Daily Progress Report: Aiims Bilanpur

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Client PMC Contractor

Daily Progress Report


AIIMS BILANPUR
Date: 18/Sep/19 Temp (Max) : 30 °C Temp (Min) : 22 °C Weather: Partly sunny

Work Progress
Actuals
No. Activity Unit
Cumm. Remarks / Location
Day Shift Night Shift Month
Project
Block- A ( TIER-1) Floor Completion. Unit. Day Shift. Night Shift. Month. Cumm. Project. Total Scope

Column Erection

Beam Erection

Insert Plate Installation

Welding Completion

Cumm.
Block -A (TIER-2) Unit Day Shift Night Shift Month Total Scope (incl. LMR) % Achieved
Project
Column Erection Nos. 8\55 - 48 48 - 87.2%

Beam Installation Nos. 6\692 - 43 43 - 6.2%

Insert Plate Installation - CW Nos. - - - #VALUE! - -

Welding Completion RMT - - - #VALUE! - -


15
Resources

Equipments Detail Material Receipt


Physical
Previous Received Total Stock
No. Equipment Nos. No. Equipment Nos. Unit
Received (on date) Received

1 Welding set 3 8 Chain block 3 Columns Nos. 54 0 54 14 nos.

2 Cutting set 9 Lifting belt 4 Beams Nos. 310 0 310 273 nos.

Wire
3 ropesling(16mm)
5 10 D-cycle 14 Welding Rods Pkt

Wire
4 ropesling(12mm)
1 11 Impact machine 3 Insert Plate Nos.

5 Spanerset 4 Anchor Bolt Nos.

6 Granding Machine 2 Base Plate Nos.

7 Torque Machine 1 STAIRCASE Nos.

Total 16 nos. Total 24 nos.

Manpower (Heads) Issues / Notes / Hindrances

No. Category Day Night No. Descriptions

1 Staff 5 Work front is not clear.

2 Welder 1 Hydra operater was 45 minutes late.

3 Helper (Welder) 1 Tower crane operater was 30 minutes late.

4 Rigger 6 Little issue with the studd machine.

5 Fitter 0

6 Gas Cutter 1

Total 14 Heads 0 Heads

Site Photos

Description ERECTION OF BEAM NO.(2BA60) Description SITE VIEW OF (BLOCK-A)

Description ERECTION OF COLUMN NO (T1-C1A-27) ERECTION OF COLUMN NO. (T1-C1A-13)

1/2
The Camellias, Gurgaon DAILY PROGRESS REPORT (FINISHES) Date: #REF!
Project Duration: 1,445 Days Time Elapsed #REF! #REF! Weather: #REF!
Work Progress
Actuals
Quantity
Sl No. Activity UOM % Completed Remarks
(Scope) This day Cumm. Month Cumm. Project

WATER PROOFING
1 Retaining Wall Sqm 3,540 - 3,011 85%
2 Balcony Sqm 62,600 12 421 58,984 94%
3 Tower Sunken area Sqm 71,968 - 71,470 99.3%
4 Podium Sqm 37,948 - 35,766 94%
5 Terrace Waterproofing Sqm 9,950 - 9,519 96% ###
HANDRAIL
1 MS Handrail (LIN) Rmt 8,675 10 8,645 99.7%
2 MS Handrail (Sub con) Rmt 5,405 - 5,405 100%
3 SS Handrail (Stage-1) Rmt 19,450 - 19,450 100%
GRC
1 Nib Rmt 22,000 - 22,000 100.0%
2 Screen Sqm 20,120 6 599 19,653 97.7%
Stone Coping & Flooring
1 Coping Rmt 23,243 124 3,073 19,312 83.1%
2 Kota Flooring (Service lift lobby) Sqm 7,324 18 572 6,018 82.2% ###
Roadwork
1 GSB Cum 4,283 - 3,849 89.9%
2 WMM Cum 4,841 - 3,585 74.1% ###
3 Semi Dense Bitumen Cum 450 - 404 89.8% ###
Expansion Joint (Basement & Podium)
1 MS Angle Fixing Rmt 2,144 - 2,045 95% ###
Expansion Joint (Tower) - Floor to Floor
1 MS Angle Fixing Rmt 729 - 729 100% ###
Fire Doors (Apartments)
1 Stage -1 (Door installation) nos. 2,377 43 2,331 98% ###
2 Stage -2 (Hardware + Puff grouting) nos. 2,377 221 2,332 98% ###
Doors (Basement) - Fire doors + SS Doors
1 Fire doors nos. 535 - 535 100% ###
Casement Windows + Doors
1 Stage -1 (Frame installation) nos. 4,898 6 100 4,787 98% ###
2 Stage -2 (Shutter + Glass) nos. 4,898 16 324 4,264 87% ###
Temporary Glazing
1 Stage -1 (Frame installation) nos. 2,435 - 2,435 100% ###
2 Stage -2 (Door + Hardware) nos. 2,435 - 2,435 100% ###
INTERNAL PLASTER Level
A1 Sqm 5,594 5,593 100.0%
A2 Sqm 19,336 - 19,330 99.97%
INTERNAL PLASTER

A3 Sqm 14,808 - 14,772 99.8%


A4 Sqm 15,497 2 22 15,424 99.5%
B1 Sqm 10,706 - 10,704 99.98%
C1 Sqm 10,780 - 10,753 99.7%
C2 Sqm 10,444 - 10,416 99.7%
C3 Sqm 10,153 - 10,147 99.9%
C4 Sqm 4,820 - 4,819 99.99%
Sub structure Sqm 3,551 - 3,534 99.5%
EXTERNAL PLASTER Level
A1 Sqm 13,169 - 13,169 100.0%
A2 Sqm 31,007 25 30,921 99.72%
EXTERNAL PLASTER

A3 Sqm 28,004 18 27,955 99.8%


A4 Sqm 37,950 69 37,877 99.8%
B1 Sqm 17,902 - 17,893 99.95%
C1 Sqm 19,751 58 19,697 99.7%
C2 Sqm 16,416 10 16,352 99.6%
C3 Sqm 16,416 - 16,235 98.9%
C4 Sqm 11,331 - 11,331 100.0%
Staircase plaster (Skin plaster)
1 Staircase Plaster Sqm 17,182 - 15,937 92.8%

Total Overall Sqm 314,818 202 312,863 99%


PAINTING
Overall Painting (Coat III) Sqm 913,049 - 839,034 92% Level

Sub-Structure Painting (Coat III) Sqm 245,857 - 214,588 87.28%

Tower A1 Painting (Coat III) Sqm 36,008 - 36,008 100.0%


Tower A2 Painting (Coat III) Sqm 120,383 - 118,558 98%
Tower A3 Painting(Coat III) Sqm 109,211 - 98,440 90%
Tower A4 Painting (Coat III) Sqm 122,911 - 97,933 80%
Tower B1 Painting (Coat III) Sqm 61,689 - 60,721 98%
Tower C1 Painting (Coat III) Sqm 63,024 - 61,611 98%
Tower C2 Painting (Coat III) Sqm 61,428 - 60,078 98%
Tower C3 Painting (Coat III) Sqm 62,246 - 60,878 98%
Tower C4 Painting (Coat III) Sqm 30,291 - 30,218 99.8%
External painting Sqm 422,164 135 3,030 299,468 70.9%

Note: The quantities (scope) are provisional.