Professional Documents
Culture Documents
Benchmarks India
Benchmarks India
(Jayanthipuram Works) 1
Plant Capacity at a Glance
Cumulative Cumulative
Year Milestone Clinker Capacity Cement Capacity
Million TPA Million TPA
1986 Line-1 commissioned 0.75 0.75
1995 Line-1 Up-gradation 1.10 1.10
1999 Slag Cement 1.10 1.60
2008 Line-2 commissioned 2.50 2.60
Mid-
Line-3 Commissioning 4.685 3.65
2021
2
Plant Capacity Enhancement
3
Management System Certificates
Occupational Environment
Quality
Health & Safety Management
Management
Management System
System
System
4
Management System Certificates
Energy 5S JUSE
Management Certificate
System
5
Thermal Specific Energy
Consumption
750
753
740 746
730
Kcal / Kg Clinker
720
724
710
700
2017-18 2018-19 2019-20
6
Electrical Specific Energy Consumption
FLY ASH ADDITION
(%)
40
34.89
35
31.45
30
25
22.16
20
Kwh / MT of Cement
15
2017-18 2018-19 2019-20
7
Cement dispatch Share in Percentage (%)
60
50 57.63 56.09
51.07
40
30 42.37
43.95 48.92
20
10
0
2017-18 2018-19 2019-20
OPC Share PPC Sahre
8
Electrical Specific Energy Consumption
40
34.89
35
31.45
90 85.44
82.1 80.91 30
80 25
22.16
20
70
15
57.63 56.09 2017-18 2018-19 2019-20
60
51.07 48.9 FLY ASH ADDITION
50 43.95 (%)
42.37
40
30
20
10
0
2017-18 2018-19 2019-20
kWh/T cement OPC Share PPC Share
(%) (%) 9
Electrical Specific Energy Consumption up to Clinker
61
60.46
60
59
Kwh / MT of Clinker
58
56.78 57.01
57
56
55
54
2017-18 2018-19 2019-20
10
Global Norms/Standards
Reference:
National Benchmark: Energy Bench Marking For Cement Industry May 2015 Version 2
International Benchmark : Indian cement and construction industries-global competitiveness-NCB-
CMA special publication presented in 8th NCB International Seminar
11
Road Map To Achieve Benchmark
12
Energy Conservation Projects Implemented in the years
2017-18, 2018-19 & 2019-20
No. of Projects : 71
Savings Investment
S. No. Energy Saving Project
(Rs. Lakhs) (Rs. Lakhs)
Saving Investme
S. No. Energy Saving Project s nts
(Lakhs) (Lakhs)
Saving
Investmen
s
S. No. Energy Saving Project ts
(Lakhs
(Lakhs)
)
Power reduction in compressor by
Installing PRV batteries and optimize
7 0.23 0.2
the pressure setting in Fly ash bulk
tankers.
To reduce the power consumption in
8 Packing Plant Compressors room by 0.026 0.24
providing hot air vent duct .
Optimization of TPP R.O pump energy by
9 0.027 0.35
installing VFD .
16
Energy Conservation Project 2019-20
Investme
S. Savings
Energy Saving Project nts
No. (Lakhs)
(Lakhs)
CF Silo Gate operation existing Screw Compressor (22kw)
1 was replaced with available (11 kW) Screw Compressor.
1.31 0.009
No. of Projects : 24
18
ENCON Projects with NIL Investment
19
Energy Conservation Project 2017-18
Savings
S. No. Energy Saving Project
(Rs)
Avoiding Idle running of Slag mill Baghouse fan motor
1 GRR Blowers by giving interlock 0.45
Power savings by providing interlock for cooler ESP
2 transport system 0.24
Power saving by providing interlock of Coalmill-2
3 baghouse drier CO2CP01 with Compressor 0.13
Power reduction in STP tank aeration blowers by
stopping one blower (7.5 kW ) through
4 interconnecting both aeration Pipe lines and 0.99
replacing blower motor with 9.3 kW
Savings
S. No. Energy Saving Project
(Rs)
Reducing the Energy consumption in Crusher
7 Baghouse Purging Compressor by optimizing the 0.02
Baghouse DP
To reduce the power consumption in Line-2 CF Silo
8 Bin aeration circuit by using less capacity standby 0.04
Airslide blower
Optimization of VRPM vent Baghouse fan & 3 way
9 separator vent fan (by optimizing the air flow in VRPM 0.14
circuit )
No. of Projects : 47
27
INNOVATIVE PROJECT-1
Hot air Duct tapping from TPP to Coal mill-2
28
Innovative project-1
The line-1 was upgraded from 3500 TPD to 4600 TPD of Clinker production. To cater
this enhanced capacity of pyro system, the fuel requirement is as below…
Parameters TPD
Kiln Productivity 4600
Fuel Requirement
Petcoke 443
Coal 636
Petcoke & Coal (50:50) 534
Coal Mill-1 Fuel available Additional Fuel Coal Mill-2 Coal Mill to be
Parameters Capacity form Coal Mill-1 required Productivity run for Line-1
TPH MT MT TPH hrs
Petcoke 15 330 113 35 3
Coal 22 484 152 42 4
Petcoke & Coal (50:50) 19 407 127 32 4 29
Innovative project-1
As per the above table the Coal Mill-2 has to run additional of 3-4 hrs per
day to cater the overall fuel requirement of Line-1.
Coal Mill-2 is required to run during Line-2 shutdown also to avoid the
production loss in Line-1.
During Line-2 shutdown, we have taken the trial of Coal Mill-2 running
without hot air. But, due to insufficient air and temperature the mill was not
able to run even with the reduced feed and reduced table speed.
Hence, to run the Mill during Line-2 shutdown, it is proposed to tap the hot
air from TPP to Coal Mill Hot ESP Fan inlet. The temperature at the TPP ID
Fan outlet is maintaining around 150°C and 85000 m3/hr gas flow, which
can be utilized for the Coal grinding. The Coal Mill-2 availability requirement
30
will be as follows during Line-2 Shutdown.
Innovative project-1
Hot gas duct from TPP Hot gas duct joining coal mill-2
inlet duct
31
Innovative project-1
Coal Mill-2 requirement during Line-2 Shutdown
Additional Fuel Coal Mill-2 Coal Mill to be
Parameters required Productivity run for Line-1
MT TPH hrs
Petcoke 113 15 8
Coal 152 19 8
Petcoke & Coal (50:50) 127 17 7
The adequacy of existing Hot ESP Fan was checked and found that the fan can run with
the available hot air from TPP.
The new duct (of diameter 1.60 m) has been laid for connecting the TPP ID Fan
outlet to Coal Mill-2 Hot ESP Fan inlet.
33
Innovative project-2
We have 2*18 MW Coal based captive power plant in our cement plant.
Whenever Single line was operating , we will run Single Thermal power
plant (TPP) for plant operation and also mines de watering and
development activities.
Whenever both raw mill and slag mill run, not possible to run cement mill
and mines dewatering activities.
Now cement mill taking 8.5 MW for mill operation along with V.R.P.M, if we
reduce mill power to 7.8 MW we can able to provide power for Mines
dewatering and development activities.
34
Innovative project-2
We have measured the CA Fans flow and specific load of
separators data as shown
ZM O-Sepa
VRPM CA Fan
Fan
Steps/Speed #/% 26 32
38
Innovative project - 3
We are unloading fly ash from bulk tanker with conventional high
41
INNOVATIVE PROJECT-4
Reduction of Overall Raw mill power
consumption
42
Innovative project - 4
We have two Raw material grinding Mills (VRM) in 1986 and 2008 Raw mill-
1 7 Raw mill-2 Respectively with single CF silo around 20,000 MT capacity
in our plant.
Due to this we would maintain same raw mix for both kilns.
In raw mill-2 we have upgraded Mill main drive motor from 2800 to 3200
kW to cater gearbox motor of 3500 kW.
After that Raw mill -2 Operating 525 TPH (12600 TPD) after changing main
drive gear box.
So Our raw mill-2 Production alone is sufficient for our kiln feed requirement
for both kilns.
43
Innovative project - 4
As our Raw mill-2 is more efficient than raw mill-1 in productivity, we are
operating raw mill-2 only daily by stopping Raw mill-1.
Whenever Raw mill-2 under maintenance or CF Silo level reaches less
than 11000 MT, we run raw mill-1 for 12 Hrs.
Benefits achieved :
45
GHG Inventorisation
Total
Year
CO2e (MT)/T Cement
2016-17 660
2017-18 680
2018-19 662
2019-20 653
46
Energy Reporting Format
Pow e r Re port on
R.Hr s . Pr oduction TPH Param e te r KWH KW Kw h/ T of M ate rial Kw h/ T of Clink e r Kw h/ T of Ce m e nt
Equipm e nt
OTD M TD YTD OTD M TD YTD OTD M TD YTD OTD M TD YTD OTD M TD YTD OTD M TD YTD OTD M TD YTD OTD M TD YTD
JPM
M ine s Wate r w or k s Ravir ala
Sub Total
A uxilliaries
Main Drive
LS Cr us he r Lighting
Maintenance
Sub total
Crus he r Late r ite Cr us he r Late r ite
A dditives
A uxilliaries
Raw Mill Fan
Raw m ill -1 Latrite Crusher
Main Drive
Maintenance
Sub total
A dditives
A uxilliaries
Raw Mill Fan
Raw m ill -2 Latrite Crusher
Main Drive
Maintenance
Sub total
A uxilliaries
Coal Mill Fan
Coal m ill -1 Main Drive
Maintenance
Sub total
A uxilliaries
Coal Mill Fan
Coal m ill -2 Main Drive
Maintenance
Sub total
A uxilliaries
Coal Mill Fan
Main Drive
Coal m ill -2-1
Bin Transport
Maintenance
Sub total
A uxilliaries
Clinker Crusher
Cooler Fans
Bag House Fan
ID Fan -1
Kiln -1
ID Fan -2
Kiln Feed
Maintenance
Kiln Stoppage
Sub Total
A uxilliaries
Bag House Fan
Cooler Fans
Kiln -2 ID Fan
Kiln Feed
Maintenance
Kiln Stoppage
Sub Total
AC
Dis t. Los s e s
Lighting
Pr e Clink e r Se rvice
Wate r Pum p
Work s hop
Sub Total
Line 1 Clink e r Up to clink e r Line -1
Line 2 Clink e r Up to clink e r Line -2
Up to clinker TOTAL Upto Clink e r
Combined
A uxilliaries
Main Drive
Maintenance
Sep Fan
Ce m e nt m ill
V RPM A uxilliaries
V RPM CA Fan
V RPM Main Drive
Sub Total 0 0 0 #DIV /0! #DIV /0! #DIV /0! #DIV /0! #DIV /0! #DIV /0!
A uxilliaries
Main Drive
Maintenance
Sep Fan
Slag m ill
V RPM A uxilliaries
V RPM CA Fan
V RPM Main Drive
Sub Total 0 0 0 #DIV /0! #DIV /0! #DIV /0! #DIV /0! #DIV /0! #DIV /0!
Pos t Clink e r
Se r vice s
48
Implementing Strategy
• Department - Plant Management, Production ,Maintenance Quality
Selection Control ,Accounting
49
Core Committee Team – Energy Cell
UNIT HEAD
WORKS
HEAD
50
Responsibilities of Steering Committee
False air study in all major sections i.e., Kiln, Raw Mill, Coal Mill and Cement
Mill on monthly basis.
Monitor fan performance and initiative corrective action required, if any, on monthly
basis.
51
Quality Circle
SNO DEPT TEAM NAME PROJECT TITLE NAME
N Rama Rao
SRINIVASA RAO B
Frequent failure of Pump
Auto YELLAMANDAIAH K
1 Ramco spoorthy delivery system in mines
garage RAGHAVENDRA M
pontoon pumps
DURGA RAO P
SURA REDDY P V
A Siva Subrahmanyam
RAMANJANEYULU B
Frequent tripping of line-1 coal BALAJI R
2 Mechanical Ramco Challengers
mill with heavy vibration NUKALA HAREESH
SK AZARUDDIN
B NARENDRA
Desing Rajan
VENKATA RAMA KRISHNA D
QC - 203 VIJAY KUMAR M
3 Electrical Frequent Failure of LT Motors
Ramasethu PRASADA RAJU A
JANAKIRAMA PRASAD B
GOPI CHANDU
VARAPRASAD GVB
U SITHA RAMA RAJU
Elimination of plastic in P S CH NARESH KUMAR
4 HR Master Mind HR
department stationery items K SREEKANTH
J HARIBHASKAR
P GOPINATH 52
Quality Circle
A R V SWAROOP
RAVI B
Instrument Delay in trouble shooting of DEEPAK REDDY K
5 Ramco Rainbow
ation Limestone Reclaimer VENKATESWARA RAO CH
RAMESH VARMA P
UDAY RAJU B
Kiran Kumar N
PETCHIMUTHURAJAN
Idle running of packer-1 or
6 Mechanical Ramco Jagruthi P VEERA BABU
packer -5.
P VEERA RAJU
TVV NARENDRA
B Rambabu
SATYANARAYANA RAO K
Heavy spillage at clinker export SRINIVASA SARMA P
7 Mechanical Ramco Diamonds
conveyor. MOHAMED MEERAN
POTHURAJU S
RATNA NAYAK
Rajesh Kumar A
CH CHANDRA MOHAN
Frequent DP problem in line-2 NAGESWAR RAO P
8 Mechanical Ramco Parishkar
Coal mill bag house LAKSHMANA RAO M
NAGUL MEERA SK
53
SAI NAGA RAJU B V
Environmental Projects
700KLD Capacity Sewage water treatment plant
54
200 Kg/day Capacity Bio-gas plant
55
Solar Plant in Budawada Mines
We have installed solar panel for borewell pump from underground to supply
water to plantation in budawada mines.
56
Environmental Projects- Green Development
Colony Ground Main Gate Entrance
57
Environmental Projects- Green Development
Health center Guest house
Road sweeper
Park
58
Environmental Projects- Green Development
Mines area Reclaimer Area
59
Environmental Projects- Green Development
Admin Admin entrance
60
LED Fittings
Factory Entrance gate Factory main road
61
Environmental Projects- Green Development
Road sweeping Water Sprinkler
Machine
62
Nurseries
63
Green Belt Development
No of Saplings
Year Area covered (acres)
Planted
2020-21(Plan) 15000 10
64
Awards
65
Best Management Award received from Hon’ble Chief Minister
of AP on the occasion of May Day Celebrations - 2016
APPCB Award for
Cleaner Production Measures
05-06-2012
The Ramco Cements Limited,
KSR Nagar
05-06-2017
State Level
Environmental Award for
Better Environmental Practices
Best Supporting Organization for Quality Circle Movement - 2018
69
Quality Leadership Award in Private Sector
from QCFI – Gwalior Chapter
70
5S Conclave at Satyamangalam, Tamilnadu
71
5S Conclave at Satyamangalam, Tamilnadu
72
N a t i o n a l L e v e l E n e r g y Aw a r d s
Mines Environment & Mines Conservation
Award 2018
73
India Green Manufacturing Challenge – 2018 Silver Award
74
Forward Way to Conserve Energy
Installation of Waste Heat Recovery Systems (WHRS) for
27 MW in 3 Phases.
75
PH-2 (PHASE-1)
AQC-2 (PHASE-1)
78