Restoration Dolly Project

Restoration Date : 02 Nopember 2017


Item SUV MPV
S - 051 S - 109 S - 034 S - 050
Part No. Description
Hour Prices Hour Prices Hour Prices Hour Prices
Material 340.000 340.000 340.000 340.000
Remove 1:00 1:00 1:00 1:00
Painting Masking 0:30 0:30 0:30 0:30
Primer 0:30 0:30 0:30 0:30
Top Coat 1:00 1:00 1:00 1:00
Material 240.000 240.000 240.000 240.000
Install Rubber, Spon, & Hose, Conveyor Cut 0:45 0:35 0:45 1:00
Bond 0:30 0:30 1:15 0:50
Part
Roller Conveyor
Hour
Part
Change Castor PU 5 " Swevel
Hour
Part
Change Floor Lock
Hour
Material 54.000
Frame Repair, pin Lock, Pin Castor
Hour 2:50 3:00 2:15 2:00

Total Hours 7:05 495.833 7:05 495.833 7:15 507.500 6:50 478.333
Total Material 634.000 580.000 580.000 580.000
Total 1.129.833 1.075.833 1.087.500 1.058.333
Expenses 15% 169.475 161.375 163.125 158.750
Transportasi 200.000 200.000 200.000 200.000
Grand Total 1.499.000 1.437.000 1.450.000 1.417.000

Picture :
S-051 S-109 S-034 S-050