Professional Documents
Culture Documents
Rasgas Company LTD Offshore Expansion Project: Train 3 (WH No.7)
Rasgas Company LTD Offshore Expansion Project: Train 3 (WH No.7)
Rasgas Company LTD Offshore Expansion Project: Train 3 (WH No.7)
(US $1,000s)
Work Breakdown
Structure Original Dec '06 Changes Cumulative Current Actual
Internal Cost Budget Budget This Month Changes Forecast Expenditure
Order Element Description (Aug '01) ITD Actual (1) ITD Budget
5 Other Costs
T5335 Commissioning & Start-up 1,000 - - - -
RGT5322 7th Flowline Hook-Up (SIMOPS) - 2,957 1,683 2,957 2,957 2,957
Sub Total (Item 5) 1,000 2,957 - 1,683 2,957 2,957 2,957
7 T5330 570100 Contingency (Exc.WH6 P/L Shore Approach) 13,111 613 800 - 613
Note 1: Accrual data (value of work to date) based on actual progress as reported.
Note 2: Does not include Buy-in Costs.
Note 3: The WH6 38" Pipeline Shore Approach, $4.858 million is included with WH7 Project at award.
Note 4: For the total cost of $9.576 million for the Change Order for the WH7 Pipeline Facilities
Increased Capacity, $1.576 million is funded from Train 3 (WH7) Contingency, and the
balance, $8.0 million, is funded from Train 4 (WH5) Project at award.
Work Breakdown Structure: Work Breakdown structure in SAP by Internal Order & Cost Element
Original Budget: AFE, approved by the Board
Dec '06 Budget: Dec'06 WP&B, approved by the Board in Dec '06
Changes this month: Value of Change Orders approved in this month
Cumulative Changes: Value of Change Orders approved cumulatively
Current Forecast: Actual spent + forecast to complete
ITD Actual: Value of work in place based on preliminary progress
ITD Budget: Planned Budget Expenditure