Professional Documents
Culture Documents
"Hotel Complex & Convention Centre": Application For Amendment in Environmental Clearance
"Hotel Complex & Convention Centre": Application For Amendment in Environmental Clearance
At
Asset No. 13, Hospitality District,
DIAL IGI Airport, Delhi
PREPARED BY:
Environmental Consultant
FORM 1
I. Basic Information
E-mail Shekhar.mohan@dbg.co.in
Telephone No. 09873779639
Fax no.
Details of Alternative Sites
examined, if any. Location of these No alternative site has been examined. It is
16.
sites should be shown on a amendment in Environmental clearance of project.
toposheet.
17. Interlinked Projects No it is not an interlinked project
Whether separate application of
18. interlinked project has been Not Applicable
submitted?
19. If yes, date of submission Not Applicable
20. If no, reason Not Applicable
Whether the proposal involves
approval/clearance under: if yes,
details of the same and their status
to be given.
21.
(a) The Forest (Conservation) Act, Not Applicable
1980?
(b) The Wildlife (Protection) Act, Not Applicable
1972?
“Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.
II. Activity
1. Construction, operation or decommissioning of the Project involving actions,
which will cause physical changes in the locality (topography, land use, changes
in water bodies, etc.)
1.18 New road, rail, air, waterborne No No new road, rail, or sea traffic is proposed.
or other transport infrastructure The transportation measures already
including new or altered routes existing near site are as follows:
and stations, ports, airports Nearest Airport:
etc.? Indira Gandhi
International Airport 0.32 Km SW
Safdarjung Airport 9.22 Km NE
Nearest Railway Station:
New Delhi Railway Station 14.08 Km NE
Palam Railway Station 4.83 Km NW
IGI Airport Metro Station 3.46 Km NW
Palam Railway Station 4.83 Km NW
Shahbad Mohammadpur
Rly. Station 4.99 Km NW
2. Use of Natural resources for construction or operation of the Project (such as land,
water, materials or energy, especially any resources which are non-renewable or
in short supply):
S.No. Information/checklist Yes/ Details thereof (with approximate
confirmation No quantities /rates, wherever possible) with
source of information data
2.1 Land especially Yes Existing Plot area- 31163.13 sq m
undeveloped or agricultural
The land was allotted for the development of
land (ha)
Hotel complex only.
The Construction has been done as per earlier
environmental clearance. Now, further
construction will be done on existing land only.
There will be no addition of land use.
2.2 Water (expected source & Yes Source
Copy & Quantity
of land During Construction
papers is enclosed as Enclosure-
competing users) unit: KLD 5.phase:
Water during construction phase shall be
taken from tanker water supplier with supply
treated water from STP of nearby area.
Source & Quantity During Operation
Phase:
The ultimate source of water will be through
Delhi International Airport Pvt. Ltd. Total
water requirement of the project will be 374
KLD out of which 166 KLD will be fresh water.
Rest of the 208 KLD water requirement will be
fulfilled by treated water. Detailed water
Management & water Balance are given in
Environmental management plan.
2.3 Minerals (MT) No Not applicable
“Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.
2.4 Construction material – Yes The major materials required for construction
stone, aggregates, sand / of the project are steel, tiles, glass, cement,
soil (expected source – agate, bricks, flooring tiles / stones, sanitary
MT) and hardware items, electrical fittings, etc.
2.5 Forests and timber (source Yes Plywood for doors & windows shall be used
– MT) which shall be procured from local market.
2.6 Energy including electricity Yes Source of Electricity – Delhi International
and fuels (source, Airport Pvt. Ltd.
competing users) Unit: fuel Total Electrical Load (After Amendment)-
(MT), energy (MW) 6000 KW
D.G. sets for power back up- 3 X 2000 KVA
2.7 Any other natural No Not applicable
resources (use appropriate
standard units)
4.6 Sewage sludge or other Yes About 27 Kg/day of dried sludge will be
sludge from effluent generated from STP within complex during
treatment operation phase and this sludge will be
passed through filter press where it will be
dewatered/ dried to form a cake and then will
be used as manure in green areas. The
unused sludge shall be given to farmers or
nursery.
4.7 Construction or demolition Yes Construction waste is being used for flooring
wastes & Back filling in roads etc.
“Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.
5.3 Emissions from materials Yes Dust will generate during construction, from the
handling including storage movement of transport vehicles & other
or transport construction activities. The effect is restricted to
construction phase only.
Water sprinklers are being used for dust
suppression.
Material shall be stored under Tarpaulin cover.
5.4 Emissions from Yes Dust & emissions are generated during
construction activities construction activities which is being reduced
including plant and by sprinkling of water in a specific time interval
equipment & timely maintenance schedule for machinery.
Also the machines are being shut down during
idle period.
5.5 Dust or odours from Yes During loading & unloading of construction
handling of materials material dust is likely to be generated during
including construction construction phase. Water was being sprinkled
materials, sewage and and tarpaulin cover was provided over stored
waste raw material to reduce dust emission, same
shall be maintained during proposed
construction.
Mobile Toilets during construction phase shall
be provided & waste water will be disposed off
in septic tank followed by soak pits.
5.6 Emissions from No Not applicable.
incineration of waste.
5.7 Emissions from burning of No Open burning of biomass/ other material will be
waste in open air (e.g. prohibited.
slash materials,
construction debris).
5.8 Emissions from any other No None
sources.
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
7. Risks of contamination of land or water from releases of pollutants into the ground or
into sewers, surface waters, groundwater, coastal waters or the sea:
Forest
Central Ridge Reserve 10.04 Km NE
Forest
Pusa Hill Forest 10.09 Km NE
Southern Ridge Forest 9.85 Km NE
Rajokri Protected Forest 3.32 Km SE
3 Areas used by protected, Asola Wild Life 14.73 Km SE
important or sensitive species of Sanctuary
flora or fauna for breeding,
nesting, foraging, resting, over
wintering, migration
Nearest Railway
Station:
New Delhi Railway 14.08 Km NE
Station
Palam Railway Station 4.83 Km NW
Shahbad Mohammadpur 4.99 Km NW
Rly. Station
IGI Airpoet Metro Station 3.46 Km NW
Shivaji Bridge Railway 13.81 Km NE
Station
Airport:
Indira Gandhi
International Airport 0.32 Km SW
Safdarjung Airport
9.22 Km NE
Post Office:
Ghitorni Post Office 6.16 Km SE
Lodhi Road Head Post 10.56 Km NE
Office
Naraina Industrial Estate 9.37 Km NE
Post Office
Kalkaji Head Post Office 13.39 Km E
Place of Worship:
Sankat Mochan 0.92 Km NE
Hanuman Mandir
Brahma Kumaris 0.59 Km SE
Rajyoga Center
Masjid Chishtiya 7.05 Km NW
Gufa Wala Mandir 6.57 Km NW
Ayyappa Temple 6.98 Km NW
School:
Delhi Public School, 5.91 Km NE
R.K.Puram
St. Paul School 7.69 Km E
HauzKhas
The British School 7.85 Km NE
Salwan Junior School 8.59 Km NE
Bank:
Bank of Tokyo 0.23 Km NE
Mitsubishi UFJ
Indian Bank of Overseas 0.47 Km SE
ATM
SBI AAI Rangpuri 1.02 Km SW
Kotak Mhindra Bank 0.01 KM SW
ATM
10 Areas containing important, high None None
quality or scarce resources
“Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.
FORM 1A
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary attach
explanatory notes with the Form and submit along with proposed environmental management
plan & monitoring programme)
I. LAND ENVIRONMENT
(Attach panoramic view of the project site and the vicinity)
1.1 Will the existing land use get The proposed project site is proposed at Asset no.
significantly altered from the project 13, Hospitality District, DIAL, IGI Airport, Delhi
that is not consistent with the
The construction was started as per earlier
surroundings? (Proposed land use
Environmental Clearance granted vide F no.
must conform to the approved
92/DPCC/SEIAA-SEAC/10/1444-1448 dated 11th Nov
Master Plan / Development Plan of
2010“Hotel Complex & Convention Centre”.
the area. Change of land use if any
and the statutory approval from the No land use change is anticipated.
competent authority be submitted).
Attach Maps of
(i) Site location The site location shown on Google Map is enclosed as
Enclosure-
(ii) Surrounding features of the Map showing vicinity around the site is enclosed as
proposed site (within 500 meters) Enclosure-
(iii) The site (indicating levels &
contours) to appropriate scales. If not Contour is enclosed as Enclosure- 7.
available attach only conceptual
plans.
1.2 List out all the major project
requirements in terms of the
Land area, Total Plot area = 31163.13 sq m
1.7 Give details regarding water supply, Water Supply: During Construction stage, water
waste handling etc. during the will be sourced through nearby STP through tanker
construction period. supplier.
Waste Generation / Handling:
Spillage of oil from the machinery or cement residual
from concrete mixer plants would be properly collected
and reused in construction site.
For construction labour, proper sanitary facilities &
wash areas were being constructed such as mobile
toilets and good hygienic conditions will be maintained
in further construction phase also.
1.8 Will the low lying areas & wetlands No low lying and wetlands area are present in and
get altered? around the project site.
(Provide details of how low lying and
wetlands are getting modified from
the proposed activity)
1.9 Whether construction debris & waste The construction debris generated from the
during construction cause health construction project is common in nature and will not
hazard? (Give quantities of various cause any health hazard to associate and nearby
types of wastes generated during population. The construction debris will be used for
construction including the land leveling / backfilling and landscaping according to
construction labour and the means of its composition. Steel scrap will be given to recycler.
disposal) Waste concrete will be reused as aggregate in
construction process.
Approx. 150 labours is being engaged during the
construction period. Proper sanitary facilities are
provided to construction labourers. Wash areas are
constructed and good hygienic conditions is
maintained.
2. WATER ENVIRONMENT
2.1 Give the total quantity of water The total quantity of water requirement shall be 374
requirement for the proposed KLD which will be provide by Delhi International Airport
project with the breakup of Pvt Limited
requirements for various uses. Water Balance Diagram is given in Environmental
How will the water requirement Management Plan.
met? Water Storage during operation:
State the sources & quantities and Storage will be provided for one-day requirement after
furnish a water balance statement. ascertaining the one-day average water requirement.
In order to ascertain the quantity of water consumed,
the supply will be through the water meter installed in
the supply line. The water main will be led into
Firefighting storage tanks and from these
compartments; the water will be allowed to overflow
into raw water tanks.
2.2 What is the capacity (dependable Daily water demand for the Hotel Complex &
flow or yield) of the proposed convention centre has been calculated to be around
source of water? 374 KL / Day. Water demand will be met from Delhi
International Airport Pvt. Limited.
2.3 What is the quality of water In case supply is not made or the supply made is
required, in case, the supply is not inadequate then the water shall be arranged through
from a municipal source? (Provide Tankers. In that case the water quality at the project
physical, chemical, biological site will be of standard as prescribed by the appropriate
characteristics with class of water authority.
quality)
2.4 How much of the water Total treated water of 208 KLD shall be generated from
requirement can be met from the the S.T.P and shall be reused in flushing, gardening,
recycling of treated wastewater? HVAC cooling & misc. purposes within the project
(Give the details of quantities, premises. Approx. 55.6 % of total water requirement
sources and usage) will be met by recycled water.
2.5 Will there be diversion of water There will not be any substantial effect on water
from other users? demand of this region as the development will be done
(Please assess the impacts of the as per the development plan of the area.
project on other existing uses and
quantities of consumption)
2.6 What is the incremental pollution The total waste water generation from the complex will
load from wastewater generated be 258 KLD which will be treated in in-house S.T.P of
from the proposed activity? capacity 310 KLD. 208 KLD of the treated water will be
reused for flushing, gardening, HVAC cooling & misc.
(Give details of the quantities and purposes. Excess water shall be discharge to sewer.
composition of wastewater
generated from the proposed
activity)
2.7 Give details of the water The rain water from terraces and other open area will
requirements met from water be collected in Rain Water Storage Tank (2 no.) of 250
harvesting? Furnish details of the Cum Capacity. The details of Rain Water Storage is
facilities created. given in Environmental Management plan.
2.8 What would be the impact of the After construction of complex; the rain water will be
land use changes occurring due to properly channelized to rain water collection tanks
the proposed project on the runoff through storm water drain within the complex excess
characteristics (quantitative as rain water will be discharged in to the existing storm
well as qualitative) of the area in water drainage of the area.
the post construction phase on a
long-term basis?
Would it aggravate the problems of No, it will not aggravate the problem of flooding or water
flooding or water logging in any logging in any way, rather will reduce the same.
way?
2.9 What are the impacts of the There will be no ground water extraction, however
proposal on the ground water? ground water recharging is proposed through rain
(Will there be tapping of ground water harvesting, so, there will be positive impact on
water; give the details of ground ground water levels.
water table, recharging capacity,
and approvals obtained from
competent authority, if any)
2.10 What precautions/measures are During the construction phase, runoff from the
taken to prevent the run-off from construction site is not allowed into the roadside. It shall
construction activities polluting be collected in a tank & after pre-treatment it is being
land & aquifers? reused for sprinkling, curing, tyre washing etc, rest will
(Give details of quantities and the be discharge in existing storm water drain of the area.
measures taken to avoid the
adverse impacts)
2.11 How is the storm water from within Adequate measures shall be taken to channelize such
storm water and the same shall be collected in rain
the site managed?
water storage tanks.
(State the provisions made to
avoid flooding of the area, details
3. VEGETATION
3.1 Is there any threat of the project to The ecology of the study area is not very rich in diversity
or high in endemism, nearby area is already developed.
the biodiversity?
Planted species are dominated in buffer zone. Core
(Give a description of the local zone is devoid of vegetation.
ecosystem with its unique The major mammalian fauna of the project-influenced
features, if any) area involves common languor, Rhesus macaques
(Macaqua mulata), mongoose (Herpestris edwardii) etc.
Avifauna is primarily represented by common crow
(Corvus splendens), House sparrow (Passer
domesticus), blue rock pigeon (Columba livia), Rose
ring paraqeet (Pitecula cramerii), spotted doves
(Streptopilia chinensis) and finches. Common peacock
(Pavo cristatus), are known to be present in within 10
km study area. Small reptiles, primarily squamates like
lizards, chameleons, poisonous & non-poisonous
snakes are also found in the study area.
No endangered or endemic species (as notified in IUCN
Red Data Book) are located within the study area. No
migratory birds breed in the study area. No Tiger reserve
4. FAUNA
4.1 Is there likely to be any displacement of Core Zone: The proposed site is under construction
fauna- both terrestrial and aquatic or & no fauna is found, so in existing conditions this place
creation of barriers for their movement? is not the habitat for local fauna. There will not be any
Provide the details. type of displacement or any other effect on the local
fauna due to proposed project activities.
Buffer Zone: There are No wild life sanctuaries within
10 km radius of the project site.
4.2 Any direct or indirect impacts on the As there is no distinct plantation at site, as trees planted
avifauna of the area? Provide details. are very young, no avifauna seen at site, however,
proper landscaping has been planned to provide a
clean, healthy and beautiful green environment for the
population.
Common native variety of trees and ornamental
flowering species are planted and more will be planted
in the green space which will attract avifauna & hence
will have direct positive impact on the local avifauna &
this will provide shelter to local birds.
4.3 Prescribe measures such as corridors, Proper measures shall be taken to protect fauna
fish ladders etc. to mitigate adverse in the area.
impacts on fauna.
5. AIR ENVIRONMENT
5.1 Will the project increase atmospheric The traffic will increase due to operation of complex.
concentration of gases & result in Increased traffic generation of vehicles due to project
heat islands? will not cause significant increase in atmospheric
concentration of gases and do not result in heat island
(Give details of background air formation.
quality levels with predicted values Tree plantation in the complex will be provided such that
based on dispersion models taking the impact of air pollution shall be minimized.
into account the increased traffic Wet scrubber will be provided to control particulate
generation as a result of the emission.
proposed constructions) D.G. Set of capacity 3 x 2000 KVA will be installed in the
complex which will be operated during power cut only.
5.2 What are the impacts on generation No dust, odour will be generated at site. Smoke will be
of dust, smoke, odorous fumes or generated from the operation of DG sets. Proper stack
other hazardous gases? Give details height and emission standards will be maintained as per
in relation to all the meteorological CPCB guidelines.
parameters.
5.3 Will the proposal create shortage of The optimum parking provision is proposed in the
parking space for vehicles? Furnish basement & surface. Hence there will be no shortage of
details of the present level of parking space for vehicles. Total parking provision of
transport infrastructure and complex will be 2168 ECS.
measures proposed for improvement
including the traffic management at
the entry & exit to the project site.
5.4 Provide details of the movement Maximum capacity of parking shall be provided in
patterns with internal roads, bicycle basement and a proper route shall be provided for the
tracks, pedestrian pathways, traffic movement as well as pedestrian movement.
footpaths etc., with areas under each
category.
5.5 Will there be significant increase in For further construction, noise barriers will be installed
traffic noise & vibrations? Give to reduce traffic noise & vibrations and during operation
details of the sources and the green belt developed within the complex which mitigate
measures proposed for mitigation of the traffic noise. Proper care is being taken during
the above. design so that there is not any increase in traffic noise
by providing adequate traffic movement, hence no
conjunction will cause.
The foundation will be made very hard and paved with
rubber flooring to minimize the vibration, also all other
measures has been adopted during designing that there
will not be any causes of vibrations during the traffic
6. AESTHETICS
6.1 Will the proposed constructions in After the construction of complex is complete, it will
any way result in the obstruction of a increase the beauty of the area by having well-ordered
view, scenic amenity or landscapes? buildings & proper landscaping.
Are these considerations taken into
Yes, all considerations have been taken by the
account by the proponents?
proponents.
6.2 Will there be any adverse impacts The development in the entire project influenced area is
from new constructions on the as per the provision of Planning Department; hence no
existing structures? What are the adverse impacts are anticipated from new constructions
considerations taken into account?
on the existing structures in this area.
However, the proposed project will improve the lookout
of area.
6.3 Whether there are any local There are no typical urban form & urban design
considerations of urban form & urban influencing the design criteria.
design influencing the design
criteria? They may be explicitly spelt
out.
Are there any anthropological or No there is no anthropological or archaeological site or
archaeological sites or artifacts artefacts near the site.
nearby?
State if any other significant features All significant features have been considered.
in the vicinity of the proposed site
have been considered.
7. SOCIO-ECONOMIC ASPECTS
7.1 Will the proposal result in any The operation of the project shall provide value addition
changes to the demographic to the existing infrastructure. The proposed project will
structure of local population? Provide
provide job facilities to for a no. of persons in it During
the details. construction phase about 150 -200 Nos. of skilled,
unskilled and professional work force including
temporary and permanent employees will be required
per day. This workforce will be hired locally in order to
generate the employment to the local people.
7.2 Give details of the existing social School:
infrastructure around the proposed Delhi Public 5.91 Km NE
project. School, R.K.Puram
St. Paul School 7.69 Km E
HauzKhas
The British School 7.85 Km NE
Salwan Junior 8.59 Km NE
School
Bank:
Bank of Tokyo
Mitsubishi UFJ 0.23 Km NE
Indian Bank of
Overseas 0.47 Km SE
7.3 Will the project cause adverse effects The proposed complex will be constructed with in the
on local communities, disturbance to designed site as per defined building by laws of
sacred sites or other cultural values? government authority. There is no sacred or cultural
What are the safeguards proposed? heritage site with in vicinity of proposed project; hence
no adverse impacts are envisaged.
8. BUILDING MATERIALS
8.1 May involve the use of building The major materials required for construction of the
materials with high-embodied project are steel, cement, bricks, flooring tiles/ stones,
energy. sanitary and hardware items, electrical fittings, etc.
Are the construction materials
Energy efficient building material shall be used.
produced with energy efficient
processes?
(Give details of energy conservation
measures in the selection of building
materials and their energy efficiency
8.2 Transport and handling of materials Mitigate Measures for Air Pollution During construction
during construction may result in stage:
pollution, noise & public nuisance. All the loose material either stacked or transported shall
What measures are taken to
be provided with suitable covering such as tarpaulin,
minimize the impacts?
etc. Water sprinkling shall be done at the location where
9. ENERGY CONSERVATION
9.7 Do the structures use energy- Suitable energy optimization will be adopted during the
efficient space conditioning, lighting calculation of energy load of the proposed project. The
and mechanical systems? Provide space heating load will be minimized using solar structure
technical details.
and suitable building envelop material. Uses of
incandescent lamp and halogen lamps have been
avoided and energy efficient CFL light shall be used for all
common area and other areas.
Provide details of the transformers The diesel generator sets shall be automatically controlled
and motor efficiencies, lighting to optimize their usage based on the actual load
intensity and air-conditioning load requirements at any time. Space conditioning will be
assumptions? provided as per norms of National Building Code – Part 8;
Building Services Section 3–Mechanical Ventilation.
Lighting intensity will be done as per the National Building
Code Guidelines.
Are you using CFC and HCFC free
CFC and HCFC free chillers will be provided.
chillers? Provide specifications
9.8 What are the likely effects of the No significant effect is envisaged on the surrounding
building activity in altering the micro- environment of project. Increased traffic generation and
climates? use of diesel generators sets( only during power failure )
Provide a self-assessment on the
in the project will not cause significant increase in
likely impacts of the proposed
construction on creation of heat atmospheric concentration of gases and will not result in
island & inversion effects? heat island formation.
9.9 What are the thermal characteristics S. No BUILDING MATERIAL ‘R’ Values ‘U’ Values
of the building envelope? (a) roof; (b) PROPOSED (in Sq m. Deg (in Watts/ Sq m.
WITH U & R VALUES C/ Watts ) Deg C)
external walls; and (c) fenestration?
1. Wall 2.28 0.44
Give details of the material used and Brick & ACC Blocks wall
the U-values or the R values of the (230 mm thick), both side
thick sand cement plaster
individual components. (12-18mm) with
insulation.
9.10 What precautions & safety measures The basic system of Fire Fighting shall be designed as per
are proposed against fire hazards? the provisions of the National Building Code 2005
Furnish details of emergency plans.
Water shall be drawn from fire reserve tanks by
electrically driven jockey pumps, fire pumps. A standby
diesel engine driven pump for fire hydrant pump shall also
be provided. All pumps shall have separate suction line
from the fire suction header and delivery shall be
connected to the system. Diesel engine driven fire pump
shall be of the same capacity and shall back up the
electrically operated fire hydrant, as per fire regulations.
This will be operated in case of total electrical power or
electrical pump failure. Independent jockey pumps (for
hydrant line) shall operate intermittently in order to take
care of hydraulic losses in the system and shall maintain
the minimum pressure respectively in wet risers.
FIRE HYDRANTS
Fire department connections, capable of directly feeding
the ring mains or static fire reserve tanks, shall also be
provided near the main entrance. It shall also be provided
on the external wall of the property near the main
entrance.
Internal standpipe fire hydrant system shall be provided
with landing valve, hose reel, first aid hose reels, complete
with instantaneous pattern short gunmetal pipe.
FIRE HOSE CABINETS
The hose cabinet to accommodate the Hose Pipes,
Branch Pipe, Nozzle and Hydrant Outlets shall be
fabricated from 2 mm thick or 14 mm gauge aluminium
sheet. Internal Hydrants shall accommodate the Hose
Reel equipment.
The hose cabinet shall be painted red and stove
enamelled.
EXTINGUISHERS
Hand held extinguishers shall be located so that the
maximum travel distance is not more than 23 meters and
would generally be located in or adjacent to the fire hose
reel cabinet.
Fire Safety:
9.12 What is the rate of air infiltration into All the window and door will be airtight quality, hence we
the building? don’t foresee any air infiltration
Provide details of how you are
mitigating the effects of infiltration.
9.13 To what extent the non-conventional Solar energy will be used to meet some electric requirement. It
energy technologies are utilized in is proposed to install solar Heater to generate hot water and
the overall energy consumption? link it to the main hot water system for augmenting the hot water
Provide details of the renewable supply to various areas.
energy technologies used.
10. ENVIRONMENT MANAGEMENT PLAN
10.1 The Environment Management Plan Environment Management Plan is given in Environment
would consist of all mitigation Report attached as ENCLOSURE -2
measures for each item wise activity
to be undertaken during the
construction, operation and the entire
life cycle to minimize adverse
environmental impacts as a result of
the activities of the project. It would
also delineate the environmental
monitoring plan for compliance of
various environmental regulations. It
will state the steps to be taken in case
of emergency such as accidents at
the site including fire.