Professional Documents
Culture Documents
Daily Progress Report: Aiims Bilanpur
Daily Progress Report: Aiims Bilanpur
Daily Progress Report: Aiims Bilanpur
Work Progress
Actuals
No. Activity Unit
Cumm. Remarks / Location
Day Shift Night Shift Month
Project
Block- A ( TIER-1) Floor Completion. Unit. Day Shift. Night Shift. Month. Cumm. Project. Total Scope
Column Erection
Beam Erection
Welding Completion
Cumm.
Block -A (TIER-2) Unit Day Shift Night Shift Month Total Scope (incl. LMR) % Achieved
Project
Column Erection Nos. 8\55 - 48 48 - 87.2%
2 Cutting set 9 Lifting belt 4 Beams Nos. 310 0 310 273 nos.
Wire
3 ropesling(16mm)
5 10 D-cycle 14 Welding Rods Pkt
Wire
4 ropesling(12mm)
1 11 Impact machine 3 Insert Plate Nos.
5 Fitter 0
6 Gas Cutter 1
Site Photos
1/2
The Camellias, Gurgaon DAILY PROGRESS REPORT (FINISHES) Date: #REF!
Project Duration: 1,445 Days Time Elapsed #REF! #REF! Weather: #REF!
Work Progress
Actuals
Quantity
Sl No. Activity UOM % Completed Remarks
(Scope) This day Cumm. Month Cumm. Project
WATER PROOFING
1 Retaining Wall Sqm 3,540 - 3,011 85%
2 Balcony Sqm 62,600 12 421 58,984 94%
3 Tower Sunken area Sqm 71,968 - 71,470 99.3%
4 Podium Sqm 37,948 - 35,766 94%
5 Terrace Waterproofing Sqm 9,950 - 9,519 96% ###
HANDRAIL
1 MS Handrail (LIN) Rmt 8,675 10 8,645 99.7%
2 MS Handrail (Sub con) Rmt 5,405 - 5,405 100%
3 SS Handrail (Stage-1) Rmt 19,450 - 19,450 100%
GRC
1 Nib Rmt 22,000 - 22,000 100.0%
2 Screen Sqm 20,120 6 599 19,653 97.7%
Stone Coping & Flooring
1 Coping Rmt 23,243 124 3,073 19,312 83.1%
2 Kota Flooring (Service lift lobby) Sqm 7,324 18 572 6,018 82.2% ###
Roadwork
1 GSB Cum 4,283 - 3,849 89.9%
2 WMM Cum 4,841 - 3,585 74.1% ###
3 Semi Dense Bitumen Cum 450 - 404 89.8% ###
Expansion Joint (Basement & Podium)
1 MS Angle Fixing Rmt 2,144 - 2,045 95% ###
Expansion Joint (Tower) - Floor to Floor
1 MS Angle Fixing Rmt 729 - 729 100% ###
Fire Doors (Apartments)
1 Stage -1 (Door installation) nos. 2,377 43 2,331 98% ###
2 Stage -2 (Hardware + Puff grouting) nos. 2,377 221 2,332 98% ###
Doors (Basement) - Fire doors + SS Doors
1 Fire doors nos. 535 - 535 100% ###
Casement Windows + Doors
1 Stage -1 (Frame installation) nos. 4,898 6 100 4,787 98% ###
2 Stage -2 (Shutter + Glass) nos. 4,898 16 324 4,264 87% ###
Temporary Glazing
1 Stage -1 (Frame installation) nos. 2,435 - 2,435 100% ###
2 Stage -2 (Door + Hardware) nos. 2,435 - 2,435 100% ###
INTERNAL PLASTER Level
A1 Sqm 5,594 5,593 100.0%
A2 Sqm 19,336 - 19,330 99.97%
INTERNAL PLASTER
2/2