HDPE
7.1 A Skilled md 3.0 1030.00 3090.00 m 50.00 2014.00 100700.00 Generator hr. 6.00 117.31 703.86
pipe with collars
Unskilled md 3.0 750.00 2250.00 Screw Jack hr. 6.00 15.00 90.00
electric heating plate hr. 6.00 25.00 150.00
Add 3% of labour cost for other
160.20
T&P
Sub total of A = 5340.00 Sub total of B = 100700.00 Sub total of C = 1104.06
Sub total of A +B + C = 107144.06 Contractor's overhead expenses 15% = 16071.61 Rate (50 m)= 123215.67
Rate (1 m ) 2464.31
Description of works: Providing, jointing and laying HDPE pipes with or without collar etc. complete in place as per Drawing and Technical Specifications. a) Unit : 50
Spec. cl. No: 701 200mm dia. m
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
HDPE pipe / HDPE
7.1 A Skilled md 3.0 1030.00 3090.00 m 50.00 545.00 27250.00 Generator hr. 6.00 937.37 5624.22
pipe with collars
Unskilled md 3.0 750.00 2250.00 Screw Jack hr. 6.00 15.00 90.00
electric heating plate hr. 6.00 25.00 150.00
Add 3% of labour cost for other
160.20
T&P
Sub total of A = 5340.00 Sub total of B = 27250.00 Sub total of C = 6024.42
Sub total of A +B + C = 38614.42 Contractor's overhead expenses 15% = 5792.16 Rate (50 m)= 44406.58
Rate (1 m ) 888.13
Description of works: Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying Reinforced cement concrete
NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications. 300 mm Unit : 12.5
internal dia(with socket system). rm
Spec. cl. No: 701
Description of works: Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying Reinforced cement concrete
NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications. 450 mm Unit : 12.5
Spec. cl. No: 701
internal dia(with socket system). rm
Description of works: Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying Reinforced cement concrete
NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications. 600 mm Unit : 12.5
Spec. cl. No: 701 internal dia (with socket system). rm
Description of works: Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying Reinforced cement concrete
NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications. 900 mm Unit : 12.5
Spec. cl. No: 701
internal dia (with socket system). rm
Description of works: Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts Providing and Laying Reinforced cement concrete
NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications. 1200 mm Unit :
Spec. cl. No: 701 internal dia (with socket system). 12.5rm
Description of works: Clearing Grass and Removal of Rubbish and Dressing and levelling the construction surface Clearing grass/ top soil and Unit :
removal meters outside the periphery of the area , including cutting and filling of small undulation. By Manual Means 10000 m2
Spec. cl. No: 201
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
2.30 Unskilled md 100.0 750.00 75000.00
Sub total of A = 75000.00 Sub total of B = 0.00 Sub total of C = 0.00
Sub total of A +B + C = 75000.00 Contractor's overhead expenses 15% = 11250.00 unit rate= 86250.00
Rate/sqm 8.63
Description of works: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement
concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of
unserviceable Material and stacking the serviceable Material with all lifts and lead of 1000 meters Unit :
Spec. cl. No: 202 Lime /Cement Concrete, By Manual Means( Lime Concrete, cement concrete grade M-10 and below) 20cum
Description of works: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement
concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of Unit :
unserviceable Material and stacking the serviceable Material with all lifts and lead of 1000 meters 10cum
Spec. cl. No: 202
Lime /Cement Concrete, By Mechanical Means( Pre-stressed / Reinforced cement concrete grade M-20 & above )
Labour (A) Material (B) Equipment (C)
Norms No.2.4iii
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled md 3.000 1030.00 3090.00 Tractor-Trolley hr 6.00 1110 6660.00
Technicians md 1.000 1030.00 1030.00
Unskilled md 30.000 750.00 22500.00
Sub total of A = 26620.00 Sub total of B = 0.00 Sub total of C = 6660.00
Sub total of A +B + C = 33280.00 Contractor's overhead expenses 15% = 4992.00 Unit Rate = 38272.00
Rate per Rm 3827.20
Description of works: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement
concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of
unserviceable Material and stacking the serviceable Material with all lifts and lead of 1000 meters Unit :
Spec. cl. No: 202 Lime /Cement Concrete, By Mechanical Means( Pre-stressed / Reinforced cement concrete grade M-20 & above ) 10cum
Norms No.2.4II,ii
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Description of works: Removal of Telephone / Electric Poles and Lines. Removal of telephone / Electric poles including excavation and dismantling
of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to a lead of
Unit : 30
1000 metres and stacking the serviceable and unserviceable Material separately.
Spec. cl. No: 202 nos
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Providing and laying Brick Masonry Work in Cement mortar in Foundation / structure complete excluding Pointing and Plastering, as per Drawing and
Technical Specifications.Cement sand mortar (1:4) Unit : 5 m3
Spec. cl. No: 2500
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
25.1C Skilled md 6.00 1030.00 6180.00 Bricks 1st class no 2800 #REF! #REF! Tools and Plants 0.00
Unskilled md 12.00 750.00 9000.00 Cement t 0.48 #REF! #REF!
Sand m3 1.35 #REF! #REF!
water KL 0.1 260.00 26.00
Sub total of A = 15180.00 Sub total of B = #REF! Sub total of C = 0.00
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Rate/cum #REF!
Description of works: Providing and laying Brick Masonry Work in Cement mortar in Foundation / structure complete excluding Pointing and Plastering, as per Drawing and
Technical Specifications.Cement sand mortar (1:4) Unit : 5 m3
Spec. cl. No: 2500
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
25.1C Skilled md 6.00 1030.00 6180.00 Bricks 1st class no 2800 #REF! #REF! Tools and Plants 0.00
Unskilled md 12.00 750.00 9000.00 Cement t 0.48 #REF! #REF!
Sand m3 1.35 #REF! #REF!
water KL 0.1 260.00 26.00
Sub total of A = 15180.00 Sub total of B = #REF! Sub total of C = 0.00
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Description of works: Providing and applying 20mm thick cement plaster including mortar mixing, scaffolding, curing etc. complete as per specification lead 30 m (manual mixing)
Unit : 100 m2
Spec. cl. No: 2502,2510
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
25.06.b Skilled md 14.00 1030.00 14420.00 Cement t 0.8 #REF! #REF! Tools and Plants 3.00% 767.02 23.01
Unskilled md 19.00 750.00 14250.00 Sand m3 2.2 #REF! #REF!
water lit 270 260.00 70200.00
Sub total of A = 28670.00 Sub total of B = #REF! Sub total of C = 23.01
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Rate(1m2) = #REF!
Providing, laying and levelling of dry stone soling works in the foundation all complete. Unit : 1 m3
Description of works:
Unit : 1 m3
Spec. cl. No: Norms 2041(1st ammendment 2050)
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Providing and laying dry stone masonry (coursed rubble) including dressing etc. complete as per specification, lead 30m.
Unit : 1 m3
Spec. cl. No: 2602,2603,2608
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.01 Skilled md 1.25 1030.00 1287.50 Stone m3 1.15 #REF! #REF! Tools & Plant 3% of L.C. 83.62
Unskilled md 2.00 750.00 1500.00
Sub total of A = 2787.50 Sub total of B = #REF! Sub total of C = 83.62
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(3)] including scaffolding, curing, preparation of mortar etc. complete,
masoned height 0-5m, lead 30m (machine mixing), mortar 35% Unit : 1 m3
Spec. cl. No: 2602,2603,2607
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.03.a Skilled md 1.50 1030.00 1545.00 Diesel lit 1.000 85.40 85.40 Concrete mixer (0.28/0.2 m3) hr. 0.15 767.02 115.05
Unskilled md 3.50 750.00 2625.00 Cement t 0.190 #REF! #REF! Tools & Plant 3% of L.C. 125.1
Sand m3 0.400 #REF! #REF! Quality Control 1.50% of T.C. #REF!
Stone m3 1.150 #REF! #REF!
water lit 120.000 260 31200.00
Sub total of A = 4170.00 Sub total of B = #REF! Sub total of C = #REF!
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Description of works: Providing and laying of Stone Masonry Work in Cement Mortar 1:4 in Foundation complete as per Drawing and Technical Specifications.
Unit : 5 m3
Spec. cl. No: 2602,2603,2607
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Concrete mixer or Other tools 5%
Skilled md 7.00 1030.00 7210.00 Cement t 0.620 #REF! #REF! 5% of L.C. 885.50
26.3B of labour cost
Unskilled md 14.00 750.00 10500.00 Sand m3 1.740 #REF! #REF!
Stone m3 5.750 #REF! #REF!
water KL 1.00 260 260.00
Sub total of A = 17710.00 Sub total of B = #REF! Sub total of C = 885.50
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Rate/cum #REF!
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(6)] including scaffolding, curing, preparation of mortar etc. complete,
masoned height 0-5m, lead 30m (machine mixing), mortar 35% Unit : 1 m3
Spec. cl. No: 2602,2603,2607
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(6)] including scaffolding, curing, preparation of mortar etc. complete,
masoned height 0-5m, lead 30m (manual mixing), mortar 35% Unit : 1 m3
Spec. cl. No: 2607
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.04.c Skilled md 1.50 1030.00 1545.00 Cement t 0.105 #REF! #REF! Tools & Plant 3% of L.C. 147.6
Unskilled md 4.50 750.00 3375.00 Sand m3 0.500 #REF! #REF! Quality Control 1.50% of T.C. #REF!
Stone m3 1.150 #REF! #REF!
water lit 70.000 260 18200.00
Sub total of A = 4920.00 Sub total of B = #REF! Sub total of C = #REF!
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Description of works: Providing and laying Coursed rubble stone masonry in cement mortar [ cement(1) : sand(3)] including scaffolding, curing, preparation of mortar etc. complete,
masoned height 0-5m, lead 30m (machine mixing), mortar 30% Unit : 1 m3
Spec. cl. No: 2600
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.05.a Skilled md 2.00 1030.00 2060.00 Diesel lit 1.000 85.40 85.40 Concrete mixer (0.28/0.2 m3) hr. 0.15 767.02 115.05
Unskilled md 3.50 750.00 2625.00 Cement t 0.190 #REF! #REF! Tools & Plant 3% of L.C. 140.55
Sand m3 0.400 #REF! #REF! Quality Control 1.50% of T.C. #REF!
Stone m3 1.150 #REF! #REF!
water lit 120.000 260 31200.00
Sub total of A = 4685.00 Sub total of B = #REF! Sub total of C = #REF!
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Providing and laying Coursed rubble stone masonry in cement mortar [ cement(1) : sand(4)] including scaffolding, curing, preparation of mortar etc. complete,
masoned height 0-5m, lead 30m (machine mixing), mortar 30% Unit : 1 m3
Spec. cl. No: 2600
Description of works: Providing and laying Coursed rubble stone masonry in cement mortar [ cement(1) : sand(6)] including scaffolding, curing, preparation of mortar etc. complete,
masoned height 0-5m, lead 30m (machine mixing), mortar 30% Unit : 1 m3
Spec. cl. No: 2600
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Providing, mixing, and Pointing cement mortar over rubble masonry works in cement mortar [ cement(1) : sand(1)] including scaffolding, curing, preparation of
mortar etc. complete, masoned height 0-5m, lead 30m (machine mixing). Unit : 100 m2
Spec. cl. No: 2602,2603,2510
Description of works: Providing, mixing, and Pointing cement mortar over rubble masonry works in cement mortar [ cement(1) : sand(2)] including scaffolding, curing, preparation of
mortar etc. complete, masoned height 0-5m, lead 30m (machine mixing). Unit : 100 m2
Spec. cl. No: 2602,2603,2510
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Providing, mixing, and Pointing cement mortar over rubble masonry works in cement mortar [ cement(1) : sand(3)] including scaffolding, curing, preparation of
mortar etc. complete, masoned height 0-5m, lead 30m (machine mixing). Unit : 100 m2
Spec. cl. No: 2602,2603,2510
Description of works: Removal of old paints by sand blasting, cleaning and repairing of metal surfaces for the application of new paints as per specification.
Unit : 1 m2
Spec. cl. No: 2713
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
27.07 Skilled md 0.12 1030.00 123.60 Diesel lit 4.0 85.40 341.60 Air compressor hr. 0.32 #REF! #REF!
Unskilled md 0.08 750.00 60.00 Sand (1.6 mm to 600 micro mm) m3 0.04 #REF! #REF! Blasting machine hr. 0.32 #NAME? #NAME?
Scaffolding 10.00% of T.C. #REF!
Sub total of A = 183.60 Sub total of B = #REF! Sub total of C = #REF!
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Description of works: Double coat whitewash on new surface including supply of materials all complete
Spec. cl. No:
Unit : 100 m2
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
27.00 old 13-1-b Unskilled md 1.10 750.00 825.00 lime kg 22.000 #REF! #REF!
Skilled md 1.50 1030.00 1545.00 Gum kg 0.880 #REF! #REF!
27.00 old 15-16-b Unskilled md 2.00 750.00 1500.00
Sub total of A = 3870.00 Sub total of B = #REF! Sub total of C = 0.00
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Rate = #REF!
Unit Rate (1 m2) #REF!
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Single coat whitewash on old surface including supply of materials all complete
Spec. cl. No:
Unit : 100 m2
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
27.00 old 13-2 Unskilled md 0.70 750.00 525.00 Lime kg 10.000 #REF! #REF!
Skilled md 0.80 1030.00 824.00 Gum kg 0.400 #REF! #REF!
Cleaning Unskilled md 2.00 750.00 1500.00
Sub total of A = 2849.00 Sub total of B = #REF! Sub total of C = 0.00
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Rate = #REF!
Unit Rate (1 m2) #REF!
Description of works: Single coat enamel paint/ readymade emulsion paint including supply of materials all complete.
Spec. cl. No:
Unit : 100 m2
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
27.00 old 15 Unskilled md 2.00 750.00 1500.00 Enamel paint kg 16.00 509.00 8144.00
Skilled md 5.00 1030.00 5150.00 Primer kg 8.10 #REF! #REF!
Unskilled md 3.00 750.00 2250.00
Skilled md 3.00 1030.00 3090.00
Sub total of A = 11990.00 Sub total of B = #REF! Sub total of C = 0.00
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Rate = #REF!
Unit Rate (1 m2) #REF!
Description of works: Restoration of rain cuts in embankment slopes including watering and compaction etc. all complete lead 10 m.
Unit : 1 m3
Spec. cl. No: 2902
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
29.01 Skilled md 0.10 1030.00 103.00 Tools 3.00% of L.C. 19.96
Unskilled md 0.75 750.00 562.50
Sub total of A = 665.50 Sub total of B = 0.00 Sub total of C = 19.96
Sub total of A +B + C = 685.46 Contractor's overhead expenses 15% = 102.82 Unit Rate = 788.28
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Maintenance of earthen shoulders by making irregularities even to the required level including watering and compaction etc. all complete lead 10m.
Unit : 1 m2
Spec. cl. No: 2903
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
29.02 Skilled md 0.02 1030.00 20.60 Tools 3.00% of L.C. 5.11
Unskilled md 0.20 750.00 150.00
Sub total of A = 170.60 Sub total of B = 0.00 Sub total of C = 5.11
Sub total of A +B + C = 175.71 Contractor's overhead expenses 15% = 26.36 Unit Rate = 202.07
Description of works: Maintenance of gravel shoulders and gravel carriageway by repairing pot holes and making iregularities even to the required level including watering and
compaction etc. all complete lead 10m. Unit : 1 m2
Spec. cl. No: 2904
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
29.03 Skilled md 0.03 1030.00 30.90 Gravel m3 0.11 #REF! #REF! Tools 3.00% of L.C. 7.67
Unskilled md 0.30 750.00 225.00
Sub total of A = 255.90 Sub total of B = #REF! Sub total of C = 7.67
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Description of works: Providing required material and repair pot holes including removal of loose material, trimming of sides, cleaning of surface applying tack coat,20 mm thick
premix carpet and seal coat with bitumen emulsion as per Technical Specifiaction and directions of the Engineer. Unit : 200 m2
Spec. cl. No: 2903
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Crushed Stone aggregate nomial
Skilled md 2.00 1030.00 2060.00 cum 5.40 #REF! #REF! Air Compressor hr 6.00 #REF! #REF!
29.11(ii) size 13.2 mm to 5.6 mm
Unskilled md 18.00 750.00 13500.00 Crushed sand passing 2.36 mm cum 1.20 #REF! #REF! Hot mix Plant hr 6.00 #NAME? #NAME?
Emulsion t 0.70 #REF! #REF! Emulsion Pressure Distributor hr 6.00 #REF! #REF!
Smooth wheeled roller hr 6.00 1589.46 9536.76
Description of works: Filling Pot-holes and Patch Repairs with open-Graded Premix surfacing, 20 mm. Providing required material and repair the the pot holes including removal of
failed material, trimming and finishing the surface applying tack coat on the sides and base of excavation , backfilling with hot bituminous Material and
compaction as per Technical specification and instruction of the Engineer Unit : 600 m2
Spec. cl. No: 2903
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Lalitpur
Err:509
Err:509
Rate Analysis for Lalitpur District FY 077/78
Description of works: Providing and installing Railing including Railing Posts -- 100 mm dia
Unit : m
Spec. cl. No: 3105
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
31.01.c GI Pipe m 1.10 #REF! #REF! Tools and plants, Manpower etc. 10% #REF! #REF!
Sub total of A = 0.00 Sub total of B = #REF! Sub total of C = #REF!
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Description of works: Providing and installing Railing including Railing Posts -- 50 mm dia
Unit : m
Spec. cl. No: 3105
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
31.01.b GI Pipe m 1.10 #REF! #REF! Tools and plants, Manpower etc. 10% #REF! #REF!
Sub total of A = 0.00 Sub total of B = #REF! Sub total of C = #REF!
Sub total of A +B + C = #REF! Contractor's overhead expenses 15% = #REF! Unit Rate = #REF!
Description of works: Providing and installing Railing including Railing Posts --38 mm dia
Unit : m
Spec. cl. No: 3105
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
31.01.a GI Pipe m 1.10 #REF! #REF! Tools and plants, Manpower etc. 10% #REF! #REF!
Description of works: Boring 700mm dia providing and installing bored cast- in-situ RCC pile of specified diameter including bentonite as per specification and drawing etc. all
Unit : m
complete[1600] excluding concrete and reinforcement
Spec. cl. No:1605
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Boring equipment with pump and
skilled md 0.35 1030.00 360.50 Bentonite Kg 27.00 18.97 512.19 hr 0.5 3000.00 1500.00
16.02.03 all accessories
crane for handling reinforcement
semi-skilled md 1.09 817.50 Diesel ltr 8.10 65.49 530.46 hr 0.31 3100 961.00
750.00 cage and trimie pipe
unskilled md 5.11 750.00 3832.50
Sub total of A = 5010.50 Sub total of B = 1042.65 Sub total of C = 2461.00
Sub total of A +B + C = 8514.15 Contractor's overhead expenses 15% = 1277.12 Unit Rate = 9791.27
Description of works: Boring 800mm dia providing and installing bored cast- in-situ RCC pile of specified diameter including bentonite as per specification and drawing etc. all
Unit : m
complete[1600] excluding concrete and reinforcement
Spec. cl. No:1605
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Boring equipment with pump and
skilled md 0.42 1030.00 432.60 Bentonite Kg 30.00 18.97 569.10 hr 0.6 3000.00 1800.00
16.02.03 all accessories
crane for handling reinforcement
semi-skilled md 1.31 750.00 982.50 Diesel ltr 9.70 65.49 635.25 hr 0.37 3100 1147.00
cage and trimie pipe
unskilled md 6.13 750.00 4597.50
Sub total of A = 6012.60 Sub total of B = 1204.35 Sub total of C = 2947.00
Sub total of A +B + C = 10163.95 Contractor's overhead expenses 15% = 1524.59 Unit Rate = 11688.54
Clearing Grass and Removal of Rubbish and Dressing and levelling the
construction surface Clearing grass/ top soil and removal meters outside the
1 0 Err:508 Err:508 0 0 periphery of the area , including cutting and filling of small undulation. By
Manual Means
Providing, jointing and laying HDPE pipes with or without collar etc. complete in
23 0 Err:508 Err:508 0 0
place as per Drawing and Technical Specifications. a) 200 mm outer dia.
Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for
culverts Providing and Laying Reinforced cement concrete NP3 Flush jointed
24 0 Err:508 Err:508 0
pipe for culverts including fixing with cement mortar 1:2 as per Drawing and
Technical Specifications. 600 mm internal dia (with socket system).
Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for
culverts Providing and Laying Reinforced cement concrete NP3 Flush jointed
25 0 Err:508 Err:508 0
pipe for culverts including fixing with cement mortar 1:2 as per Drawing and
Technical Specifications. 900 mm internal dia (with socket system).
Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for
culverts Providing and Laying Reinforced cement concrete NP3 Flush jointed
26 0 Err:508 Err:508 0
pipe for culverts including fixing with cement mortar 1:2 as per Drawing and
Technical Specifications. 1000 mm internal dia (with socket system).
Roadway Excavation in all types of soil by Manual Means as per drawing and
27 0 Err:508 Err:508 0 0 technical specification, including removal of stumps and other deleterious
matter, with all lifts and lead as per Drawing and instruction of the Engineer.
Road way Excavation in all types of soil by Mechanical Means as per Drawing
28 0 Err:508 Err:508 0 and technical specifications including removal of stumps and other deleterious
matter, all lifts and lead as per Drawing and instruction of the Engineer.
Providing suitable material and Back filling with Granular Material behind
abutment, wing wall and return wall complete as per Drawing and Technical
49 0 Err:508 Err:508 0
Specifications.
Crusher Run Macadam sub-base. Providing and laying Crusher Run Macadam
on a prepared surface, spreading and mixing , watering and compacting to
65 0 Err:508 Err:508 0
form a layer of sub-base/Base course as per Drawing and Technical
Specifications. By Mix in palce method. ii) for 63mm maximum size
Crusher Run Macadam Base. Providing and laying Crusher Run Macadam on
a prepared surface, spreading and mixing , watering and compacting to form a
66 0 Err:508 Err:508 0
layer of sub-base/Base course as per Drawing and Technical Specifications.
By Mix in palce method. ii) for 45mm maximum size
67 0 Err:508 Err:508 0 Err:509
68 0 Err:508 Err:508 0 Err:509
69 1 Err:508 Err:508 0 Err:509
70 1 Err:508 Err:508 0 Err:509
71 0 Err:508 Err:508 0 Err:509
72 0 Err:508 Err:508 0 Err:509
73 0 Err:508 Err:508 0 Err:509
74 0 Err:508 Err:508 0 Err:509
75 0 Err:508 Err:508 0 Err:509
76 0 Err:508 Err:508 0 Err:509
77 0 Err:508 Err:508 0 Err:509
Providing and applying tack coat with hot Bitumen By Mechanical Means at
78 0 Err:508 Err:508 0 0 specified rate on the prepared non-bituminous surfaces including cleaning as
per Technical Speciation .
Providing and applying tack coat with hot Bitumen by Manual Means at the
specified rate the prepared surfaces including cleaning as per Technical
79 1 Err:508 Err:508 0
Speciation .
Providing and applying prime coat with hot bitumen MC 30/70 (including
cutter)on prepared surface of granular base including cleaning of road surface
80 0 Err:508 Err:508 0
and spraying at specified rate by mechanical means as per Technical
specification.
Providing and applying prime coat with hot bitumen MC 30/70 (including
81 0 Err:508 Err:508 0 cutter)on prepared surface of granular base including cleaning of road surface
and spraying at specified rate by manual means as per Technical specification.
Painting on Steel Surfaces, Providing and applying two coats of ready mix paint
102 0 Err:508 Err:508 0 of approved brand on steel surface after through cleaning of surface to give an
even shade as per Drawing and Technical Specifications.
Providing , Preparing and Installing form work including necessary supports
and removing after completion for foundation and footings.(Class F1 Finish)
103 0 Err:508 Err:508 0 0
Using timber (soft wood )
Providing , Preparing and Installing form work including necessary supports
104 0 Err:508 Err:508 0 and removing after completion for foundation and footings. (Class F1 Finish)
Using steel
Using timber (soft wood ), Providing , Preparing and Installing form work
105 0 Err:508 Err:508 0 including necessary supports and removing after completion for walls.(Class F2
Finish), vertical plain surface Height upto 3 m
Using timber (soft wood ), Providing , Preparing and Installing form work
106 0 Err:508 Err:508 0 including necessary supports and removing after completion for walls.(Class F2
Finish), vertical plain surface Height above 3 m to 6 m
Using timber (soft wood ),Providing , Preparing and Installing form work
107 0 Err:508 Err:508 0 including necessary supports and removing after completion for walls.(Class F2
Finish), vertical plain surface Height above 6 m to 9 m
Using timber (soft wood ) Providing , Preparing and Installing form work
including necessary supports and removing after completion for walls.(Class F2
108 0 Err:508 Err:508 0
Finish), vertical plain surface
Height above 9 m to 10
Using Steel,Providing , Preparing and Installing form work including necessary
supports and removing after completion for walls. (Class F2 Finish), vertical
109 0 Err:508 Err:508 0
plain surface Height above 3 m to 6 m
Providing and laying , fitting and placing un-coated Mild steel / HYSD
126 0 Err:508 Err:508 0 reinforcement complete in foundation as per drawing and technical
specification
Providing and laying ,fitting and placing Mild steel reinforcement complete in
127 0 Err:508 Err:508 0
sub-structure as per drawing and Technical Specification.
128 0 Err:508 Err:508 0 Err:509
129 0 Err:508 Err:508 0 Err:509
130 0 Err:508 Err:508 0 Err:509
131 0 Err:508 Err:508 0 Err:509
132 0 Err:508 Err:508 0 Err:509
133 0 Err:508 Err:508 0 Err:509
134 0 Err:508 Err:508 0 Err:509
135 0 Err:508 Err:508 0 Err:509
136 0 Err:508 Err:508 0 Err:509
137 0 Err:508 Err:508 0 Err:509
138 0 Err:508 Err:508 0 Err:509
139 1 Err:508 Err:508 0 0 Err:509
140 0 Err:508 Err:508 0 Err:509
141 0 Err:508 Err:508 0 Err:509
142 0 Err:508 Err:508 0 Err:509
143 0 Err:508 Err:508 0 Err:509
144 0 Err:508 Err:508 0 Err:509
145 0 Err:508 10 0 Err:509
Providing and laying Brick Masonry Work in Cement mortar in Foundation /
146 0 11 37 0 0 structure complete excluding Pointing and Plastering, as per Drawing and
Technical Specifications.Cement sand mortar (1:4)
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work
147 0 38 48 0 structure as per Technical Specifications Cement Mortar 1:4 (1 cement : 4
sand)
Providing and laying of Stone Masonry Work in Cement Mortar 1:4 in
148 0 49 58 0
Foundation complete as per Drawing and Technical Specifications.
Providing and laying of Stone Masonry Work in Cement Mortar 1:6 in
149 0 59 67 0 0
Foundation complete as per Drawing and Technical Specifications..
Providing and laying Stone Masonry work in cement mortar 1:4 in structure
complete as per Drawing and Technical Specifications Random Rubble
150 0 68 79 0
Masonry
Providing and lying Stone Masonry work in cement mortar 1:6 in structure
151 0 80 92 0 complete as per Drawing and Technical Specifications Random Rubble
Masonry
Providing and Pointing with cement mortar on masonry work structure as per
152 0 93 104 0
Technical Specifications cement mortar (1:3 )
153 0 105 115 0 Err:509
154 1 116 127 0 Err:509
155 0 128 139 0 Err:509
156 0 140 152 0 Err:509
157 0 153 165 0 Err:509
158 0 166 178 0 Err:509
159 1 179 191 0 Err:509
160 0 192 204 0 Err:509
161 0 205 217 0 Err:509
162 0 218 228 0 0 Err:509
163 0 229 240 0 Err:509
164 1 241 252 0 Err:509
165 1 253 265 0 Err:509
166 0 266 275 1 0 Err:509
167 1 276 285 1 Err:509
168 1 286 312 1 Err:509
169 1 313 326 1 Err:509
170 1 327 335 1 1 Err:509
171 1 336 344 1 Err:509
172 1 345 353 1 Err:509
Page 18 of 81
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Development Co-operation Implemetation Division
Kathmandu Ring Road Improvement Project
Ekantakuna,Lalitpur
Cm t1 t 2 t 3 t 4
Where,
Cm=Cycle time
t1=Excavating Time
t2=Swing Time (Loaded)
t3=Dumping Time
t4=Swing Time (Empty)
1 1
T 0.022(hr / cum)
Q 45.64
Prepared By Checked By Approved By
Page 19 of 81
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Development Co-operation Implemetation Division
Kathmandu Ring Road Improvement Project
Ekantakuna,Lalitpur
1 1
T 0.022(hr / cum)
Q Analysis
Rate 45.64 for Excavator PC 200
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Development Co-operation Implemetation Division
Kathmandu Ring Road Improvement Project
Ekantakuna,Lalitpur
Rate Analysis
DESC UNIT UNIT RATE AMOUNT
Labour
Unskilled md 0.00469 670 3.14
Sub-Total 3.14
Materials
Disel ltr 0.26 85.40 22.20
Lubricant 0.22
Sub-Total 22.42
Equipments
Excavator hr 0.022 3581.85 78.80
Sub-Total 78.80
Grand Total 104.36
Contractors overhead@ 15 % 15.65
Total 120.01 (WO VAT)
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Development Co-operation Implemetation Division
Kathmandu Ring Road Improvement Project
Ekantakuna,Lalitpur
Rate Analysis
DESC UNIT UNIT RATE AMOUNT
Labour
Unskilled md 0.00469 670 3.14
Sub-Total 3.14
Materials
Disel ltr 0.26 85.40 22.20
Lubricant 0.22
Sub-Total 22.42
Equipments
Excavator hr 0.022 3581.85 78.80
Sub-Total 78.80
Grand Total 104.36
Contractors overhead@ 15 % 15.65
Total 120.01 (WO VAT)
Landslide clearence
Provide Combination of mannual and machined excavation
Soft Soil Percentage Rate Amount
Mannual Excavation 0 693.92 0.00
Machined Excavation 100 120.01 120.01
Total 120.01
Hard soil
Percentage Rate Amount
Mannual Excavation 0 693.92 0.00
Machined Excavation 100 120.01 120.01
Total 120.01
Soft rock
Percentage Rate Amount
Mannual Excavation 0 Err:509 Err:509
Machined Excavation 100 120.01 120.01
Total Err:509
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Development Co-operation Implemetation Division
Kathmandu Ring Road Improvement Project
Ekantakuna,Lalitpur
Rate Analysis
DESC UNIT UNIT RATE AMOUNT
Labour
Unskilled md 0.00469 670 3.14
Sub-Total 3.14
Materials
Disel ltr 0.26 85.40 22.20
Lubricant 0.22
Sub-Total 22.42
Equipments
Excavator hr 0.022 1858.80 40.89
Sub-Total 40.89
Grand Total 66.45
Contractors overhead@ 15 % 9.97
Total 76.42 (WO VAT)
Excavation of foundation
Provide Combination of mannual and machined excavation
All types of soil condition Percentage Rate Amount
Mannual Excavation 10 808.45 80.85
Machined Excavation 90 76.42 68.78
Total 149.63
Rate Analysis
DESC UNIT UNIT RATE AMOUNT
Labour
Unskilled md 0.00469 670 3.14
Sub-Total 3.14
Materials
Disel ltr 0.26 85.40 22.20
Lubricant 0.22
Sub-Total 22.42
Equipments
Excavator hr 0.022 1858.80 40.89
Sub-Total 40.89
Grand Total 66.45
Contractors overhead@ 15 % 9.97
Total 76.42 (WO VAT)
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Development Co-operation Implemetation Division
Kathmandu Ring Road Improvement Project
Ekantakuna,Lalitpur
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Central Regional Road Directorate
Division Road Office
Katunje, Bhaktapur
Rate Analysis for Kavre
Description of works: Providing mechanically woven double twisted crate (3*1*1) , heavy zinc coated ,hexagonal mesh type 100 mm x 120 mm, mesh wire 3 mm, selvage wire 3.9
mm, lacing wire 2.4 mm, including assembling work ,binding with wire,bracing and tieing with wire and filling stone/boulders in gabion box all complete Unit : per
Spec. cl. No: 2402
as per drawing and technical specification. box
3297.00 12362.90
Sub total of A = Sub total of B = Sub total of C = 0.00
Sub total of A +B + C = 15659.90 Contractor's overhead expenses 15% = 2348.99 Unit Rate = 18008.89
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Central Regional Road Directorate
Division Road Office
Katunje, Bhaktapur
Rate Analysis for Kavre
Description of works: Providing mechanically woven double twisted crate (2*1*1) , heavy zinc coated ,hexagonal mesh type 100 mm x 120 mm, mesh wire 3 mm, selvage wire 3.9
mm, lacing wire 2.4 mm, including assembling work ,binding with wire,bracing and tieing with wire and filling stone/boulders in gabion box all complete
as per drawing and technical specification. Unit : per
box
Unskilled md 750.00
For 10 Cum 8060.00 24200.00
Per Box 1612.00 4840.00
Sub total of A +B + C = 10651.11 Contractor's overhead expenses 15% = 1597.67 Unit Rate = 12248.78
Description of works: Providing mechanically woven double twisted crate (1.5*1*1) , heavy zinc coated ,hexagonal mesh type 100 mm x 120 mm, mesh wire 3 mm, selvage wire Unit : per
3.9 mm, lacing wire 2.4 mm, including assembling work ,binding with wire,bracing and tieing with wire and filling stone/boulders in gabion box all box
Spec. cl. No: 2402
completeLabour
as per(A)
drawing and technical specification. Material (B) Equipment (C)
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Central Regional Road Directorate
Division Road Office
Katunje, Bhaktapur
Rate Analysis for Kavre
Providing mechanically woven double twisted crate , heavy zinc coated ,hexagonal mesh type 100 mm x 120 mm, mesh wire 3 mm, selvage wire 3.9 mm, lacing wire 2.4
mm, including assembling work ,binding with wire,bracing and tieing with wire and filling stone/boulders in gabion box all complete as per drawing and technical
Unit : 1 m3
specification.
Norms No. 24.2A, 24.3, 24.4