Professional Documents
Culture Documents
Venture Weekly Report - WE Dec 13, 2007 Submitted To VB
Venture Weekly Report - WE Dec 13, 2007 Submitted To VB
510707523.doc Page 1 of 8
lay-down area. In the second incident, root-cause investigation is in progress. Immediate Corrective
Action: Focus on hand safety on safety walk; site-wide hand injury campaign issued.
3. PROJECT MANAGEMENT
Staffing:-
Plan 1) Actual Variance + / -
Offshore 2) 34 32 30 -4 -2
RGX2 235 195 -40
Offplot Projects 102 88 -14
Barzan 6 4 -2
Venture Functional Support 70 62 -8
TOTAL 445 379 -66
1) End-December Plan through VOC #37 – 07.
2) Plan through VOC #39-07
Plan Actual
Ve nture Sta ffing
395 414 430 436 445
357 365 379 379
400 340
200
0
De c. 2006 M ar . 2007 Jun. 2007 Se p. 2007 Cur r e nt
10,000 9 ,0 3 2 9 ,2 8 7
9 ,19 6
Offshore
8,000
Onshore (RGX)
6,000
4,000
2 ,76 2 2 ,8 6 6 3 ,0 3 8 666 Onshore (RGX2)
2 ,2 4 2 2 ,4 59
2 ,18 6
2,000
590 645 651 Offplots
RGX2
Train 6
Offshore
WH6 Deck Fabrication 2) 1.6% 1.8% 73.5% 72.2%
WH8 Deck Fabrication 2) 0.5% 0.6% 66.6% 66.7%
Train 7
AKG-2
510707523.doc Page 2 of 8
5. TRAINS 6 & 7
ONSHORE & OFFSHORE
Accomplishments
- Offshore
Cumulative WH6 deck fabrication progress is slightly ahead of plan: WH8
cumulative progress is essentially on revised plan.
The following key equipment has been received to support deck
fabrication: three (of 8) 38-inch high pressure ball valves and
the WH8 instrument air package all arrived at the port in Dubai
and has cleared customs. The WH6 instrument air package
was received in Jebel Ali.
The WH6 wye piece for the subsea flange assembly on the 38-
inch export pipeline has arrived at the port in Dubai.
- Onshore
Train 6
Progress shortfalls continue to put pressure on mechanical completion. Detailed schedule
analysis including Level 4 Schedule optimization workshops completed. Final timeline and
strategy for schedule assurance action plans implementation will be finalized by CTJV and
Company by mid-December.
CCIC Construction metrics for the week:
CCIC This Week Last Week
Plan Basis – Recovery Forecast Plan Actual % Achieved Plan Actual % Achieved
Direct construction 1.50% 0.98% 65 1.56% 1.13% 72
Structural Steel Erection - Ton 160 126 79 196 190 97
510707523.doc Page 5 of 8
Progress at Korean vessel fabricators Ilsung and Sungjin continues to slip behind schedule.
CTJV monitoring the situation and applying strong expediting efforts.
Offgas Compressor retest was successful and vibration issue is now closed.
Delays in delivery of late-identified additional structural steel may negatively impact project
schedule. Fabricator (Hanmaek) is implementing agreed mitigation measures (as reported
previously). CTJV and PMT monitoring the situation closely.
CTJV submitted draft Level 4 construction schedule with EPC duration of 39.5 months (vs.
Contract 37 months). Following a review by PMT, CTJV and CCIC, a revised schedule was to
be issued by CTJV on December 6, but only partial and preliminary information was provided.
Timetable for formal submission of complete schedule is uncertain.
Near Term Plans
- Offshore
AKG-2 Offshore Construction Readiness Review (CRR) to be
held in early 1Q2008.
- Onshore
Interconnecting Piperack constructability workshop scheduled for December 16.
7. RGX2 SPECIAL PROJECTS
Accomplishments
Wet Gas Flow Assurance Upgrade
Completion of Phase 1 Flow Assurance Upgrade facilities continue per plan with Onshore
Priority 1 supplemental water filtration and remaining MEG injection/heat tracing and insulation
facilities completed and handed over to Operations, along with the kinetic hydrate tank nitrogen
blanketing and MEG storage & injection facilities on WH9 and WH5.
MEG
Offshore actual cumulative progress is 70% vs. planned cumulative of 96%.
systems installed and commissioned on three RGX platforms
(WH5, WH7, WH9). MEG system for WH4 completed and in
510707523.doc Page 7 of 8
FEED Invitation to Tender bidders meetings in progress at contractor’s home offices December
3-10. At first four bidders meetings, contractors expressed strong interest in submitting FEED
proposal.
Met with QP to review Residue Gas Compressor Study (driver and steam update) and H2S
Flexibility Study.
Award recommendation from WGI for Site Geotechnical and Topographical Survey work with
EM for approval. Targeting placement of work order through WGI by December 17.
Emerging Issues
Optimize operations support for offshore facilities (shore-based vs. RGA Living Quarters
expansion).
Timely completion of shareholder commercial agreements to avoid schedule impact.
Timely availability of staffing during a period of high industry activity.
Near Term Plans
Finalize development and approval of FEED organization plan by year-end at Gate 2 approval.
Barzan Project Steering Committee meeting scheduled for December 13 in Doha.
Onshore Layout Workshop with QP in Doha January 9-10 (proposed).
Gate 2 IPR rescheduled to January 28 – February 1.
510707523.doc Page 8 of 8