Professional Documents
Culture Documents
Stone Placing: Constrution Methode
Stone Placing: Constrution Methode
Stone Placing: Constrution Methode
FOR
STONE PLACING
A. GENERAL
B. CONSTRUCTIONS METHOD
P
/
O
4
1-
0
4
5
1 Stage (+10 m)
P
/
O
4
1-
0
4
5
1 Stage (+10 m)
10 m
5 passing
Max. 1 tons
2. Under Layer
If core rock have been placed at toe protection foundation, and
have inspected, Under Layer can be placed.
P
/
O
4
1-
0
4
5
P
/
O
4
1-
0
4
5
B. Groins Structure.
1. Core Rock material.
Core rock placing activity can do through after the Toe Protection
foundation have completed. Stone shall placed still in a layer
every 0.2 meter with every 10 meters space by excavator.
Especially for layer above MSL will be compacted by vibro roller.
2. Under Layer.
With the same method step, under layer material can placed
through after the Core rock layer have completed. Stone shall
placed still in a layer with at least 2 (two) rocks thickness.
3. Armor Rock.
The next step, after the temporary leveling of the under layer
material is completed and have approved by Engineer, armor rock
will be placed.
Placing of armor rock will be carried out by an excavator, with
individually placed so that it’s neighbors securely hold each rock.
2 Before Underlayer Placing * Check top elevation of 10 m pitch Joint inspection Upper surface of core
(after Core rock placing) core rock + 150 mm
* Check dimension of - 150 mm
core rock
* Cohari setting for Side of core :
underlayer placing + 150 mm
- 150 mm
3 Before Armour Rock Placing * Check top elevation of 10 m pitch Joint inspection
(after Underlayer placing) under layer
* Check dimension of
under layer
* Cohari setting for
armour rock placing
4 After Armour Rock Placing * Check top elevation of 10 m pitch Joint inspection Upper surface of armour
armour rock placing + 250 mm
* Check dimension of - 0 mm
armour rock / Groin
Side of armour :
+ 250 mm
- 0 mm
JOINT
SURVEY
MARKING
No
CEK
Yes
EXCAVATION
PROFILE
EXCAVATION
CHECK: No
1. SUBGRADE ELEVATION.
2. DEMOLITION CEK
3. COHARI SETTING FOR CORE PLACING.
Yes
PLACING CORE
ROCK
PROFILE CORE
ROCK LAYER
CHECK:
1. TOP ELEVATION FO CORE ROCK.
No
2. DEMENTION CEK
3. COHARI SETTING FOR UNDER LAYER.
Yes
PLACING UNDER
LAYER
PROFILE UNDER
LAYER
CHECK:
1. ELEVATION OF UNDER LAYER,
No
2. DIMENTION OF UNDER LAYER, CEK
3. COHARI SETTING FOR ARMOR ROCK.
Yes
PLACING ARMOR
ROCK
PROFILE ARMOR
ROCK
CHECK:
No
1. TOP ELEVATION FO ARMOR ROCK. CEK
2. DEMENTION OF ARMOR ROCK.
Yes
FINISH
C. QUALITY CONTROL
The quality control work will base on shop drawing. Joint survey will be
conducted to ensure the correct position, and dimension.
The quality control flow chart for shore protection work as follow :
CALCULATION VOLUME
No
CEK
Yes
SHOP DRAWINGS
No
CEK
Yes
COMMENCEMENT WORKING
No
CEK
SURVEY
Yes
QUANTITY CALCULATION
D. SAFETY CONTROL
During executions of stone placing, safety barricades will be installed
around the area to prevent entry by tourist or others.
Safety sign boards will be displaced.
REEF AREA
GROIN
EXCAVATOR
SHORE LINE
STONE BURGE
SAFETY BUOY
NO ENTRY
1M
Information Board.
Information board’s will be installed on site as conform engineer
approval.
(see attachment : 2)
Information leaflet.
Already submitted to hotel/restaurant owner’s and local people
on March 26th 2002 (when socialization meeting).
(see attachment :3).
2 Before Underlayer Placing * Check top elevation of 10 m pitch Joint inspection Upper surface of core
(after Core rock placing) core rock + 150 mm
* Check dimension of - 150 mm
core rock
* Cohari setting for Side of core :
underlayer placing + 150 mm
- 150 mm
3 Before Armour Rock Placing * Check top elevation of 10 m pitch Joint inspection
(after Underlayer placing) under layer
* Check dimension of
under layer
* Cohari setting for
armour rock placing
4 After Armour Rock Placing * Check top elevation of 10 m pitch Joint inspection Upper surface of armour
armour rock placing + 250 mm
* Check dimension of - 0 mm
armour rock / Groin
Side of armour :
+ 250 mm
- 0 mm