Professional Documents
Culture Documents
SAMSUNG SEM-9461E - Process Design Manual - Preparation of P&ID and UFD Rev1 2005
SAMSUNG SEM-9461E - Process Design Manual - Preparation of P&ID and UFD Rev1 2005
SAMSUNG SEM-9461E - Process Design Manual - Preparation of P&ID and UFD Rev1 2005
SEM – 9461E
Process Design Manual
Rev : 1
CONTENTS
1. General 5
1.1 Purpose 5
1.2 Scope of application 5
1.3 References 5
1.4 Definitions and Acronyms 6
1.4.1 Flow diagram 6
1.4.2 Line number 6
1.4.3 Drawing symbol 7
1.4.4 Issuing stage of drawing 8
4. Data required for preparation of P&ID & UFD and the contents of note at each issuing stage 22
4.1 Data requirements 22
4.2 Note contents for each issuing stage of P&ID and UFD 23
4.2.1 Preliminary 23
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(1) Example case for that connecting nozzle size is determined according to the issue state
progress of P&ID and UFD 209
(2) Action of main valve 212
(3) Equipment and instrument having by-pass line 213
(4) Sampling connection type 215
(5) Flexible hose 216
(6) Air trap and drainer 218
(7) Steam trap 218
(8) Pressure relief valve and rupture disc 221
(9) De-Super heater 227
(10) Pump 230
(11) Compressor and blower 242
(12) Water spray facility 254
(13) Sealing method for low pressure tank 255
(14) Strainer 258
(15) Insulation and tracing 259
(16) Shower and eye washer 262
(17) Typical vent/drain System 263
(18) Piping or connection for purge 269
(19) De-aerator 275
(20) Cooling Tower 276
(21) Air dryer for instrument air 278
(22) Gas supply with gas cylinder 282
(23) Pneumatic conveying of particle Material 283
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
1. General
1.1 Purpose
The purpose of this manual is to describe the preparation method for Piping and Instrument
Diagram (P&ID) and Utility Flow Diagram (UFD) based on the process engineering work
practice.
1.3 References
The reference manuals are available. They are:
Line Number
4 P 3 125 B I A (H)
Insulation symbol
Piping material
Kind of piping material Piping specification
Flange class
Sequence number
Area (Section) classification number
Fluid symbol
Piping nominal size (use inch unit in principle)
Note: For further details, refer to Korean version manual SEM-3010 (i.e. Piping
class determination).
(1) Preliminary
This is P&ID and UFD issued first time after process design work resumed. The
technical information on major equipment, piping, instrument, etc are shown in this
drawing sheet.
this drawing sheet contents are same as compared with preliminary. If the client's
comments are received, their comments should be reflected when issuing AFP.
2. Paper size and composition
2.2 Composition
All kind of equipment, piping, fittings, valves, instrument controls, signal, various notes,
equipment name and number, short specification of equipment, and equipment description will
be shown in P&ID and UFD. Also the continuity symbols of drawing, title block, revision
column and issue block should be described to establish the completeness of drawing.
Special attention should be paid to a few important things such as how to prepare a looking
good composition, easy understand to see, and accuracy of the contents put in because
P&ID and UFD are very important work products of engineering business. Since composition
needs to be properly balanced, the following rules should be respected to avoid confusion on
the packed information. In addition to these, detailed information on the size of letter,
thickness of line, etc. is given in the guidelines of P&ID CAD preparation.
(Note:) * 1 Since the water treatment system consists of various devices, it should
be written down based on the function and/or of each unit categorized.
* 2 In the case that upper area of drawing sheet is not appropriate for
reading it at the equipment arrangement point of view, the drawing sheet
bottom or other areas can be used.
* 3 For the facility that can be categorized into individual equipment, they
should be written down based on the equipment category. In other
hand, regarding the equipment that is not easily categorized, appropriate
judgment is necessary to select the best place visually in the top and
bottom of drawing sheet.
* 4 When selecting the top or bottom locations of drawing sheet, the
appropriate decision has to be made based on the concept if it is easy
to find and read it.
However, this rule does not need to be obeyed if there are no ways to
put it at the top or bottom. Other inevitable case is that, in the P&ID
and UFD, the location of related equipment needs to be clearly visual
each other's location.
Example:
* 1 Line Number
* 2 Expression of the equipment departing or destination to the equipment
In principle, equipment item number has to be used for indicating all the
equipment departing from or destination to. In case that it is connected
to the other drawing sheets after it is merged with other lines, then the
line number needs to be write down.
* 3 Drawing continuation number
Continuity symbol of drawing sheet ( ) should be written at
the left or right hand side of the drawing sheet borderline. In principle,
the symbols should be written at the same elevated position as for the
drawing.
Example:
* 1 Line Number
* 2 Drawing Continuity Number
Put the drawing continuity symbol of utility line at appropriate location in
the P&ID sheet.
Example:
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(a) Use the methods described in Section (2)-(a) in marking on the drawing sheet
including utility supply facility.
(b) Use the methods described in Section (2)-(b) in marking on the drawing sheet
except for the above Section (3)-(a).
(c) In some cases, either Section (3)-(a) or (3)-(b) is applicable to the same
drawing sheet. And the symbols of based on both Sections (2)-(a) and (2)-(b)
can be coexisted in the same drawing sheet.
Example :
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
* 4 In case that detail drawing is not shown in the related P&ID and UFD,
show that portion to indicate that the referred parts of detail drawing exists.
It is shown below:
Detail “A”
(DWG.No.16A)
Reference: SEM-1002 Description of drawing Issue and the assigning method of revision number.
SEM-1003 Filling method for drawing title block
Example:
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
Job Name
Example :
IRAN-KOREA PETROCHEMICAL CO., LTD.
BANDAR, SHAHPUR, IRAN
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
3.2.3 Job No.: Write down the Job Number or Proposal Number
As a general rule, process P&ID has to be named according to process name of that
P&ID. With regard to auxiliary facility and utility facility, it should go with the name
based on the system name according to the fluid name written in Remark column of
Section 3.2.6 Table. Also, It is all right to include more than two system names in
the same drawing sheet.
* 1
Of these, drawing number is directly related to the type of flow diagram, plant name
or system name. Use the contents of following Table:
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
* 1 In case that the plant complex consists of many plants, the drawing can be
identified by writing down the abbreviation of plant name along with
Job/Proposal Number.
Example:
FLOW DIAGRAM
10 PLOT PLAN
11 GENERAL ARRANGEMENT
HEATING SYSTEM
28~49 RESERVED
* 1 In general, material balance has to be written in PFD. But, just material balance
only can be prepared in some cases.
* 2 Consider the followings as a name of Water.
Also, in addition to these, Brine (i.e. Calcium Chloride Solution, Salt Solution,
etc.) can be included in the drawing number 16 or 17.
4 Data required for preparation of P&ID & UFD and the contents of note at each issuing stage.
Required data for preparation of P&ID & UFD are listed below:
(a) Contract (Especially, applicable regulations and standards, standards, design philosophy or
conditions, operational guarantee, test methods, sampling methods, etc. that are specified
in the contract)
(b) Material, heat and pressure balance
(c) Equipment type, piping design calculation
(d) Process Flow Diagram
(e) Utility Balance Diagram
(f) Equipment List
(g) Symbol of Equipments and piping
(h) Symbol of instrument
(i) Line number selection method and piping specification
(j) Process Sketch and Engineering Drawing
(k) Pump and Compressor Data Sheet
(l) Heat Exchanger Data Sheet and Engineering Drawing
(m) Heater Data Sheet
(n) Other special equipment data sheet
(o) Instrument Process Data and Instrument Schedule
(p) In-line equipment Process Data Sheet and Specification Sheet
(q) Vendor drawing or data sheet for equipment and instrument
(r) Manual and Standard (Refer to paragraph 1.3)
(s) In addition to the above, job special specification
(t) Operation manual or guide
(u) Safety equipment design or installation for preventing overpressure
(v) Accessories installation for preventing overpressure
(w) Comparison of regulation and standard for pressure vessel and boiler
4.2 Note contents for each issuing stage of P&ID and UFD (1/5)
(1) PRELIMINARY a) Basic structure and Flow for Process and Service
b) Items associated with Equipment
i) Equipment's Item Number and service name
Usage purpose in piping design ii) Equipment type and drive type with figure
In terms of time schedule of piping design, iii) Piping connected with equipment, the shape of Vent
it will be used for preparation of /Drain, Instrument nozzle, built-‐in level gauge,
information and various design during basic sight Glass, Nozzle for lightning, etc
design. iv) Insulation and external steam coil or trace
a) Plot Plan Preparation v) In case of lump-‐sum order to maker, scope of handling and tie-‐in
b) Routing Study and Critical Line (Directed by Project team)
Study c) Piping Items
c) Civil Information i) Piping classification (Classification between Main
i) Building(Compressor Room etc) piping, general piping and instrumental piping,
Study aboveground and underground piping, double piping, etc)
ii) Information preparation for ii) Piping branch and join
Concrete, Steel Structure and iii) Flow direction
Pipe Rack iv) Piping size (about main piping)
d) Piping Specification vii) Class Break (and Design Break)
viii) Figure of piping
ix) Insulation and Trace
x) Vent and Drain for fluid and method for release
xi) Process requirement
Ex) * Relative location of valve in terms of Layout
* Requirement for Symmetrical piping
* Requirement for straight run length or distance
except instrument
* Requirement for Cleaning line
(At Job Starting time, Classify description of P &
ID / UFD and description of Note, to be discussed
with each design department and project)
d) Instrument and electricity
i) Measuring point
ii) Instrumental and control system
iii) Location of safety device installation & way to release
4.2 Note Contents for each issuing stage of P & ID and UFD (2/5)
4.2 Note Contents for each issuing stage of P & ID and UFD (3/5)
4.2 Note Contents for each issuing stage of P & ID and UFD (4/5)
(Note): * Other things that caused some problems in the past and
Recently, work case that line numbering countermeasure for it.
is completed in the AFP stage has been (Classify the things about the memo and about marking on
increased. P&ID and UFD at the time of job start. Adjustment with project
team and technical discipline departments)
ix) Completion of line numbering (Area classification and
putting serial number)
4.2 Note Contents for each issuing stage of P & ID and UFD (5/5)
(3) APPROVED FOR DESIGN (AFD) a) Follow-‐up the note contents in AFD
(Client comments, Hold point, additional items, etc)
Purpose in piping design
Issue before starting piping drawing b) Equipment related items (by information from instrument department)
work i) Finalizing connection parts with Maker
a) Preparation of piping drawing ii) Finalizing the way of release, equipment vent and drain
b) Piping B/M
c) Piping Hanging Design c) Piping related items
i) Completion of line numbering (Area classification and
fill up of serial number)
ii) Tag number of in-‐line equipment
iii) Vent and drain required in terms of piping and test plan
and its way of release
iv) Finalizing the connection parts with In-‐line equipment maker
a) Writing down the errors found, revised and corrected items that were
found during construction.
(5) AS BUILT DRAWING
Complete the note contents by writing down the necessary items based on SECL standard P&ID
Symbols and Legend and the followings.
Note: * 1 = Regarding vendor’s drawing, prepare list in case that it is referred in P&ID or
UFD.
(b) Type and size rule of main instrumental valve in case of abbreviations
(c) General process requirements for piping that handles special fluids
(d) In case that the provisions specially for the following are required:
* Countermeasure for highly hot area
* Countermeasure for cold area
* Prevention of Freezing or solidification
* Countermeasure for preventing interruption of electric power
In this section and section 7, various expression methods and items that need to be reviewed in
preparation of P&ID and UFD are listed below: Prepare separately for the method of detailed
consideration.
(a) Review item in case that internal check and cleaning is required after partly separating
during plant is running.
(iv) Others
* Venting method (Atmospheric release, Closed vent system, Flare or Stack
etc.)
* Drain method
* Heating method such as steam tracing, etc
* Cleaning method
(Disassemble, Chemical Cleaning, Jet Cleaning, Pig, Air or Nitrogen, Purge,
(5) Others
Symbol Application
Lines except process main line and utility flow diagram lines
Line width 0.5 mm
7.2.2 In case that classifying which plant the item is included in is not necessary.
DA 303
CO2 Product Wash Cooler
7.2.3 Due to the client’s request (or licenser), other item number assigning method that is
difference from SECL's has to be used in some case. In this case, it needs to use
two kind of item number. (In principle, write down client's item number first and then
put the SECL's inside of parenthesis)
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
7.2.4 Due to client's request or domestic project, there is a case that short specifications
needs to be put in P&ID and UFD. In this case, standard expression is as follows.
- Tower: Capacity (No. of Tray or Packing Height), Size(Dia*Height), Design
Pressure,
Design Temperature, Material
(2) Tank/Drum
(a) Ball Type, Spherical
(i) Single Wall (ii) Double Wall
(b) Cylindrical
(i) Vertical
(ii) Horizontal
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(e) Other
(i) De-aerator
or
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
or
or
shape.
or
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(Note): In case of pipe type exchanger, add it under the item number so that the
parallel or hair pin number can be seen. (Example): 8Hair Pins * 2
Parallel
or
(g) Other
(i) Plate type and Plate Fin type
2 Fluid Case:
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
3 Fluid Case:
or
(i) AEL
(ii) AEU
(iii) BEM
(iv) AJS
(v) AGT
(vi) CFU
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(vii) BKU
(viii) AKT
or
(4) Pump
(a) Horizontal Centrifugal Pump
In general, it is same as (ⅰ). But, in case that it is necessary at the
client’s request, the expression method described in (ii) and (iii) can be
referred. (i) Volute and Turbine or
Diffuser type
(f) Other
(i) Snake Pump
(6) Compressor
(a) Centrifugal (Turbo Compressor)
(i) Common or Normal Type (PFD common use)
(b) Reciprocating
(i) Single-Stage type
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
or
or
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
or
or
(d) Cyclone
(i) Single Stage type
(g) Venturi-Scrubber
(e) Thickener
(h) Disintegrator
or
(k) V-Mixer
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
or
Note: In case that the shape of two rotating axis is different, put it shape
and some equipment is attached with jacket.
(n) Screw Extruder
Note: In case that jacket exists, write down its shape and show the in/out
of utility line.
Note: In case that hot air blow is contacted, show that line.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(c) Spray-Dryer
(i) Nozzle type
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(15) Screen
(a) Vibrating Screen
(i) Single Deck
Use instead of
Use instead of
(c) Trommel
(16) Conveyor
Show instead of ,
or
F type L type
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(17) Feeder
(a) Rotary Valve (Feeder)
(b) Tripper
(i) Fixed type
(c) Weigher
(i) Weighing scale with support
·Gauge, sloped automatic type
(h) Pelletizer
or
or
or
or
(l) Hand Cart
Rear Car
(d) Reclaimer
or
(e) Stacker
or
(ii) For Tank Lorry & Car
or
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
or
(g) Others
For the equipment that has special shape, draw appropriate symbol closely
looking like the equipment shape.
(24) Others
(a) Pit
(i) No Partition exists (ii) Partition exists
(d) Pallet
(i) plate Pallet
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(e) For the equipment that has special shape, draw appropriate symbol closely
looking like the equipment shape.
(3) Tray
(a) Downcomer Tray
Note: Tray number shall be assigned to the top tray, bottom tray,
instrument installed tray, liquid
supplied or discharged tray. Tray number shall be
assigned as like top, bottom 1, 2, ---, etc.
or
(4) Spray
(a) Spray pipe
or
(5) Mixer
There are various types of Impeller. Typical types are given in this section.
Other than these, appropriate symbol has to be selected based on the shape.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
Stage
shall to be described exactly.
(a) Propeller type (ex. 1 stage)
(f) Others
For the equipment that has special shape, draw appropriate symbol closely
looking like the equipment shape.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(6) Baffle
(a) Common type
or
or
Of many baffles, cooling baffle is described as follows.
(8) De-mister
or
(10) Coil
(a) In case that Nozzle is Horizontal
or
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
or
or
(13) Vortex-Breaker
This is shown in (a). But, (b) and (c) may be used at
licensor's request, etc.
(a) Attached above Liquid Outlet Nozzle
(b) Cover
(15) Others
(a) Trickle Valve
7.3.3 Driver
(1) Motor
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(2) Steam-Turbine
In general, it shows as (a). When it needs to be specially classified, it could
also show as (b).
(a) For Large, Compressor (b) For Small, Pump
(3) Gas-Turbine
Note: It is about Turbine and Engine. It can refer to Vendor P & ID because it
is for vendor's package. The scope of package shall be determined at
job start. Regarding other equipment,
instrument and piping, it needs to be described in SECL's P & ID and
UFD.
(n) Duct
(o) Chute
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(3) Valve
(a) Gate Valve
(r) Damper
or
(b) Butt weld Cap
(e) Hose-Connection
(h) Silencer
(i) Hood
(b) T-Strainer
(2) Sight-Glass
(a) Sight Glass (Looking Glass)
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(3) Flame-Arrester
(5)
(a) Pressure Relief Rupture Disk
(6) Oiler
(7) Trap
(a) Steam Trap & Condensate Drainer
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(10) Shower
(11) Mixer
4-P-4032-AIA-H , 4-P-4032-AIA-C
(b) For Exchanger, it should be marked by identifying shell and tube type.
(2) Design Break (Even if class symbol is same, use design break on the border in
case that fluid symbol, design temperature, design pressure and insulation
necessity are different).
(5) * Sewer (when necessary, use * with appropriate symbol according to the job
specific requirements)
(8) By Vendor
(9) By Customer
(10) Grade
or
or
or
(14) Utility Connection
(18) Electro static bonding of piping (In principle, it does not need to note down. But
use this symbol in case that licensor requested)
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(19) This is a symbols for chemical loading by hand. Put the chemical name in
parenthesis.
The above examples show flow rate record controller attached with alarm.
(b) Gauge number shall be assigned one digit to each one loop. However,
gauge number has to be assigned separately in case that it is connected
supportively to one loop.
Notes: 1. Additional symbols are shown as follows.
2. When there are more than two same types of elements in the
same loop and it needs to be classified, gauge symbol can be
shown to each element. Example:
(i)
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
(ii)
(iii)
MEASURED OR READOUT OR
LETTER
INITIATING MODIFIER PASSIVE OUTPUT MODIFIER
VARIABLE FUNCTION FUNCTION
A ANALYSIS ALARM
C CONDUCTIVITY
(ELECTRICAL) CONTROLLER
DENSITY (MASS)
D DIFFERENTIAL
OR SPECIFIC
GRAVITY
G GAGING GLASS
(DIMENSIONAL)
I CURRENT INDICATE
(ELECTRICAL)
J POWER SCAN
M MOISTURE OR MIDDLE OR
HUMIDITY INTERMEDIATE
Q QUANTITY OR INTEGRATE OR
EVENT TOTALIZE
T EMPERATURE TRANSMIT
W WEIGHT WELL
Z POSITION DRIVE,
ACTUATE
OR
UNCLASSIFIED
FINAL CONTROL
ELEMENT
1 EM Emergency (13)
4 FO Valve Open at the time of power source lost (normal operation) (14)
5 FC Valve Close at the time of power source lost (abnormal operation) (14)
Valve lock at the time of power source (14)
6 FL (No change of positioner)
Classify FLO/FLC according to valve open/close for the minimum signal
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
9 RO Restriction Orifice
14 PU Manometer (Independently)
17 PH PH Meter (Independently)
20 MO Motor Operated
1) If analyzer is marked as the first letter "A", write down the measuring
composition at the figure symbol.
Example:
2) Use the function symbol “S” for On-Off Control and mark down (On-Off)
on figure symbol. Use the same expression in case of on-off control with
electrical relay. The emergency equipment, watch lamp, etc. should be
clearly classified.
Example:
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
4) "R" and "I" can not be written down together even if it has directive
function in case that the function is marked as “R”. For example, it
does not show as “PRI-101".
5) Use function symbol "T" when transportation body is installed solely and
is supportively connected to the loop having other function.
6) Variable symbol "U" will be used for the common alarm system that
collects various alarms as follows:
or
or .
7) Trend recorder should be shown with "R". And “R” has to be shown in
the case of Trend by Hard Recorder. But, In case of DCS Trend, it
should use “R” or “I”. They should not used together. As Computer
Hard Disk Memory is increased, most “I” variables got the trend function
recently.
Example:
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
8) It should use the function symbol, "W" when well is installed alone.
"TEW" is not appropriate way of expression even
if protective well is a part of the temperature element "TE".
10) When there are more than 2 limit switches, 2 limit switches should be
shown and this rule is also applicable in case that it is related with
other figure symbol. Also, signal direction and function can be shown
expressed by a sentence.
Example:
16) Use function symbol “Y” for expression of calculation and relay for Add,
Subtract, Divide, Multiply, Signal Select, Signal Limit, Ratio Set, Signal
Convert, Root Extract. It should show at the upper side of
symbol’s outside. In general, it can be omitted when the existence and
function is clear.
BA Flame alarm
BI Flame indication
JR Power indication
JRQ Power record and totalized
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
OR Orifice Restriction
PA Pressure alarm
PC Pressure control
PCV (Automatic) Pressure control valve
PG Pressure Gauge, Draft-Gauge U type Manometer
PI Pressure indication
PIC Pressure indication and control
PR Pressure record
PRC Pressure record and control
PDA Pressure difference alarm
PDC Pressure difference control
PDCV (Automatic) Pressure difference control valve
PDG Pressure difference gauge
PDI Pressure difference indication
TA Temperature alarm
TC Temperature control
TV Temperature control valve
TE Temperature element
TG Temperature gauge (Dial gauge)
TI Temperature indication
TIC Temperature indication and control
TR Temperature record
TRC Temperature record and control
TDI Temperature difference indication
VT Vibration Transmitter
WI Weight indication
WIC Weight indication and control
WR Weight record
WRC Weight record and control
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
ZA Position alarm
ZI Position indicating
ZS Position Switch (Limit Switch)
NO SYMBOL DESCRIPTION
(m) COMPUTER
∑ ADD OR TOTALIZE
SUBTRACT
× MULTIPLY
÷ DIVIDE
> HIGH SELECT
± BIAS
l:l VOLUME BOOSTER
AVG AVERAGE
HIGH LIMIT
LOW LIMIT
DIR DIRECT
REV REVERSE
ANALYSIS
* IDENTIFIES KEY COMPONENTS
1
DENSITY/
RADIOACTIVE TYPE DENSITY ELEMENTS
SP.GR 2
CONNECTED TO RECORDER ON PANEL
E
INDICATING VOLTMETER CONNECTED
VOLTAGE 1
TO TURBINE GENERATOR
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 118 of 283
F
GENERAL SYMBOL THE WORDS
FLOW RATE 1
LAMINAR, ETC., MAY BE ADDED
TRANSMITTER
9 VENTURI TUBE
10 FLUME
11 WEIR
17 VORTEX SENSOR
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 120 of 283
19 FLOW NOZZLE
20 MAGNETIC FLOWMETER
I
CURRENT TRANSFORMER MEASURING
CURRENT
1
CURRENT OF ELECTRIC MOTOR
J
INDICATING WATTMETER CONNECTED
POWER
1
TO PUMP MOTOR
K
1 CLOCK
TIME OR TIME-
SCHEDULE
MULTI POINT ON-OFF TIME SEQUENCING
2
PROGRAMMER POINT 7
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 121 of 283
L
GAUGE GLASS, INTEGRALLY MOUNTED
LEVEL 1
ON TANK
HUMIDITY
SELF-CONTAINED HUMIDITY CONTROLLER
2
IN ROOM
P
PRESSURE INDICATOR, DIRECT
PRESSURE OR 1
CONNECTED
VACUUM
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 123 of 283
LINE MOUNTED
3 PRESSURE INDICATOR CONNECTED TO
DIAPHRAGM SEAL WITH FILLED SYSTEM
1 RADIATION INDICATOR
RADIATION
S
1 SPEED TRANSMITTER
T
TEMPERATURE CONNECTION WITH
TEMPERATURE 1
WELL
LOOPS)
1
LOW FLOW SWITCH ACTUATING ONE
POINT OF A MULTI POINT MULTI
VARIABLE ALARM ANNUNCIATOR
ALTERNATIVE 2
2 LOW FLOW SWITCH ACTUATING ONE
POINT OF A MULTI POINT MULTI
VARIABLE ALARM ANNUNCIATOR
U
MULTIVARIABLE
ALTERNATIVE 1 (TREATED AS DISTINCT
LOOPS)
3
LEVEL SIGNAL RECEIVED BY ONE POINT
OF A MULTI POINT MULTI VARIABLE
INDICATOR
ALTERNATIVE 2
4 LEVEL SIGNAL RECEIVED BY ONE POINT
OF A MULTI POINT MULTI VARIABLE
INDICATOR
VIBRATION,
ANALYSIS
POSITION,
DIMENSION
LIMIT SWITCH THAT IS ACTUATED WHEN
VALVE IS ACTUATED WHEN VALVE IS
3
CLOSED TO A PREDETERMINED
POSITION
1 Gate Valve
2 Globe Valve
3 Butterfly Valve
4 Angle Valve
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 129 of 283
11 Damper or Lower
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 130 of 283
SPRING-OPPOSED, SINGLE-ACTING
CYLINDER, WITHOUT POSITIONER OR OTHER PILOT
DOUBLE-ACTING
8 SOLENOID
PREFERRED ALTERNATIVE. A BALLOON WITH INSTRUMENT TAGGING, E.G., TY-1, MAY BE USED INSTEAD OF THE
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 131 of 283
INTERLOCK SYMBOL
ABB
REVIA
TION
CYLI
NDER
WITH
POSITI
ONER
AND
OVER
RIDIN
G
PILOT
VALVE
11 ELECTRO HYDRAULIC
NO SYMBOL DESCRIPTION/APPLICATION
NO SYMBOL DESCRIPTION
*
C
TEMPERATURE INDICATING
CONTROL 1
CONTROLLER
DIFFERENTIAL TEMPERATURE
1
INDICATOR
DIFFERENTIAL
VIEWING
SIGHT GLASS FOR INTERNAL
1
DEVICE, VIEWING
GLASS
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 137 of 283
H
HAND ACTUATED ELECTRIC SWITCH,
2
HAND MOMENTARY
J
SCAN
K
RECORDING FLOW CONTROL, WITH
CONTROL 1
ADDITIONAL FLOW AND PRESSURE
PENS, RECORDER IS A DEDICATED
STATION TYPE
LIGHT OR
LOW
PILOT LIGHTS TO SIGNAL THAT
TEMPERATURE HAS RISEN TO
2
INTERMEDIATE, HIGH, AND VERY HIGH
VALUES
POINT
METER WITH
Q
(1) RECORDING OF FLOW RATE,
INTEGRATE
1 (2) INDICATION OF INTEGRATED
OR TOTALIZE
FLOW, AND
METER WITH
FLOW, AND
R
MULTI POINT MULTI VARIABLE DATA
RECORD OR
1 LOGGER, UJR-100, WITH SWITCH FOR
PRINT POINT 7
S
LOW TEMPERATURE SWITCH WITH
1
SWITCH ONE OUTPUT FOR ALARM AND TRIP
T
TRANSMITTER
2 ALTERNATIVE TO 1
VALVE,
1 CONTROL VALVE WITH HAND JACK
DAMPER, OR
LOUVER
OVERHEAD CONTROL.
5 TANK OUTLET VALVE TO OPEN AS
REQUIRED BY THE HIGHER OR TWO
LEVELS
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 142 of 283
Z
PROPORTIONING PUMP WITH
DRIVE, 1 AUTOMATIC AND MANUAL STROKE
CONTROL
ACTUATE, OR
UNCLASSIFIED
FINAL
CONTROL
NO SYMBOL DESCRIPTION
WITHOUT OVERRIDE.
PRESSURE CONTROLLER ACTING
THROUGH SERVO VALVE ACTING AS
13 VOLTAGE TO HYDRAULIC CONVERTER TO
MODULATE DOUBLE ACTING CYLINDER
ACTUATED CONTROL VALVE HAVING
POSITIONING SYSTEM
ALTERNATIVE 1
INTERRELATED INSTRUMENTS WHOSE
SYMBOLS ARE SCATTERED ON
DIAGRAM. (A MULTI POINT
27 INSTRUMENT, SUCH AS A DATA
LOGGER, THAT IS DESIGNATED WITH
POINT NUMBERS ON A DIAGRAM IS NOT
EXPECTED TO HAVE THE SYMBOLS
FOR THE VARIOUS POINTS TIED OR
REFERENCED TOGETHER)
ALTERATIVE 2
INTERRELATED INSTRUMENTS WHOSE
SYMBOLS ARE SCATTERED ON
DIAGRAM. (A MULTI POINT
28 INSTRUMENT, SUCH AS A DATA
LOGGER, THAT IS DESIGNATED WITH
POINT NUMBERS ON A DIAGRAM IS NOT
EXPECTED TO HAVE THE SYMBOLS
FOR THE VARIOUS POINTS TIED OR
REFERENCED TOGETHER)
Example of complex batch kettle control involving both shared display/control and
programmable logic control. The purpose of this drawing is to allow a general
understanding of the control scheme and to define and identify the connected
components. Detailed understanding would be obtained from the study of other
documents.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 150 of 283
Detailed symbolism and more complete identification used to describe the control
system when type of hardware and kinds of signals have been chosen.
(b) Double
4 - P - 1325 - BIA - H
Insulation Type
Class Identification
Area Clarification, Serial No. : Max. 5 letters
Line Service Identification : Max. 3 letters
Line Size
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 155 of 283
P Process
G Process Vent, Purge Gas
L Process Drain, Purge Liquid
M Medicine (Chemical, Additive Inhibitor)
S Steam
W Water
A Air
I Inert
C Condensate
R Refrigerant
O Oil
F Fuel & Fire Fighting
Note: The letter symbol that has been easily used before together with others should be
avoided.
Example: The initial letter of inert is “I”. But, in case of “IA”, it is confusing with
Instrument Air that is used before. Likewise, for the same reason, “PW” should be
avoided.
(1) Process
(a) General purpose “P”
(3) Utility
(a) There are various utilities. If it does not need to particularly classify, use those
symbols listed in the following Section (b) or (c). In case that there are any problems,
classify it precisely as much as possible by adding and/or correcting the abbreviation.
(b) Fluid symbols for general utilities
(i) Steam
Fluid Symbol
-------------- Steam S*
High Pressure Steam SH
Middle Pressure Steam SM
Low Pressure Steam SL
Superheated Steam SS
' Wet Exhaust Steam SW
Dry Superheated Exhaust Steam SE
(ii) Water
Fluid Symbol
-------------- Water W*
Cooling Water WC
Refrigerated Water WR
(Chilled)
Hot Water WH
Sea Water WS
Raw(Industrial) Water WI
Treated(Clarified) Water WT
Demineralized Water WD
Polished Water WP
Boiler Water WB
(iii) Air
Fluid Symbol
-------------- Air A*
Instrument Air AI
Plant (Utility) Air AP
(iv) Inert
-------------- Inert - I*
Inert Gas IG
(Inert) Nitrogen IN
(v) Condensate
------------- Condensate C*
Atmospheric Condensate CA
Low Pressure Condensate CL
High Pressure Condensate CH
(vi) Refrigerant
-------------- Refrigerant R*
Ammonia Refrigerant RA
Methane Refrigerant RM
Freon Refrigerant RF
Ethane, Ethylene Refrigerant RE
Propane, Propylene Refrigerant
---------- Oil O*
Lubricating Lube Oil OL
Gland Oil OG
Seal Oil OS
Flushing (Washing) Oil OW
(c) When it is necessary to clearly distinguish the fluids having different pressure level
at the utility system showing as the same fluids, express them as following:
For classification and expression based on the insulation purpose, use the expression methods
described in Section 7.3.6 in page 97 and the following descriptions:
(1) Insulation symbols:
4P - - BIA - H
Fluid name and class symbol inside of parenthesis ( ) indicates the outer pipe.
(2) In case that it is difficult to show it as class symbol (i.e. Shut, Trough, Duct, etc.), it should
show as follow:
When there is a strong request by the project owner or licenser, both SECL’s numbering and
other number methods can be employed. In this case, these two numbering may need to be
used together. (Expression method and content should be determined separately based on
the job specification).
Regarding connection with the vendor drawing, refer to Section 2.2.4 (4) in page 13. It should
be checked later with Vendor’s connection list.
(1) For Single Equipment Item
In principle, B.L should be indicated at piping or nozzle that is connected with the vendor
portion.
(c) In case that branch line becoming the above round line from underground line.
(i)
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 164 of 283
(ii)
(b) When piping material is to be connected to other type of material, replace with high
class material for both control valve and by-pass valve.
(c) In case that upstream and downstream material of control valve is different
Use high class material for both control valve and by-pass valve, and the position of
the class break position after control valve is as follow:
(d) When the control valve connecting point that is minimum 300 lbs by job specification is
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 165 of 283
(b) Even though all the“A5K” specification symbols are applicable for the nozzle and
flange of corrosive gas absorber tower, the following example is for that it is all right to
use “A2A” symbol for the purified top gas.
(c) As an example for batch type reactor, “B2K” is necessary for the ball valve attached to
the reactor body due to high pressure during reaction. However, it is all right to use
“A1K” or “A6K” for the inlet and outlet piping as shown in the following example:
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 167 of 283
(d) In case that connecting pipe specification symbol is different due to interior material change of
reactor:
(i) Tower example:
(ii) In case that material of construction of filer element upstream and downstream is
different: Piping specification change (A6S A1X) due to the filter body material
change from carbon steel to galvanized carbon steel.
(e) The connected piping specification symbol can be different due to different inlet and
outlet pressure of rotating machinery (i.e. pump, compressor). But it does not need to
provide break mark around rotating machinery. It just needs to show material symbol
at both drain valve and vent valve outlet of rotating machinery.
(c) When any one side or both side of valve inlet and outlet is different with the piping
specification, it should show as follow:
(i) In case that outlet flange is different,
(2) Others
When fluid name is changed, design break should be shown
Refer to Section (a) page 174, 7.10.1 xxxxxxxxxxxxxxxx Check page number xxx
Note: When it places between equipment, grounding should be shown on both equipment
side and it should also be shown on all piping.
7.9 Expression on Internal Pressure and Leak Test and Initial Start
Temporary piping and facilities which is used for performance test at construction site such as vent
valve, drain valve, temporary recycle piping, raw material or intermediate product injection facilities
and special equipment should not generally be shown in P&ID and UFD. Commissioning engineer
should handle these by preparing special P&ID and UFD. When necessary to show it particularly,
refer to the following example:
7.9.1 Example for vent valve and drain valve for test
Note: Temporary valves installed at high temperature and pressure, toxic, flammable fluid
system can be removed if they are unnecessary at the maintenance point of view.
Generally, branched line can be cut off and safely sealed after attaching plug by welding.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 170 of 283
Note: Though a permanent strainer is installed, temporary strainer should be inserted at the
suction line of rotating machinery such as pump and compressor, and place piping so
that assembling is easy. Strainer body is generally cone type punch-plate. But,
when it needs to be connected to large diameter pipe, Y or T type permanent strainer
can be used.
(d) When it exists as solid state inside of drum, it should consider if necessary to melt it for
liquefaction or crushing.
Note: When design pressure of Tank Lorry is lower than that of GN piping, safety
valve is necessary.
Example (ii)
Note: Strainer can be inserted at the pump suction side. As shown in above two
examples, after completion of supplying from tank lorry, fluid remained in
piping is transferred to 3/4B drain valve by connecting the nitrogen, plant air
and water.
Note: When handling the material that can flow but does not burn at the flare stack,
vent stack is necessary. In this case, nitrogen purging and steam out for the
inside of piping is needed.
7.9.5 Example of Temporary Piping and Facilities for use of the Site Performance Test and Special
SEM - 9461E
.,M:fjii ii'
ENGINEERING
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE : 06-30-2005 PAGE : 173 of 283
Equipment
SIL
TO ATM 101
I
(CONNECTION FOR TEMPORARY SILENCER & PIPING
FOR PERFORMANCE TEST RUN OF GB-201.
SIL-l0l SHOULD BE USED AS TEMPORARY SILENCER.)
SM
B1A-H
FROM GB-201
EA-20 1
HEATER
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 174 of 283
(Remarks)
Because the replacement of batch coolant (WH & WC) for each batch
operation is necessary, the valve should be closely arranged to prevent
operation mistake.
Put the steam tracing to prevent the pipe-freezing problem for the location
having winter season.
Show existence of insulation, fluid name for both sides of design break.
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 175 of 283
(b)
(Remarks)
This is the case that the liquid having high freezing point is transferred once
per a day. It is necessary to circulate the day tank liquid and the valve
should be closely arranged for replacement when start and stop of fluid
transfer.
(2) When installing the valve where instrument system can be visually operable.
(a)
(Remarks)
For the particle condenser which could be easily contaminated, perform boil-
up cleaning work once per every a couple of months by steam after water
flushing under the by-pass work.
In order to operate the by-pass line with watching the pressure indicator,
place the block valve where pressure indicator is closely located and can
easily see it.
Use the steam tracing for the liquid having high freezing point. To prevent
solidifying problem at the place where liquid is separated, maintain minimum
distance between main piping and branch or merging piping.
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 177 of 283
(3) When placing the valve within minimum distance to the point of easily freezing
branch pipe or equipment.
(a)
(Remarks)
Because the kind of batch effluent is different by being changed each other
per every batch operation, valve operation has to be performed to meet the
kind of effluent. Since these liquid fluids having high freezing point become
quickly solidifying, the valve of unused line should be closely located from
the branch point.
After liquid transfer is completed, GI line is being used to eliminate the
residual liquids inside of piping. In the above case, the distance between
connecting point and valve needs to be as little as possible.
(Remarks) When handling the highly viscous and easily solidifying slurry,
stand-by pump should be completely isolated.
(c)
(Remarks)
I I I
I [
(d)
I _
(Remarks) It is a process for producing warm water by injecting the steam into
cold water. It is necessary to locate the thermometer at the point so
that the mixed warm water temperature can show its average value.
The above value shown is an example and since it is different in
each case, the length limit is usually about minimum 1 meter except
for the case suggested by the licenser.
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 182 of 283
(2)
(Remark)
1. Because it prevents short pass of the condensate piping when starting up
batch operation, maintain the liquid height level corresponding to the different
pressure at that time. The position of TW is as shown in the Section 3
below.
2. This indicates the seal height when it is desired to maintain the liquid height
from the bottom of sight glass corresponding to the maximum pressure
difference between EA-101 vapor pressure and none condensate gas
pressure at the vent condenser (EA-102) outlet.
(b)
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 184 of 283
(Remark)
This is an example of seal height required for not to release drain together
with gas when the liquid drain is transferred to atmospheric tank from
pressurized gas system. In this case, the liquid should always be
remained in the equipment and it shows the location related to header (3P
A1K), drain frequency according to the drain liquid level maintaining at
each SG.
(Note) * The seal height between drain header (3K A1K) and every sight
glass (SG-101), 102, 103) shall be as follows:
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 185 of 283
(c)
(Remark)
Gas release has to be prevented by maintaining the constant height of
liquid level of the FA-701.
The seal height has to be determined to correct the differential
pressure between atmospheric pressure and maximum operating
pressure of FA-701.
(On the * part, the minimum height has to be determined according to
Engineering Drawing)
To prevent the liquid level decreasing of the FA-701 by over liquid
leasing due to siphon action, it needs to install the vent pipe at the
liquid outlet pipe for breaking siphon action.
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 186 of 283
(Remark)
As an example for barometric condenser, it requires barometric leg corresponding
pressure difference between maximum vacuum and atmospheric pressure of the
system. Theoretically, it is determined by differential pressure and liquid density.
But, it generally needs more than 10 meter of water height.
It gave more than minimum 45 of slope.
When pumping, partition is required to maintain the level. If partition is not installed
for cost saving, the pipe should be submerged lower than the pump suction nozzle.
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 187 of 283
(Remark) Since the tower bottom liquid is saturated at lower temperature, vaporizing
problem is possible due to pressure lost inside of the piping up to the
control valve, the height difference (part * for high and low) between tower
bottom and control valve is required to prevent this problem. (shirt height
is indirectly determined)
(Note) In addition to the above case, the following Section (4) and (5) is
applicable for restricting the skirt height.
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 188 of 283
(Remark) In addition to make NPSH available on pump suction, pump suction head
needs to be raised to minimize air inlet from ground.
(Remark) After the required amount of liquid is entered into the re-boiler due to
thermo-syphon phenomena and is evaporated, again the fluids get into
the tower. The pressure difference that is required for fluid transfer
will be given by the head between tower bottom and tube sheet at
the re-boiler bottom.
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 190 of 283
(Remark) Relative location of column and reflux drum in case of gravity flow
type reflux
(2) Circulating by slurry line via head tank and sloped line in case of liquid
supplying by maintaining the constant liquid level inside of head tank.
SAMSUNG SEM - 9461E
ENGINEERING DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 193 of 283
,
>
7.10.6 Example for that pocket or trap should not be allowed in the line
Normal operation will be disturbed if, in the middle of line, there is pocket or trap
where liquid or gas can be stayed.
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 194 of 283
(1) Vent line dealing with gas or high temperature saturated vapor containing mist
(a)
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 195 of 283
(b)
(Remark)
When flow meter is installed at the liquid piping, in principle, gas pocket
should not be located at the upstream of flow meter. When special
attention on the flow meter that is for sale or connected to control
system is required, it should be as shown in above Figure (b).
Regarding the flow meter for sale, as shown in (b), gas removal pot
should be installed for separation of non-condensable gas produced due
to pipe internal pressure loss and pipe exterior heat or low boiling point
vapors from liquid.
(c)
7.10.7 Example for that minimum length of easily plugging piping from turning point and
equipment needs to be shown.
Refer to 7.10.1(2) & (3) and 7.10.5 (1) & (2)
(2)
(2)
7.10.10 Example for that piping requirement is existed for reason of cleaning, maintenance and
process
(1)
(Remark) As instrument device installed at liquid piping system that has very high
o
condensing temperature (Approximately 53 C), piping liquid should be
completely drained out when stopping batch operation for the next batch
operation. Example for the case that, based on sloped by-pass line, flow
meter and control valve need to be vertically located at the upper side of
piping system.
(2)
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 199 of 283
(3)
Note: 1. The type of fitting for “PS” Lines shall be Flange for convenience in
Cleaning of these Lines. A piece of these lines shall be 10 meters
maximum in straight length with a Flange on both ends. However, a
piece with two bends shall not be used.
(Remark) This is an example for the case that master power made by mixing
power with agents be sent back by Hand Cart.
*1 Putting by hand
*2 Line to show Master Power flow even though there is no piping
system.
(Remark) This is an example for the case that vent line of indoor equipment be
routed to outdoor.
(Remark) This is the case that showing connection between piping by using
Spool Piece.
(Remark) Showing recycling process for collecting powders from wet air by
Cyclone of Fluidized Drying System.
SEM - 9461E
DESIGN MANUAL REV.: 1
PREPARATION OF P&ID & UFD
DATE : 06.30.2005 PAGE : 203 of 283
*1 When there is special hanger to equally distribute air for each cyclone in the
mult-Cyclone System.
*2 Though this is the case that Cyclone and Receiver is directly connected,
show Remark because many lines need to be noted in terms of expression.
(Remark) This is the case for that LI be located near pump because the tower
liquid level needs to be checked according to GA-701.
8. Job Specification
When additional note is necessary because of not agreeable with the contents of P&ID and UFD
preparation methods and each part of SEM and SES with regard to the items that should be
included in contract documents, local and process specific issues and licenser’s demands,
concerned condition should be notified to related teams by using “job specification” preparation.
- First Edition
0 98.09.30 All pages - Team: Process Team
- Made by: Y.Y.Gu, K.J.Moon, J.S.Lee, S.J.Lee
- Checked by: J.C.Ro
- Approved by: S.G.Oh
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 206 of 283
(Appendix)
Example of General Description on P&ID and UFD
- Content -
PAGE
(1) Showing connecting nozzle size that will be decided according to P&ID and UFD issuing stage ----
209
(a) Small size by-pass of Control valve -----------------------------------------------------------------------------
209
(b) Large size manual handle of Control Valve --------------------------------------------------------------------
210
(c) Pump -------------------------------------------------------------------------------------------------------------------- 211
218
(a) Ordinary type ---------------------------------------------------------------------------------------------------------- 218
(b) Equalizing line and water priming cup --------------------------------------------------------------------------
218
258
(15) Insulation and Tracing ----------------------------------------------------------------------------------------------------259
(a) Equipment Insulation ------------------------------------------------------------------------------------------------ 259
(b) Piping Insulation ------------------------------------------------------------------------------------------------------ 259
(c) Equipment Tracing --------------------------------------------------------------------------------------------------- 260
(d) Pipe Tracing ----------------------------------------------------------------------------------------------------------- 261
(1) In case that the Connecting Nozzle Size has to be determined according to progressing of P&ID and
UFD Stage.
(Remark) The above explanation is about the contents of P&ID and UFD issue stage in
case of new process. So, when the presence of by-pass and reducer is
determined in the licensed process or other processes, it can be specified in
the preliminary stage.
(a) Instrument
(i-2) When gas separation is required at the upstream of flow meter for sale.
Refer to subsection (2)-(b) of Section 7.10.6
or
(Remark) In case of flow meter for sale, by-pass line can be eliminated because valve
leaking from by-pass line is not desirable. But, because it is necessary for
start-up, it could be installed. In this case, make locked close the by-pass
valve, insert blind as show in above, or put double block and breathing system.
}-uA' ~
Water, HeavyOil
}-US, ~ Light Oi 1
I-a C1
WhenSampl eCooler is installed
Hot Water
Hot HydrocarbonLiqui d
~
Light Oi 1
L.
IJ~
I I·
+"
'L..
~
Gas, Li quefi ed Gas
\I;
WhenSampl eCooler is installed
Hot HydrocarbonGas
Hot Li ght Oi 1
(ii) Flexible Hose installed between Tank and Pump (Preventing settling and heat stress)
(ii-1) Passing the Tank Dike above
(Remark) Try Cock or Check Valve as shown in Section (iii) can be installed and refer
to Section 7.7.1 (3) for Spec. Break of steam trap down-stream.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 222 of 283
(Remark) Check the piping size based on the pipe arrangement because water hammer
could likely occur between the piping system up to condensate collection drum.
Also, refer to Section 7.7.1 (3) for Spec. Break of Steam-Trap Down Stream.
In principle, safety valve should be directly installed at equipment body. However, when it needs to
be installed at the piping system, the relationship between equipment design pressure (or maximum
operating pressure), set pressure of safety valve, and over-pressure after considering pressure loss
(less than 3% of set pressure) up to valve entrance from equipment connected to piping system.
Also, pipe size from equipment to safety valve must not be less than the connected nozzle size of
valve.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 224 of 283
Material and Condition Vent to ATM Discharge to Flare Discharge to Blow-‐ Recovery to
System down System Facility
1. Process Vapor
1) Flammable (Non-‐condensable) X
2) Flammable (Condensable) X
3) Nonflammable, Non-‐condensable, X
Non-‐hazardous
4) Nonflammable, Non-‐condensable, X X
Hazardous
5) Nonflammable, Condensable, X
Non-‐hazardous
6) Nonflammable, Condensable, X X
Hazardous
7) Liquid & Gas Mixture X
2. Process Liquid
* Liquid (from Relief Valve) X X
* Liquid (from Blow-‐down Valve) X
3. Steam etc
* Excess Steam Discharge X
* Boiler Blow-‐down X
(Remark) Condensable is the materials that more than 50% of them can be condensed at
atmospheric pressure and temperature.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 225 of 283
(b) Block Valve Installation Standard at Safety Valve Inlet and Outlet
(Base on the Inspection standards of Korean Industrial Safety Company)
* In principle, installation of block valve at safety valve inlet and outlet is not allowable.
* However, block valve can be installed at the following cases:
(i) When safety valve is installed at the pressurized equipment which is located near by.
(ii) When automatic pressure control valve is parallely connected at safety valve.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 226 of 283
(Remark) When continuously operating remote controller (HC), both A, B should only be
associated one of safety valve. Install the limit switch so that open direction
of three-way valve can be identified at HC operating place.
(iv) When two pressurized equipment (one stand-by) is installed with safety valve
(Remark) The distance to temperature sensing point is vendor’s requirement. In general, water
control valve can be put in charge of vendor to guarantee the performance of de-
super heater.
(b) Steam Atomizing Type
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 231 of 283
(Remark) The distance to temperature sensing point is vendor’s requirement. In general, water
control valve and atomizing steam can be put in charge of vendor to guarantee the
performance of de-super heater.
(Remark) Sleeve length and distance to temperature sensing point is often determined by
empirical basis. In general, temperature loss by spray nozzle is utilized when
accuracy is required and fluid volume is largely fluctuated.
In the above example, water injection rate is controlled by remote valve. But, as
shown in (b), temperature control can also be used.
(10) Pump
As pump accessory, there are vent, drain valve, discharge pipe, cooling water line, flushing line,
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 233 of 283
steam line, lube oil line. Of these, lube oil line is generally not shown in P&ID, but others are
as shown below:
(They are shown as combined each other in P&ID and UFD because each affiliated piping is
given as an example).
(Remark) Install “PG” to control back pressure and “FI” to confirm flow of cooling
fluid because of closed pipe line.
Regarding pressure loss of suction line, calculate flow volume with considering reverse
circulation.
(ii) Water Supplying Connection (Large Capacity Pump with Foot Valve with Strainer)
(ii-1) Fixed Connection
Put “PG” to check operating conditions of vacuum pump and ejector. Also install
sight glass to confirm liquid suction status.
Head tank should always be filled with water so that pump and suction line is full with
water.
But, at this time, water should not be drained out from discharge.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 243 of 283
(I) Others
(Remark) In terms of piping design, when pulling out drain nozzle from check valve
itself and direct connection between check valve and block valve, do not
show as follow:
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 244 of 283
--+:J
FT
I
I
I
I
I
I
I I-
I I
I I
I
I
I
I
I
I I
~-----------------------------j-----
and flow volume for not to engaged with over load trip. Flow guide vane control is
adopted.
1---------------------
T
, ,
/
(Remark) Example for Small Size Air Compressor for instrument system.
(Remark) It is for quick cooling water start up as sealing water supply is always maintained.
* On the above pressure system, instrument air purge is needed at fluid pipe line to prevent
clogging problem by powder materials.
While powder materials are supplied from dryer through vacuum air blower system for
transporting powder materials, significant electrostatic charge is forecasted. So, steam is injected
to discharge electrostatic electricity.
(i) Example 1
(Remark)
This is an example for Rotary Blower System to pneumatic-transfer the pressurized powder
materials. Due to high atmospheric temperature, discharge temperature is cooled down to the
limited temperature of powder materials. At the blower operating conditions, interlock of
pneumatic transfer system is to stop the rotary valve of powder material supply. If not doing
that way, re-start up is not possible without removal of powder materials settled inside of pipe-
line.
(ii) Example 2
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 255 of 283
(Remark)
This is an example for rotary blower system to air transferring the powder particles by closed loop.
This system is with scrubber for removal of powder material and cooler for removal of vapor
mixtures installed at the inlet side of blower because residual solvent of powder materials for
st nd
pneumatic transfer system in the drying course of powder materials (in between 1 stage and 2
stage of dryer) can be evaporated and entered into the transporting gas. This is not shown here.
(iii) Example 3
SAMSUNG
ENGINEERING SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 256 of 283
<
> ------------r------l
I I
I
I L
I
I
I
I
I II IJ
';zf
T
-1----------
(Remark)
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 257 of 283
This example is about rotary system for powder materials pneumatic transfer system by closed
loop.
Due to the temperature limit of powder materials, install the cooler at the blower outlet side to
properly manage the rising blower temperature. Also, by cooler installation at the blower inlet
side, consider eliminating the temperature rising problem by heat transfer of powder materials.
Also, by doing this way, think about proper maintaining the performance of blower.
(Note)
The strainer at the pressure valve downstream is in special shape because the pressure system
function could be deteriorated by incoming powder materials existed in gases. Though there is
a way to purge them into load pipe, this method is selected because special gas is needed
here.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 258 of 283
(Remark)
When safety valve operation is necessary due to pressure rising inside of ball tank by direct
sun light during summer season, cool down by tank top water sprayer.
Also, in some case, water spray system can be installed at suction line because pump can
be damaged or transferring is not possible due to vapor lock and cavitation by vaporization in
pump suction line. And in high temperature region, temperature rising is prevented by
complete stopping of heat transfer by the external cooling system.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 259 of 283
(Remark) * Steam tracing is installed because this is the case that tank internal vapor can
easily be condensable.
* In case of flammable liquid, pressure relieving/vacuum man-way must be
installed.
In general, breather valve is not installed, but it can be installed if it is
necessary.
* It can be used when condensation is necessary because vent gas contains
VOC materials.
(Remark) It should be able to check the liquid level of seal pot. When tank is in vacuum
condition, seal pot liquid level would be raised into tank vent line as much as
vacuum level. But, vacuum breaker should be installed to cover the pressure
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 260 of 283
higher than the tank design pressure. (It can be replaced with pressure
relieving/vacuum man-way) And, if low seal gas price can be sufficiently obtained,
instead of “PIC” such as the following (c) Section, it can always allow small
volume of flow by “FI”.
(c) Water Sealing Type
(i) Water Sealing
(Remark) This method is applicable in case of that the polluting possibility via seal gas header
is allowable.
* 1 In lieu of drain pot, direct connection to the slope tank would be better way.
(14) Strainer
(i)
(Remark)
This is the case that flammable or toxic
fluid that is easily polluted is sent to vent
stack or flare. Regarding spec break,
after reviewing sufficiently, it should be
noted according to each case.
(ii)
This is an example for that, for above Section (i), it is desired to purge completely
with N2.
Regarding the basic expression method for insulation, refer to Section 7.3.6 or Section 7.4.3.
(iii) Boundary Expression between Hot Insulation (Keep Warm) and Fire Protection
* Use this way when the method is determined based on the job specific requirement.
(a) Shower
* When not draining during operation * When draining is needed during operation
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 269 of 283
* Re-boiler Case
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 273 of 283
(Remark)
This is a tower example that is for absorption and removal of saturated water in fluid by solid
caustic soda. Because caustic soda as a 50% water solution will be remained at the bottom
of tower, the bottom water needs to be drained every 1-2 month and put caustic soda as
much as necessary. At this time, after completion of depressurizing, pressurized nitrogen
supplying and vent depressurizing has to be repeated several times. After that, drain out the
50% bottom water and supply caustic soda pellet through hand hole at the top of tower.
(Remark)
Hose connection for steam purge or gas purge of tower.
In some case, 1B could be applicable to prevent equipment nozzle damage during
construction and or transportation. Tough this example is suitable, consider the following
methods because, in general, hose station consists of 3/4B hose connection:
1B Special Flange
(Tough this pump requires steam for steam jacket and bearing cooling medium, but they
are not shown here.)
(Remark)
Because this fluid has high freezing point, piping fluid has to be purged by nitrogen when
transfer stop. However, the residual fluids should be purged via the lowest line and pump
drain.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 277 of 283
(Connection for
water flushing)
(Remark)
Because it is slurry handling piping system with water as dispersion medium, solid sediments
can be formed sometimes. At this time, hose connection will be used for washing out the
sediments with process water when operation is stopped. Also, it is necessary before re-
starting.
Regarding hose connection configuration, refer to Attachment (18), (a) (ii).
------------------~
FT
1-/
II 1/
CCI
-r 1~
SAMSUNG
ENGINEERING SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 280 of 283
(19) Deaerator
,-------------
I
I I
,
,
H
....
I II
adopted.
(Remark)
When water drain line to cooling tower is at ground.
During winter season, the 10B piping is not routed to cooling tower except for draining, but it has
purpose to let flow directly to basin.
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 282 of 283
X
L
f-- f
--r-
,---_/
---V<}-
I
h
<lc;U~N: l ~ ____________________________ _
Tlr,i ..
~----------l I
~---- I
, I
:J
!
,,
I
t X
!
----l/1 I~
~I
-T~j
,~
~-~
"(
L - - - - - - - - - - - - - - - - - - - - - - - - - -
'lY
- - - - - - - - - -
(Remark)
Example for absorbent regeneration method by using a part of dry air.
(Pressure Swing Adsorption System)
N2 CYLINDERS
(BY OWNER)
SEM - 9461E
DESIGN MANUAL
PREPARATION OF P&ID & UFD REV.: 1
DATE: 2005.06.30
PAGE : 289 of 283