RASGAS EXPANSION PROJECT - OFFSHORE FACILITIES PROJECT

TRAIN 3 (WH7) - CHANGE ORDER STATUS SUMMARY

Approved Change Orders Change Orders Excluding External


APPROVED CHANGE ORDERS Cost ($1000s) Authorisation/Funding
Rev. 0 Rev. 1
CNF Platform Pipeline Approval Platform Pipeline Platform Pipeline
CO No. No. DESCRIPTION Facilities Facilities Date Facilities Facilities Facilities Facilities
28"/38" Expandable Tool Development
WH7PL-1 9 Develop and test, in a mock up of the Wye connection, the 28"/38" 740 24-Mar-02 740 740
expandable drive module for vendor's intelligent pipeline pig.
WH7 Pipeline Facilities - Increased Capacity
WH7PL-2 5 The EPC Work Scope changes to the 38" export pipeline, the WH5 tie-in 1,576 29-Jun-02 1,576 1,576
connection and the shore approach section for the future 38" pipeline.
Includes the Engineering Feasibility Study for the Increased Capacity.
Subsea Cable Rerouting Changes
WH7PL-3 3 Increased cable length is required for route changes due to the 738 10-Jun-02 738 738
location of an SPM in the Maersk Block 5 Development.
UT in Lieu of Radiography of Lay Barge Girth Weld
WH7PL-4 12 Use UltraSonic (UT), in lieu of radiography, for NDT of the girth welds (110) 28-Jul-02 (110) (110)
during offshore pipeline installation on the Lay Barge.
Well Kill Valves
Procurement of 8 (eight) Actuated Well Kill Valves from Wellhead Tree 244 16-Sep-02
Manufacturer.
WH7 Platform Facilities
WH7PF-2 26 Change in Insrument and Plant Air Packege for WH7 Platform 36 16-Jun-03 36 36

Ground Fault Detection


WH7PF-3 35 Deletion of Ground Fault Detection System on the existing RasGas Alpha (39) 21-Mar-04 (39) (39)
Process/Utility Platform.
WH7 Flowline Debottleneck Study
WH7PL-6 27 Feasibility Study to determine capacity constraints in current 10" 280 26-May-04 280 280
well flowlines, and then investigate the impact of increased flowline
capacity of 200 MM scfd on the design of 9 and 12 slot Platforms.
Pad Eyes
WH7PF-4 43 Provision of 12 Nos. Pad Eyes welded on WH7 Drill Deck. 20 7-Jun-04 20 20

Platform 38" Valve String Installation


WH7PF-5 43 Offshore installation of 38" Valves with a crane barge performed during hook-up 900 13-Jul-04 900 900
of the Facilities. Company portion of shared cost with Contractor.
WH7 - 7th Well Flowline Hookup/Mechanical Completion (SIMOPS)
WH7PF-6 57 Engineering, Procurement and Installation for the 7th Well Flowline 1,600 25-Aug-04 1,600 1,600
at WH7 Platform (SIMOPS).
WH7 - 7th Well Flowline Hookup/Mechanical Completion (SIMOPS)
WH7PF-7 68 Incremental costs for standby of equipment and personnel 83 18-Nov-04 83 83
due actual mobilization 12 days later than planned.
WH7 - Pipeline Blowdown System
WH7PF-8 24 Change with respect to modifications to the Platform mounted temporary flare 500 16-Nov-04 500 500
to blowdown the Export Pipeline.

File: 510655337.xls (WH7) 1 of 9


02/19/2021
RASGAS EXPANSION PROJECT - OFFSHORE FACILITIES PROJECT
TRAIN 3 (WH7) - CHANGE ORDER STATUS SUMMARY

Approved Change Orders Change Orders Excluding External


APPROVED CHANGE ORDERS Cost ($1000s) Authorisation/Funding
Rev. 0 Rev. 1
CNF Platform Pipeline Approval Platform Pipeline Platform Pipeline
CO No. No. DESCRIPTION Facilities Facilities Date Facilities Facilities Facilities Facilities
Additional HVAC Requirements
WH7PF-11 15 Additional costs to provide HVAC unit compliant with Class 1, Division 2 200 14-Dec-05 200 200
requirements.
Test Separator Transportation
WH7PF-12 Additional premium for direct shipment of the Test Separator to Jebel Ali. 40 14-Dec-05 40 40
Test Separator Internals
WH7PF-13 13 Increase length of inlet diverter for WH7 Test Separator. 43 14-Dec-05 43 43
Additional Secretary
WH7PF-14 Provision of additional secretary to Company for 1 year. 50 14-Dec-05 50 50
Global Practice
WH7PF-15 Implementation of ExxonMobile Global Practice GP 29-01-17 Version A. 600 14-Dec-05 600 600
Bolt Tensioning Equipment
WH7PF-16 48 Supply Hydra-tight Equipment for the 38" Valve on the WH7 Platform 55 14-Dec-05 55 55
Post Installation Survey
WH7PF-17 50 Carry out the WH7 Deck Post Installation Survey using an ROV instead of 75 14-Dec-05 75 75
a Sector Scan Survey.
KHI Tank Internal Coating
WH7PF-18 72 WH7 KHI Storage Tank Internal Coating Repair. 451 14-Dec-05 451 451
Subsea Cable
WH7PF-19 76 Supply of 2No.'s Subsea Cable Splice Kits 82 14-Dec-05 82 82

TOTAL APPROVED CHANGE ORDERS 4,940 3,224 4,696 3,224 4,696 3,224
8,164 7,920 7,920

Note: For the total cost of $9.576 Million for the Change Order for the WH7 Pipeline Facilities Increased Capacity, $1.576 Million is funded from Train 3 (WH7) Contengency, and the
balance, $8.0 Million, is funded from Train 4 (WH5) Option.

File: 510655337.xls (WH7) 2 of 9


02/19/2021
COMMENTS

Authorised by the Board


(See Note)

Contract OPTION 6.4 (Exh.7.13)


converted into Change Order.
Procured by RasGas DTF
on behalf of Offshore PMT

Requested and Authorised by


Venture Manager

Approved by Venture Manager

File: 510655337.xls (WH7) 3 of 9


02/19/2021
COMMENTS

File: 510655337.xls (WH7) 4 of 9


02/19/2021
RASGAS EXPANSION PROJECT - OFFSHORE FACILITIES PROJECT
TRAIN 4 (WH5) - CHANGE ORDER STATUS SUMMARY

Approved Change Orders Change Orders Excluding External


APPROVED CHANGE ORDERS Cost ($1000s) Authorisation/Funding
Rev. 0 Rev. 1
CNF Platform Pipeline Approval Platform Pipeline Platform Pipeline
CO No. No. DESCRIPTION Facilities Facilities Date Facilities Facilities Facilities Facilities COMMENTS
Engineering Studies relating to WH5 Platform Facilities
Feasibility Study to convert WH5 Platform to 12-slots, from 9-slots for Authorised by the Board
WH5PF-1 6 the Increased Capacity Case of 1.2BSCFD, and the EPC engineering 191 11-May-02 191 191
and drafting to produce AFC drawings for the 12-slot Jacket.
WH5 DCS System HART Communications Protocol
WH5PF-3 42 HART Communications enables the DCS to communicate with transducers 15 25-Apr-04 15 15
to access the transducers firmware and allow integration or changes
to transmitter parameters.
WH3 Link to WH4 Export Pipeline Requested and Authorised by
WH5PL-2 28 Feasibility Study to evaluate options available to engineer and construct 320 07-Sep-04 320 320 Venture Manager
a pipeline link between RasGas "Alpha" Wellhead Platform and WH4
Export Pipeline.
Pad Eyes
WH5PF-4 53 Provision of 12 Nos. Pad Eyes welded on WH5 Drill Deck 7 12-Oct-04 7 7
Onshore Pipeline Section Construction Changes
WH5PL-3 16 Scope changes related to restricited ROW access and double 700 29-Nov-04 700 Separate Budget Funding
handling of materials and other related construction costs. for RLIC scope changes
WH7 - 8th Well Flowline Hookup/Mechanical Completion (SIMOPS)
WH7PF-9 67 Engineering, Procurement and Installation for the 8th Well Flowline 1,200 16-Nov-04 1,200 1,200 Train 4 Well drilled
at WH7 Platform (SIMOPS). on WH7 Platform
Platform Shutdown System Modifications
WH5PF-5 70A Changing the current shutdown logic from PSD to ESD and 90 27-Dec-04 90 90
provide shutdown bypass for H2S detectors.
WH5 Drill Deck Strengthening
WH5PF-6 63A Engineering, procurement, fabrication and trial fit of 1 No. BOP 180 27-Dec-04 180 180
Stack Mounting frame.
WH7 - 8th Well Flowline Hookup/Mechanical Completion (SIMOPS)
WH7PF-10 86 Incremental costs for standby of equipment and personnel 243 24-Mar-05 243 243 Train 4 Well on WH7 Platform
due actual mobilization 17 days later than planned.
Platform Modification toEnhance SIMOPS
WH5PF-7 60A Provide beams and grating modifications suitable for use during 185 17-Apr-05 185 185
drilling operation to provide sufficient opening for drill bit.
UPS Power Outlet
WH5PF-8 85A Engineering, Procurement and Installation of UPS Power Outlet 37 17-Apr-05 37 37
on the WH5 Drill Deck.
Well Kill Valves Procured by RasGas DTF
Procurement of 9 (nine) Actuated Well Kill Valves from Wellhead Tree 268 3-Aug-03 on behalf of Offshore PMT
Manufacturer.
Pigging Lessons Learned
WH5PF-9 91 Change from Grating to Plate at Pig Loading Location. 21 23-Jun-05 21 21
Corrosion Coupons
WH5PL-4 93A Supply one set (6 pieces) of Corrosion Coupons for WH5 Piplilne. 1 7-Aug-05 1 1
Commissioning and Start-up Support Authorised an funded by
WH5PF-10 90A Provide Offshore Operations Asset Group with Manpower support for 129 29-Jun-05 129 OED/OAG
the WH5 Platform Commissioning and Start-up.

File: 510655337.xls (WH5) 5 of 9


02/19/2021
RASGAS EXPANSION PROJECT - OFFSHORE FACILITIES PROJECT
TRAIN 4 (WH5) - CHANGE ORDER STATUS SUMMARY

Approved Change Orders Change Orders Excluding External


APPROVED CHANGE ORDERS Cost ($1000s) Authorisation/Funding
Rev. 0 Rev. 1
CNF Platform Pipeline Approval Platform Pipeline Platform Pipeline
CO No. No. DESCRIPTION Facilities Facilities Date Facilities Facilities Facilities Facilities COMMENTS
Global Practice
WH5PF-11 Implementation of ExxonMobile Global Practice GP 29-01-17 Version A. 600 14-Dec-05 600 600
Vent and Relief
WH5PF-12 73A Engineering, procurement, fabrication, Installation and Testing of WH5 500 14-Dec-05 500 500
Deck Vent and Relief modifications.
Additional SIMOPS Materials
WH5PF-13 81 Additional Engineering, procurement and installation of materials required 405 14-Dec-05 405 405
for SIMOPS Wells on WH5 (4 No.'s) and the supply of material for 1 No.
contingency Well.
TOTAL APPROVED CHANGE ORDERS 4,072 1,021 3,804 1,021 3,674 321
5,093 4,825 3,996

Note: For the total cost of $9.576 Million for the Change Order for the WH7 Pipeline Facilities Increased Capacity, $1.576 Million is funded from Train 3 (WH7) Contingency, and the
balance, $8.0 Million, is funded from Train 4 (WH5) Option.

File: 510655337.xls (WH5) 6 of 9


02/19/2021
RASGAS EXPANSION PROJECT - OFFSHORE FACILITIES PROJECT
TRAIN 5 (WH9) - CHANGE ORDERS STATUS SUMMARY

Approved Change Orders Change Orders Excluding External


APPROVED CHANGE ORDERS Cost ($1000s) Authorisation/Funding
Rev. 0 Rev. 1
CNF Platform Pipeline Approval Platform Pipeline Platform Pipeline
CO No. No. DESCRIPTION Facilities Facilities Date Facilities Facilities Facilities Facilities COMMENTS
WH9 Pre-engineering Geophysical and Geothechnical Surveys Board Authorized as

WH9PF-1 39 Conduct Geophysical Survey for the WH9 Pipeline route and the Subsea 696 412 08-Jan-04 412 Ch.Order ($1,108) for LNG
Cable route. Conduct Geotechnical Survey at the WH9 Jacket location Agreement T3EPC-02
WH9 Jacket and Temporary Deck Board Authorized as
WH9PF-2 42 Engineering , Procurement and Construction for the WH9 Jacket (12-slots). 9,800 14-Jan-04 Ch.Order for LNG Agreement
with a completion date of 28 June 2004 for offshore installation. T3EPC-02
WH9 Jacket
WH9PF-3 59 Additional Survey coverage for Drill Rig Approach 20 24-Aug-04 20 Booked to DTF Account
Pad Eyes

WH9PF-4 55 Provision of 12 Nos. Pad Eyes welded on WH9 Drill Deck 6 12-Oct-04 6 6
WH9 - Deck Steel Escalation
WH9PF-5 82 Cost of Material Escalation for the Deck Steel Structure that 137 27-Dec-04 137 137
exceeds the agreed basis at the time of awarding the option for WH9.
WH4 Drill Deck Strengthening
WH9PF-6 63C Engineering, procurement, fabrication and trial fit of 1 No. BOP 180 27-Dec-04 180 180
Stack Mounting frame.
Platform Shutdown System Modifications
WH9PF-7 70C Changing the current shutdown logic from PSD to ESD and 66 28-Dec-04 66 66
provide shutdown bypass for H2S detectors.
Well Kill Valves Procured by RasGas DTF
Procurement of 12 (twelve) Actuated Well Kill Valves from Wellhead Tree 390 15-Mar-05 on behalf of Offshore PMT
Manufacturer.
UPS Power Outlet
WH9PF-7 85C Engineering, Procurement and Installation of UPS Power Outlet 26 28-Apr-05 26 26
on the WH9 Drill Deck.
Platform Modification toEnhance SIMOPS
WH9PF-9 60C Provide beams and grating modifications suitable for use during 99 01-Jun-05 99 99
drilling operation to provide sufficient opening for drill bit.
Vent and Relief
WH9PF-10 73C Engineering, procurement, fabrication, Installation and Testing of WH9 400 14-Dec-05 400 400
Deck Vent and Relief modifications.
Additional SIMOPS Materials
WH9PF-11 81 Additional Engineering, procurement and installation of materials required 155 14-Dec-05 155 155
for SIMOPS Wells on WH9 (9 No.'s) and the supply of material for 1 No.
contingency Well.

TOTAL Approved Change Orders 11,974 412 1,088 412 1,068 0


12,386 1,500 1,068
File: 510655337.xls (WH9)
02/19/2021
RASGAS EXPANSION PROJECT - OFFSHORE FACILITIES PROJECT
AKG 1 (WH4) - CHANGE ORDER STATUS SUMMARY

Approved Change Orders Change Orders Excluding External


APPROVED CHANGE ORDERS Cost ($1000s) Authorisation/Funding
Rev. 0 Rev. 1
CNF Platform Pipeline Approval Platform Pipeline Platform Pipeline
CO No. No. DESCRIPTION Facilities Facilities Date Facilities Facilities Facilities Facilities COMMENTS
Procurement of the WH6 Onshore Pipeline Section Authorised and Funded by
WH6PL-1 10A Procurement of the line pipe for the WH6 Onshore Pipeline between the 4,199 13-May-02 ExxonMobil
Shore Approach and the pipeline battery limit within the Onshore Plant. (See Note 1)
Engineering Studies relating to WH6 Options Authorised and Funded by
WH6PL-2 4 Evaluation of the Increased Capacity flow rate of 1.2BSCFD in the WH6 97 11-May-02 97 ExxonMobil
and WH4 pipelines, the Feasibility Study to convert WH6 Platform to
12-slots, and the EPC engineering for the WH6 Onshore Pipeline.
WH6 Onshore Pipeline Installation Authorised and Funded by
WH6PL-3 10B Installation of the WH6 Onshore Pipeline Section between the Shore 3,799 4-Jul-02 ExxonMobil
Approach and the battery limit within the Onshore Plant. (See Note 1)
Advanced Engineering for WH6 Jacket Authorised and Funded by
WH6PF-1 21 Advance Engineering design work for WH6 Jacket/Piles to develop 320 19-Nov-02 320 ExxonMobil
AFC drawings.
WH4 Pipeline/Cable Route Survey and Jacket Location Surveys Authorised and Funded by
WH4PL-1 22 Pre-Eengineering hydrographic survey due to revised Platform 999 23-Dec-02 ExxonMobil
location and revised 38" Pipeline routing, and Engineering to develop AFC
Jacket drawings.
WH4 DCS System HART Communications Protocol
WH4PF-2 42 HART Communications enables the DCS to communicate with transducers 15 25-Apr-04 15 15
to access the transducers firmware and allow integration or changes
to transmitter parameters.
Additional Well Flowlines Authorised and Funded by
WH4PF-3 58 Engineering, Procurement and Construction of the initial installation of the 4,100 25-Aug-04 ExxonMobil
8th and 9th Well Flowlines. Excludes the offshore hookup/mechanical
completion of the Flowlines (SIMOPS).
Pad Eyes
WH4PF-4 54 Provision of 12 Nos. Pad Eyes welded on WH4 Drill Deck. 6 12-Oct-04 6 6
Platform Shutdown System Modifications
WH4PF-5 70B Changing the current shutdown logic from PSD to ESD and 90 27-Dec-04 90 90
provide shutdown bypass for H2S detectors.
WH4 Drill Deck Strengthening
WH4PF-6 63B Engineering, procurement, fabrication and trial fit of 1 No. BOP 180 27-Dec-04 180 180
Stack Mounting frame.
WH4 Line Pipe Customs Clearance
WH4PL-2 62 Customs Clearance at Doha Port for WH4 Linepipe Transportation. 90 15-Feb-05 90 90
Well Kill Valves Procured by RasGas DTF
Procurement of 8 (eight) Actuated Well Kill Valves from Wellhead Tree 237 28-Apr-04 on behalf of Offshore PMT
Manufacturer.
UPS Power Outlet
WH4PF-7 85B Engineering, Procurement and Installation of UPS Power Outlet 41 28-Apr-05 41 41
on the WH4 Drill Deck.

File: 510655337.xls (WH4) 8 of 9


02/19/2021
RASGAS EXPANSION PROJECT - OFFSHORE FACILITIES PROJECT
AKG 1 (WH4) - CHANGE ORDER STATUS SUMMARY

Approved Change Orders Change Orders Excluding External


APPROVED CHANGE ORDERS Cost ($1000s) Authorisation/Funding
Rev. 0 Rev. 1
CNF Platform Pipeline Approval Platform Pipeline Platform Pipeline
CO No. No. DESCRIPTION Facilities Facilities Date Facilities Facilities Facilities Facilities COMMENTS
Platform Modification toEnhance SIMOPS
WH4PF-8 60B Provide beams and grating modifications suitable for use during 107 1-Jun-05 107 107
drilling operation to provide sufficient opening for drill bit.
Pigging Lessons Learned
WH4PF-9 91B Change from Grating to Plate at Pig Loading Location. 21 23-Jun-05 21 21
Corrosion Coupons
WH4PL-3 93B Supply two set (12 pieces) of Corrosion Coupons for WH4 Piplilne. 3 7-Aug-05 3 3
Commissioning and Start-up Support Authorised and funded by
WH4PF-10 90B Provide Offshore Operations Asset Group with Manpower support for 134 31-Aug-05 134 OED/OAG
the WH4 Platform Commissioning and Start-up.
Hook-up spread standby cost
WH4PF-11 106 Hook-up spread standby cost resulting from the gas leaks in the WH4 24 28-Nov-05 24 24
Wellbay area by passing X-mas tree valves .
Additional Tug Boats
WH4PF-12 107 Provision of Tug Boats for Derrick Barge 27 during WH4 Hook-up activities 340 4-Dec-05 340 340
Vent and Relief
WH4PF-13 73B Engineering, procurement, fabrication, Installation and Testing of WH4 600 14-Dec-05 600 600
Deck Vent and Relief modifications.
Additional SIMOPS Materials
WH4PF-14 81 Additional Engineering, procurement and installation of materials required 241 14-Dec-05
for SIMOPS Wells on WH4 (2 No.'s) and the supply of material for 1 No.
contingency Well.
TOTAL Approved Change Orders 6,456 9,187 914 190 1,424 93
15,643 1,104 1,517

Note: 1. Early award of the onshore portion of the Export Pipeline for WH6 Option; redesignated WH4 Pipeline when TOR Field Development change was implemented for the Expansion Project.