Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

R

Developments
in Pipeline Protection
Reviewed

All photos courtesy of Stopaq Europe B.V.


By Brian Goldie, JPCL

ecent developments in pipeline performance is due to its hydrophilic nature and the result-
protection were discussed at ing ability to maintain a high glass transition temperature
the 18th International (Tg), despite humid and hot surroundings. The key to main-
Conference on Pipeline Protection, organized by the BHR taining adhesion under such conditions is good surface
Group and held in Antwerp, Belgium (November 4–6, preparation, usually based on chemical pre-treatment of
2009). blasted steel with chromate- or phosphate-based products.
More than 20 presentations were given, with fusion-bond- The authors described the development of a faster, solvent-
ed epoxy (FBE) coatings being the primary technology dis- free, non-toxic chemical pre-treatment. They then demon-
cussed in papers covering different aspects of the effect of strated its effect on the adhesion of FBE coatings immersed
temperature on the application of FBE powders. Other main in hot water.
topics discussed were three-layer polyolefin coatings (LPO), The development of new FBE products was the subject of
field joint coatings, and the rehabilitation of existing two presentations. J.K. Pratt and M.L. Mallozzi of the 3M
pipelines. Company (USA) discussed the development of an FBE coat-
This article summarizes some of the developments ing that could be either a stand-alone coating or a primer in a
presented. multi-layer system. The authors reported that the new FBE
could be applied at temperatures as low as 180 C (356 F).
Fusion-Bonded Epoxy (FBE) The authors also explained that for FBE coatings to achieve
Application-related problems were the theme for the pre- optimum performance, they need to be applied at tempera-
sentations on FBE. The effect of a novel chemical, non-toxic tures in excess of 230 C (446 F) for single-layer systems and
pre-treatment on increased adhesion of the FBE layer was 200 C (392 F) for three-layer systems. High-strength steels
described in a paper by G. Gaillard and J.L. Bouliez, of BS have started to be used for pipeline construction, but most of
Coatings (France). According to the authors, the long-term these grades cannot withstand pre-heat temperatures above
anticorrosion protection of buried pipelines is linked to the 200 C (392 F). The temperature limit puts constraints on the
good barrier properties of the coating, which also needs to coating to be used. This new FBE coating provides a solution
have good adhesion to withstand severe conditions of high for protecting pipeline made of high strength steels. The
temperature and humidity. authors also highlighted the two additional benefits of the
It has already been determined that for FBE, good barrier coating—enhanced line speeds and energy savings.

30 JPCL September 2010 www.paintsquare.com


Three-Layer
Polyolefin Coatings
M. Patterson, S. Drew, and V. high temperature pipeline applications.
Boerschel of AkzoNobel Powder The system is based on a maleic
Coatings GmbH (Germany) described The presentations on three-layer anhydride-grafted adhesive resin with
the development of a mid-Tg coating polyolefin (LPO) coatings included the excellent peel strength at high-
suitable for application on high- results of two studies. A. Hussain and temperatures and a high-density
temperature pipelines (120–150 C C. Pflugbeil, Comtech GmbH polyethylene topcoat.
[248–302 F]), but still having good (Germany), described the findings of an
flexibility and good adhesion. As the analytical study of three-layer Field Joint Coatings
exploration and extraction of oil from polyethylene coatings with emphasis on Field coatings are traditionally thought
fields at increasing depths continues, the FBE primer/substrate interface. of as the weak link in corrosion protec-
pipelines need to carry these fluids at A team of experts from the US and tion of pipelines. Two presentations
temperatures in the 120–150 C Canada reported results from an addressed this concern. The paper by M.
(248–302 F) range. The authors noted extensive study (sponsored by the US Mallozzi and M. Perez, the 3M Company
that it is widely accepted that the Tg of Department of Transportation [DOT]) of (USA), described the development of a
a coating should be at least 10 degrees the disbondment of the FBE layer from new coating system, based on an inter-
C (18 degrees F) above the operating the steel surface and topcoat cracking. penetrating network of linear poly-
temperature of the pipeline, but that According to the authors of the DOT olefins and monomeric epoxy. The coat-
few FBE coatings are commercially study, there have been several incidents ing has the ability to adhere to the FBE
available with Tgs in the 130–160 C of coating disbondment at the FBE-steel primer without the need of a polyolefin
(266–320 F) range. The few that exist interface of three-layer polyolefin adhesive. The network coating is also
have limited flexibility, particularly at coatings and polypropylene cracking compatible with polypropylene topcoats
low temperatures. The low flexibility reported in the literature. The research to give a seamless system between the
limits the range of environmental analyzed the residual stresses in LPO field joint coating and the factory
conditions that pipelines coated with coating systems and how these stresses applied pipe coating.
the products can withstand. The paper affect coating disbondment and the The second paper, by D. Tailor and E.
presented the development of a range polypropylene topcoating cracking. The Tacoma of Canusa-CPS (Canada),
of mid-Tg FBE powder coatings (Tgs in high coefficient of thermal expansion of reviewed the recent installation of a 24-
the 130-150 C [266–320 F] range) that three-layer LPO coating materials inch gas pipeline across the
had demonstrated excellent adhesion generates high residual stresses, which Mediterranean Sea. The authors focused
and mechanical properties down to remain high due to their low water on the field joint coating solutions adopt-
-60 C (-76 F). absorption and permeability. The three- ed for onshore, shallow water, and deep-
The use of kinetic and rheological layer LPO coating can delaminate from water sections. The solutions involved a
tools to predict melt viscosity and the steel substrate if the FBE/steel number of joint system designs and
curing behavior of FBE powder was interfacial strength becomes low. This installation innovations to meet the pro-
presented in a paper by M.A. Shafi et reduced strength could be due to poor ject requirements.
al., The Dow Chemical Company (USA). surface preparation, under-cure, or
The authors explained how the thermo-oxidative or hydrothermal Maintenance and
approach could be used to select the ageing, and the delamination is more Rehabilitation
appropriate powder for the specific severe if the polyolefin layer is thicker. Pipeline rehabilitation for the 21st cen-
application. During the application of The polypropylene topcoat degrades by tury was the subject of a presentation
FBE coating, the powder must melt, thermo-oxidation either during the from T.J.M. Bond et al. of Pipestream®
flow, and cure before quenching. The extrusion process or in storage under Inc (USA) and Xodus Group Ltd (UK).
minimum melt viscosity of the FBE direct sunlight. The residual stresses The authors described a method to con-
powder is critical. Melt viscosity will cause cracking of the polypropylene tinuously apply reinforcing steel strips
influences the ability of the material to if its strength retention becomes lower to existing corroded pipelines in the
form a uniform layer on the substrate than the residual stresses. ground, while they are still operating, to
before it gels. Consequently, achieving A further presentation from O. reinstate them to their original condi-
the correct balance between the Henschke, Dow Europe GmbH tion. According to the authors, the bene-
rheology and cure kinetics is important (Switzerland), described a new three- fits to the owners of continuous rein-
to maximize the coating performance. layer polyethylene coating suitable for forcement from one valve to the next

www.paintsquare.com JPCL September 2010 31


Pipeline Protection
are greater throughput and higher oper- melt or butyl rubber adhesives. The tem. The authors concluded that this
ating pressures with renewed asset authors discussed material properties system, compared to more conventional
integrity for the design life. needed for the rehabilitation process products, improved the quality of the
The repair system has three compo- and how they can be met by three-ply recoating and reduced the time spent on
nents. tapes or hot-spray applied the renovation, both critical aspects for
• Ultra-high-strength steel (UHSS) strip polyurethane. The use of self-amalga- the owners.
helically wrapped round the defect area mating three-ply tapes in the refurbish- F.A. Orr et al. of Applied Concrete
and factory coated with FBE for corro- ment of a 40-inch oil pipeline is also Systems Partnership (UK) described the
sion protection. described in detail. The authors conclud- use of a rapid hardening concrete cloth
• Heat- and chemical-resistant epoxy ed that for the refurbishment of for pipeline protection and also as an aid
adhesive, manually applied to fill any pipelines operating up to 50 C, three-ply for access in difficult terrains. The con-
corrosion pits and to bridge weld caps. tapes offer the widest range to meet the crete cloth consists of a pre-blended
This adhesive allows direct transfer of many conditions on site and can be cement mix held between two layers of
hoop stress to the reinforcing strips. A applied at temperatures from –35 to + polypropylene and PET fibers.The cloth
different epoxy is used to bond was initially developed to pro-
the strips to the pipe. duce tough, self-supporting,
• Concentrically-wrapped ter- demountable shelters for mili-
minating UHSS strips to retain tary and humanitarian aid
the ends of the reinforcing deployment. The cement blend
strips and prevent them from within the cloth matrix was
becoming unwound or dis- designed to match the perme-
bonded from the pipe. These ability of the carrier cloth to
strips are also coated with FBE permit water to penetrate to
for corrosion protection. the interior and subsequently
The authors reported a hydrate the cement, producing
demonstration project carried a durable, stable structure.
out to confirm the efficiency The hardening is achieved by
and viability of the concept. either passing the impregnated
Defects were introduced into a cloth through a tank of water
10-inch-long New Process Steel as the cloth is unwound or by
pipe, 5.9 mm wall thickness x placing the cloth as a sheet in
42 inches inside diameter, by the required position and hos-
removing 4.8 mm of wall 60 C. For higher operating tempera- ing the set-up with water.
thickness. These defects were rehabili- tures or for increased mechanical resis- The authors gave examples of using
tated with a total thickness of 2.2 mm of tance, thermosetting compounds based the concrete cloth as a pipe coating to
UHSS strip. The repair proved to be on polyurethane or epoxy would be a provide a rock shield during back-fill; or
stronger than the original pipe, with better choice, the authors said. to act as a weight coating, or to provide
burst pressures well in excess of 200 The renovation of the pumped water temporary (or permanent) bunds, ditch-
bar (~3,000 psi). storage system of the Wehr hydro- es, or hard standing for tracked vehicles
An alternative rehabilitation process power station in southern Germany during pipelaying. According to the
was explained by M. Schad et al. of was described by A. Zwangzinger of authors, the system allows flexibility of
Denso GmbH (Germany). They Corro Tec Korrosionsschultz application, coupled with the simplicity
described the use of state-of-the-art tape Vertriebsges (Germany) and co-authors and practicality of a product on a roll to
wrappings and polyurethane coatings as from the power station owners and provide concrete protective coatings.
economical solutions for a variety of energy supply company. The plant had
project requirements. This detailed pre- been in operation for 30 years. Over 12 Further Information
sentation covered a range of pipeline months, approximately 41,000 m2 of The complete set of papers presented at
coatings in use today that have to be steel surfaces were renovated. The old the conference can be obtained from the
rehabilitated, including bitumen, coal tar-based coating was removed by abra- organizers, the BHR Group,
tars, PVC tape with hot-melt or bitumi- sive blasting and recoated with two to www.bhrconferences.com.
nous adhesives and PE tapes with hot- three coats of a solvent-free epoxy sys- JPCL
32 JPCL September 2010 www.paintsquare.com
Click our Reader e-Card at paintsquare.com/ric
We at Polyguard view cathodic
shielding by disbonded coating as a
huge problem in pipelines. We also
believe that the shielding problem has
been largely ignored worldwide.
The evidence has grown for 25 years now. Visit
www.polyguardproducts.com/nonshieldingcoating.htm to
view some of this evidence, and to see our non-shielding coating
Polyguard RD-6. The RD-6 coating system has been used by major
operators since 1988, and to our knowledge, there has never been a
case of serious corrosion found under RD-6.

Note that newly issued DOT regulation Title 49 CFR §192.112 “Additional design
requirements for steel pipe using alternative maximum allowable operating pressure”
requires that “The pipe must be protected against external corrosion by a
non-shielding coating.”
As operators discover shielding on their lines, many are converting to RD-6. This has made
us one of the fastest growing companies in the world for pipeline coatings.

70

3RO\JXDUG KDV EHHQ ,62  FHUWL¿HG VLQFH 

3KRQH   &XUUHQW FHUWL¿FDWLRQV DUH


 $PHULFDQ 1DWO 6WDQGDUGV ,QVWLWXWH

ZZZSRO\JXDUGSURGXFWVFRP
S \J S  'XWFK &RXQFLO IRU &HUWL¿FDWLRQ
 'HXWVFKHU $NNUHGLWLHUXQJV 5DW
Click our Reader e-Card at paintsquare.com/ric

You might also like