Production Plan: Casting Production Plan Is Based On The Regular Supply of Wapda and Raw Materials

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Production Plan Issue: 01

Revision: 00
From 01-Oct-2020 To: 30-Oct-2020 Code: SOP-F-09-01/19
RAVI Automobile Pvt Ltd.
Component Diff case fiat Diff case RH- Diff case LH-240 Diff Case LH Diff Case RH Diff case fiat RH Diff case fiat LH Axel Housing water body Water body WB Fiat Pully C.B 78cc C.B 97cc C.B 72cc Oil pump MF-
M1 240 385 385 MF-240 MF-385 240

Schedule 800 400 400 200 200 25 25 2700 1900 1600 2700 3000 8000 5000 2500
Plan & Do P D P D P D P D P D P D P D P D P D P D P D P D P D P D
1/Oct/20 90 100 100 700
150
2/Oct/20 70 30 70 100 750

3/Oct/20 72 150 100 700

5/Oct/20 72 130 50 120 540


150
6/Oct/20 40 150 100 120 700
150
7/Oct/20 40 150 100 120 700
150
8/Oct/20 96 150 100 120 700
150
9/Oct/20 96 150 100 120 700
150
10/Oct/20 96 150 100 120 700
150
12/Oct/20 96 150 100 120 700
150
13/Oct/20 72 150 100 120 700
150
14/Oct/20 40 150 100 120 700
150
15/Oct/20 100 150 100 120 700
150
16/Oct/20 100 150 100 120 700
150
17/Oct/20 40 150 100 120 700
150
19/Oct/20 40 150 100 120 700
150
20/Oct/20 40 150 100 120 700
150
21/Oct/20 60 150 100 120 700
150
22/Oct/20 100 150 100 120 700
150
23/Oct/20 40 150 100 120 600 100

24/Oct/20 40 200 100 120 700

26/Oct/20 40 200 100 120 700

27/Oct/20 40 200 100 120 700

28/Oct/20 100 200 100 120 700

29/Oct/20 60 200 120 700

30/Oct/20 200 120 700

31/Oct/20 200 120 700

Total Qty 600 300 300 160 160 2840 2030 1620 3180 5500 8290 5000 2550
Remarks: Casting Production plan is based on the regular supply of wapda and raw materials.

Prepared By: _______ Reviewed Approved By: __________


Production Plan Issue: 01
Revision: 00
From 01-Oct-2020 To: 30-Oct-2020 Code: SOP-F-09-01/19
Infinity Engineering Pvt. Ltd.
Fly Wheel
Component 12'' PP MF Cover FW Plate PTO FIAT Cover Inner Plate Outer Plate GS-1 GS-2 GT-1 GT-2 CAM IMC Crank Shaft C B A E BKT. Caliper

Schedule 2300 2300 2000 2000 1000 800 800 500 500 500 500 2500 700 1000 500 2000 1000 800 2500 Set
Plan & Do P D P D P D P D P D P D P D P D P D P D P D P D P D P D P D P D P D P D P D
1/Oct/20 110 110 200 100 30 15 332

2/Oct/20 110 200 50 220 30 15

3/Oct/20 110 200 50 220 30 15

5/Oct/20 110 200 50 220 30 15 240

6/Oct/20 110 200 50 220 30 15 180

7/Oct/20 110 200 50 110 110 30 15 240

8/Oct/20 110 200 50 220 30 15 240

9/Oct/20 110 200 50 220 30 15 240

10/Oct/20 110 200 50 220 30 15 264

12/Oct/20 110 200 50 220 30 15 70

13/Oct/20 110 200 50 100 30 15 60

14/Oct/20 110 110 50 200 30 15 60

15/Oct/20 110 110 50 200 30 15 60

16/Oct/20 110 110 50 200 30 15 60

17/Oct/20 110 110 50 200 30 15 60

19/Oct/20 110 110 200 100 30 15 60

20/Oct/20 110 110 200 100 30 15 60

21/Oct/20 110 110 200 100 30 15 120

22/Oct/20 110 110 200 100 30 15 180

23/Oct/20 110 110 200 100 30 15 180

24/Oct/20 110 110 200 100 30 15 180

26/Oct/20 110 110 200 100 30 15 180

27/Oct/20 110 110 200 100 30 15 180

28/Oct/20 110 110 200 100 30 15 180

29/Oct/20 110 110 200 100 30 15 112 180

30/Oct/20 110 110 200 100 30 15 224 180

31/Oct/20 110 110 200 100 30 15 168 210

Total Qty 2420 2420 2200 2000 700 600 600 550 540 540 550 1200 810 405 504 960 596 490 1950
Remarks: Casting Production plan is based on the regular supply of wapda and raw materials.

Prepared By: _______ Reviewed Approved By: __________