Slug Catcher Crossover Mitigation Scenarios Train 6

1 1 1 1 1 1 1 1
Activity
Mar Apr May Jun Jul Aug Sep Oct
Base Case ( as awarded ) Hook-Up and Mechanical Completion in parallel
WH6 Deck Set - H-U / M.C. M.C. Train 6 Facilities 30 June 2008

WH8 Deck Set - H-U / M.C.


Scenario 1 - Set Decks as per Contract - Hook-Up and Mechanical Completion back to back
WH6 Deck Set - H-U / M.C.
WH8 Deck Set - H-U / M.C.
Pros: Access given back to Drilling for a period of 2 months following WH8 Deck set (possible savings on SIMOPs)
Cons: Cost impact delaying EPC Contractor
Cons: 2 Months additional drilling possibly insufficient for completion of remaining wells
Cons: Drilling rig standby costs (during WH8 Deck installation)
Scenario 1A - Set Decks as per Contract - Hook-Up and Mechanical Completion follows completion of drilling activities
WH6 Deck Set - H-U / M.C.
WH8 Deck Set - H-U / M.C.
Pros: Access given back to Drilling following WH8 Deck set (savings on SIMOPs)
Cons: Cost impact delaying EPC Contractor
Cons: 2 Drilling rig standby costs (during WH8 Deck installation)
Cons: Condition of Platform following the completion of drilling activities
Scenario 2 - Postpone Setting WH8 Deck until completion of Drilling activities
WH6 Deck Set - H-U / M.C.
WH8 Deck Set - H-U / M.C.
Pros: Drilling continues until completed (savings on SIMOPs).
Cons: Impact associated with additional Mob/Demob of suitable Heavy Lift barge for WH8 Deck Set, Cost impact due to
additional Mob/Demob of suitable Hook-Up spread and and extended schedule duration.
1 1 1 1 1 1 1 1
Mar Apr May Jun Jul Aug Sep Oct

Setting the WH Platform Deck


Legend : =
onto the Jacket

Hook-Up and Mechanical


=
Completion activities