Project : Lahendong 5&6 Geothermal Power Plant Project

Job No :
Client : PT. rekayasa industri

STONE PITCHING METHOD


STON PITCHING U SEAL PIPE PIT AREA

a. Volume Stone pitching Stage 1


Length = 19.60 m
Widht = 1.50 m
High = 3.00 m

Volume (A) = 88.2 m3 (Stage 1 Unit 5)


= 176.4 m3 (Stage 1 Unit 5 & unit 6)

a. Volume Stone pitching Stage 2


L= (length + High) = 5.20 m
Widht = 19.60 m
total = 101.92 m (Stage 2)

Volume (B) = 203.84 m3 (Stage 2 Unit 5 & unit 6)

Total Volume Stone Pitching Useal Pit Area 5 & 6


Total all area = 380.2 291.00

c Sand Fill
Length = 15.00 m
Widht = 1.50 m
High = 0.05 m

Volume (A) = 1.125 m3 (Stage 1 Unit 5)


= 2.3 m3 (Stage 1 Unit 5 & unit 6)

d. Tools and Equipment


Scafolding (By Rek) : 8.00 Ea
tangga akses (Naik & Turun) : 2.00 Ea

e. Man Powers
Foreman : 1.00 Man
Labour : 8.00 Man (untuk 1 area)
Mechanic : 1.00 Man

f. Material (Concrete k'-300 kg/cm2)


Cement Type 1/m3 = 1019.04 Zak
Sand/m3 = 2.25 m3

Remarks :
Project : Lahendong 5&6 Geothermal Power Plant Project
Job No :
Client : PT. rekayasa industri

PASANGAN BATU CONDENSER


HOT WHELL PUMP AREA UNIT 5 & 6

a. Volume Stone pitching


panjang = 16.50 m
lebar penampang atas = 0.40 m
lebar penampang bawah = 0.60 m
Tinggi = 1.30 m
(penmpng atas + bawah)
x tinggi = total x panjang
2
pnpng atas+ pnmpng bwh / 2 = 0.5 m
p atas+ p bwh /2 x tinggi = 0.65 m2
total (b x Panjang) = 10.73 m3

Total Volume Stone Pitching Wall Condenser HWP Unit 5 & 6

Total all area = 21.5 m3 (U-Seal Pipe Pit Unit 5 & unit 6)

e. Man Powers
Foreman : 1.00 Man
Labour : 8.00 Man (untuk 1 area)
Mechanic : 1.00 Man

Remarks : sketch see method Drawing for U-seal Pipe Pit area

PT. TRIKARYA ESHA GEMILANG PT. REKAYASA INDUSTRI


Print Name

Signature

Date
Project : Lahendong 5&6 Geothermal Power Plant Project
Job No :
Client : PT. rekayasa industri

STONE PITCHING METHOD


STONE PITCHING HOT WHELL PUMP AREA

a. Volume Stone pitching


panjang = 12.24 m
lebar penampang atas = 0.30 m
lebar penampang bawah = 0.80 m
Tinggi = 5.10 m
(penmpng atas + bawah)
x tinggi = total x panjang
2
pnpng atas+ pnmpng bwh / 2 = 0.55 m
p atas+ p bwh /2 x tinggi = 2.805 m2
total (b x tinggi) = 34.33 m3 (HWP Unit 5)

Total Volume Stone Pitching Useal Pit Area 5 & 6


Total all area = 68.7 m3 (HWP Unit 5 & unit 6)

e. Man Powers
Foreman : 1.00 Man
Labour : 8.00 Man (untuk 1 area)
Mechanic : 1.00 Man

Remarks : sketch see method Drawing for HWP Area

PT. TRIKARYA ESHA GEMILANG PT. REKAYASA INDUSTRI


Print Name

Signature

Date
Project : Lahendong 5&6 Geothermal Power Plant Project
Job No :
Client : PT. rekayasa industri

STONE PITCHING METHOD


STON PITCHING HWP AREA

a. Volume Stone pitching Stage 1


L= (length + High) = 2.38 m
Widht = 11.04 m
total = 26.22 m (Stage 2 unit 5)

Volume (A) = 52.44 m3 (Stage 2 Unit 5 & unit 6)

Total Volume Stone Pitching HWP area 5 & 6


Total all area = 96.6

c Sand Fill
Length = 11.04 m
Widht = 2.10 m
High = 0.05 m

Volume (A) = 1.1592 m3 (Stage 1 Unit 5)


= 2.3 m3 (Stage 1 Unit 5 & unit 6)

d. Tools and Equipment


Scafolding (By Rek) : 8.00 Ea
tangga akses (Naik & Turun) : 2.00 Ea

e. Man Powers
Foreman : 1.00 Man
Labour : 8.00 Man (untuk 1 area)
Mechanic : 1.00 Man

f. Material (Concrete k'-300 kg/cm2)


Cement Type 1/m3 = 355.49 Zak
Sand/m3 = 2.32 m3

Remarks :
CONSTRUCTION METHODE
POURING CONCRETE TURBIN GENERATOR FOUNDATION
STAGE 1 (fc'-300 kg/cm2)

a. Volume Concrete Stage 1


Length = 11.00 m
Widht = 4.80 m
High = 1.50 m (Stage 1)

Volume (A) = 79.2 m3

b. Produktivitas Carmix (1 Hour)


Produktivitas/hour/unit = 2.60 m3

Qty. Equipment = 2.00 Unit

Produktivitas (B) = 5.20 m3/hour

c. Time Estimate For Pouring Concrete Stage 1


= (A) / (B)

= 79.20 / 5.20

= 15.23 Hour

d. Tools and Equipment


Concrete Vibarator : 3.00 Ea
Bucket Pouring : 1.00 Ea
Tremi Dia 6 inch. : 1.00 Ea
Carmix : 2.00 Ea
Mobile Crane : 1.00 Ea

e. Man Powers
Foreman : 1.00 Man
Labour : 20.00 Man

Operator : 3.00 Man


Operator Helper : 3.00 Man
Mechanic : 1.00 Man

f. Material (Concrete fc'-300 kg/cm2)


Cement Type V/m3 = 420 kg = 831.60 zak
Sand/m3 = 612 kg = 55.40 m3
Agregat 10/20 /m3 = 575 kg = 64.03 m3
Agregat 20/30 /m3 = 383 kg = 42.65 m3
Water /m3 = 185 ltr = 14,652.00 ltr

Remarks :

SUBCONTRACTOR SUMITOMO CORPORATION PT. PLN (PERSERO)


Print Name

Signature

Date
CONSTRUCTION METHOD
POURING CONCRETE TURBIN GENERATOR FOUNDATION
STAGE 1 (fc-300 kg/cm2)

a. Volume Concrete Stage 1

Length = 11.00 m
Widht = 4.80 m
High = 1.50 m (Stage 1)

Volume (A) = 79.2 m3

b. Produktivitas Carmix (1 Hour)

Produktivitas/hour/unit = 2.60 m3

Qty. Equipment = 2.00 Unit

Produktivitas (B) = 5.20 m3/hour

c. Time Estimate For Pouring Concrate Stage 1

= (A) / (B)

= 79.20 / 5.20

= 15.23 Hour

d. Tools and Equipment

Concrete Vibarator : 3.00 Ea


Bucket Pouring : 1.00 Ea
Tremi Dia 6 inch. : 1.00 Ea
Carmix : 2.00 Ea
Excavator : 1.00 Ea

e. Man Powers
Foreman : 1.00 Man
Labour : 20.00 Man

Operator : 3.00 Man


Operator Helper : 3.00 Man
Mechanic : 1.00 Man

d. Material (Concrete fc-300 kg/cm2)

Cement Type V/m3 = 420 kg 831.60 zak


Sand/m3 = 612 kg 55.40 m3
Agregat 10/20 /m3 = 575 kg 64.03 m3
Agregat 20/30 /m3 = 383 kg 42.65 m3
Water /m3 = 185 ltr 14,652.00 ltr