Professional Documents
Culture Documents
Water Well Diagram and Proper Well Construction
Water Well Diagram and Proper Well Construction
html
[?]Subscribe To
This Site This Water Well Diagram Like 354 Share
Water Treatment
Biosand Filters
Ceramic Filters
Sawyer Filters
Sanitation 1
Sanitation 2
Poverty Solutions
Field Notes
Video Library
CLICK HERE to learn more
Get Involved about how YOU can create
Organizations lasting change!
Reading Mat'l
Groundwater Sources
Casing – The well casing lines the borehole and is often made of PVC
pipe. As stated above, if the borehole is 200mm (8 inches) then the well
casing would be 100mm (4 inches) making a space of 50mm (2 inches) all
around the casing. The bottom of the well casing is capped and the lower
section is slotted to permit water to pass into the casing.
Gravel Pack – This layer of coarse sand or gravel fills the 50mm (2 inch)
space between the well casing and the borehole. The gravel pack allows
water to flow from the aquifer into the well and should extend about 1
meter above the well screen. Manual Well Digging
It is a good idea to add a layer of clay cuttings and bentonite (that have
been removed during the drilling process) directly on top of the gravel
pack. This will help seal the gravel pack and prevent the
bentonite/cement slurry from penetrating downward into the gravel pack.
Well Site Location
The slurry is poured into the 50mm (2 inch) space around the well casing.
It should extend from the top of the gravel pack all the way up to ground
level.
The tremie method involves pumping the slurry down a small diameter
pipe like a 3/4 inch PVC pipe. The bottom of the pipe rests on top of the
gravel pack and the slurry is pumped down the pipe and deposited direcly Pump Pad Construction
on top of the gravel pack (or on top of the cuttings and bentonite layer
you layed down on top of the gravel pack).
As the slurry is deposited, the "tremie pipe" is slowly removed from the
borehole, depositing the slurry all along the length of the borehole, and
all the way to the surface.
This method helps assure a good sanitary seal that extends all the way to
the gravel pack and has no gaps or air pockets in it. Basics of Mixing Concrete
The pump pad and sanitary seal are extremely important in preventing
well contamination. It is easier to include both of these components in
smaller diameter wells (100mm-200mm) than in large diameter wells,
such as hand dug wells. This is one reason that hand dug wells are more
easily contaminated.