Professional Documents
Culture Documents
Griffin 008934282
Griffin 008934282
SUBMITTED 1975-
r«<l
SCHOOL UBRAR*
UNIVERSITY OF NlfJ
13 AUG '9% !
LIBRARY jj
wmi ^ .m I
A DIRECT CURRENT TRACTION SYSTEM.
General Summary.
are presented.
CONTENTS
1.1 Inbroduction 1
2.1 Outline 14
2.6 Calculations 21
2.9 Conclusions 24
C o N T E K T S (Continued)
3.1 Outline 26
3.2 Intertripping 26
3*5 Applications 33
4.1 Summary 35
4.3 Conclusions 42
3.1 Summary 44
5-2 Losses 45
3.3 Recommendation 49
APPENDIX.
d.1 Introduction.
system.
eouinment.
Pnrrp q
1.3 History of the Present System.
Japan.
Page 2.
1.4 Type of System (Continued) .
5 minutes.
Figure 1.1.
Page 5»
6 on}
Th srm a J Be />;
Instantaneous Be/a
v*ith Time Dc/oy.
Short Core:ie_r
or Unit Circuit Breaker.
--- f----
'OOO /•>
1.5 Converting Plant.
Page 4.
J,
A A A
--—i
5 A
'VIs—
-«—~7\ 1500V
-
D.C.
sX
.jf'----
Z A A
..A
33 kV /610V
A Ar
Transformer c »>wwc * **ar
rig I'3
Silicon Kediffer firronqennent.
The early silicon rectifiers required a lot of
operation is obtained.
1.5-3- Filtering.
The output of the rectifiers must be
Page 5-
0
c
0
& vj
§ 0
£'
-x 0
o •N
» -c L
I £ <
o
J-
N uj<5 to
.5 vQ
ft
.—*■ H-
<J)
D .00
m ►- -Kfc- -© ©■* ■©) ■ —4— —Q —--- . cc Zjn+nj
11 c
I
J2_ I
SECTION
® &—•>—:—•——<r>>sv-
?\
n<Q
•5 |
LO ^
sf
BUS
___ <0
—o ©—•)-- ♦------ ©'"N*-
f:
V.
0
I Hi-
o
□ - - °! V
> -<•- —© &- —i>— —®------© 01
o 2
o
LO
L-- ♦■ij*
o—
/'°y
6t>W °L
Fig \,/\-
Substation Arrangement.
the output. For a 12 pulse rectifier the filters
in Fig. 1.4.
Detection of Faults.
A fault anywhere in the section must be
Page 6.
c~-~ 00
;r Z
o O
h- (—
O o
LU LlJ
lO CO
--------------------4
-cm-
-CZ3—<'
—IN—cm— \\ //
--cm— CO
CIRCUIT BREAKER
m— ---------------- <
uo uo
2: z.
o o
F— i—
o
a UJ
< IJO cn
AND
HZ>
FIG !•£ ARRANGEMENT OF SUBSTATIONS
-M-cm- —
\\
e> O-H i
---
-----1
----- 1 LL
Y
ro ■u
-y
-
2l
o O
h K
o O
UJ U.i
\r (S> CO
—-e*-
!----- 1
___r ■ ''
C>h
-W-a- sN y
-O- •'4
r2:^
v- j
H-
O
UJ
cO
directions are as shown. The circuit breakers
Page 7.
MAIN CONTACTS
_r jt
TRIP COIL.
CALIBRATION
SPRING
SCREWS.
HOLDING COIL
laminated
SECTION
-------
voltage.
Page 8.
Series Parai!c /
Transition
77/r> e
Page 9-
series parallel with two parallel groups of three
current 1imiting.
Page 10.
For a train ascending a grade, the torque
down.
Advantages.
Page 11.
may be placed further apart,, the conductors can
Disadvantages.
Page 12.
However if a large extension was made for
Page
CHAPTER 2 BASIC SYSTEM DESIGN.
2.1 Outline.
not be excessive.
Page 1
ConfacH WircL
SoTm.0 measures obviously would not be very
overhead system.
2.1.
Registration arms at each support structure
Page 1
2
(more than 500 mm ) . Increasing the conductor size
Page 16.
2.2.2 Substations.
Overall.
limits allowable.
Individual Substations.
largest costs are for the civil work for the building
Page 7,
approximately 30% of the cost of a substation.
Page 1 8.
Rp - KiZStstance. Os&rhed4 -
minimum voltage.
calculations.
also presented.
Page 19-
For the calculations the effect of any loads in
ignored.
circuit breaker.
Page 20.
S^Ttinc^ Cft^ 10°^
Current
SS>
2.6 Calculations.
Page 21 .
sub s tation-sectioning hut substati.on, and
See Appendix.
1 600 V.
Page 2.2.
plus Saif ion hutcosts.
WeaA S^b^taiion
2.0
uPi2rL£^t Change,
10
r p c
I tg L-’O
CZ K <Pt A 0 e. in £i/lo£'fai'[crv toS t" r \00 r/ilfOn ”
i a over \r\2d.c{ Const/\)c\ios>
2
example increasing the catenary size from 322 mm
2
to 4-22 mm would change the resistance by approximately
apart.
saving.
Page 2'5-
or less.
2.9 Conclusions.
(1) With a requirement of 5 COO A circuit breaker
Page 2 4.
For the traffic pattern already assumed, it would be
reasonable to expect thb equivalent ox a 6 000 A
recommended.
Page 25.
t
Curren
F»a 3M
ilcr/nal Prefect we Rartcjg
FIG 3*2.
Use s{ IrtecVrt pj'ito Firt^nrJ Profac'fi/r Paiioe
CHAPTER 3___ IMPROVING BASIC PROTECTION SYSTEM.
3.1 Outline.
advantage anyway.
Fa ge 26.
settings can be raised by approximately 50% above
not be much.
reduced setting.
speed.
Page 27.
in the other breaker will rise exponentially until
low level faults are not cleared until about 100 ms.
Page 28.
trip arrangement similar to a conventional high
achieved.
of isolation is needed.
control battery.
Page 29-
+ /500V. Bus
C8
Trt p Co / /
Rail
»» " if //
v5. S. 8 S.S. B
Trip
Page 30.
R1 is a calibrating resistance to ensure the
conditions.
"X1” to release.
Page 31 .
SS ‘'A' 5S"e>"
|cb“fi‘
i
Xt[—I >R1
l
C6"6’‘
$ M.C.
Fig 3'5
„Sirnple Inl&rTri pping
3-3 Alternative Methods.
will be similar.
trip on fault.
safe operation.
Page 32.
3*4 Substation Busbar Faults.
tripping direction.
3*3 Applications.
are acceptable.
Page 33-
single point load equivalent ir considered
additional substations.
Page 34.
CHAPTER 4 OTHER METHODS OP FAULT DETECTION.
4.1 Summary.
4.2.1 Description.
Page Dp.
Tcut t
Tun e
L/~L-r 0
n°rrf
At---“l\ 0
O —1.
— I, ^
.*^Vv'
y/zZa — I
-A/w^*7.' 4J ;
r. u,~ R L Rz Li ^ if'-'
0>) — Ie
Shunt Circuit
C~Currmi 1/ to
Tf p Circa t Breaker
FIG 4-3
MODIFICATION CF SifTT ilk4G i>UE
TO INDUCTIVE silt/iVT ClALUir
If all the main current is passed through
where:-
Feeder resistance
Feeder inductance
Resistance of shunt
Inductance of shunt
I1 = R2 x I - (1)
Ryj + Rp
transient conditions.
Page 36.
This is shown in Figure 4.3 (a) and (b) .
as: -
+ I R. -(R1+R0)t )
1 - e -r—rr ) - (2)
r1+r2 b/j +L2
)
c t t )
I1 = IB (c(e T - e T? ) + (1 - e ^ )) - (3)
(1 - e rjT~ ) “ (^0
‘3
For T = T
a
then ly, max. = BI D, -(b)
1 a ta
Page 37.
T - SC mse c.
T = dSm s
3000 ----------
/OO kA/.ie c
RATE OF RISE
FIG.4'fDYNAMIC CHARACTERISTIC OF A MAGNETICALLY
HELD CIRCUIT BREAKER
If I d is the steady state current that will
a' and b *
T = = time constant at the shunt loop.
4.2.2 Disadvantages.
A number of disadvantages soon became
apparent when the rate of rise characteristic was
Page 38-
Magnetically He’d
Circuit Breaker.
s fau/1
\ Currarita
Else, front I c
Cur
Load Currents
tO kA/Sec.
Rate of rise
FIG 4-5
Corf-.pancoA lotttland CuJlf oKaratVv
faults.
4.3.1 General.
occur.
Page 39 •
Rate Load
Fau! t
T max load
F m c/x faults
T/me de tting -
A B
Fault Trips
and the rate of rise must stay above the switch off
Figure 4-7-
The timer must remain on for the setting
Page 40 -
mal-operation due to the timer resetting if a drop in
undervoltage relays.
Page 41.
relay could only see the arc voltage at the fault,
4-.5 Conclusions.
-t age 4-2.
Quite a good system can be built up by
a.new system.
Page 43.
CHAPTER ^ CONCLUSIONS AND RECOMMENDATIONS.
5-1 Summary.
Page 4-4.
that increasing the size of catenary to reduce the
5.2 Losses.
Page 45'
Fig '
5 i ScAo. I Cost Cofvss.
3 000 A.
5.2.3 Results.
The curves showed the costs relative
Page 46-
A B
ROC R»Ox)
-v\AA —sAAA—
Loa ci
Fig 5'2
Resistounce VemwttoA m a
5.2.3 Results (Continued)
in the area below curve (c), and that the cost and
optimum spacing will be about the same.
Because of the other advantages of a
consideration.
5.2.4 Variations .
Cs - § - (1)
10L
L is section length in km
Page 47.
The losses vd.ll be dependent on the
B.
The effective resistance R* at any point
moves.
R' = RX-R(1-X)
RX+RC1-X)
= R(X-X2)
is j
Page 48 .
The annual cost of losses will he
3 500 L E N - ( 5)
$
where L Section Length (km)
+ C- 3 500 L E N - (4)
10L F
dO » -S o + 3 500 E If a 0 - (5)
dL 10L^ F
F = 6
L = / S = 8 km a
V5 800 E N
number of trains.
5.5 Recommendations.
Page 49.
the traffic is heavy, the recommended construction
to be tolerated.
Page 50 .
BIBLIOGRAPHY.
are used:
1)
G .3. Circuit Breaker.
S.S. Substation.
2)
The overhead wiring construction used-, is
specified by the cross sectional area in square
wire(s).
3)
The voltage drop curves in the Appendix
amperes.
APPENDIX A
/O
O'
Cf»
c
vn
\v
v
s
s»
cii
-t--'
"-S
0
S.
O
£
£
rj
"s^
LcAtAfK fk^
11.00
i l 00
2. 4- if
£ub.<,i ttfiovi H ui i> faring (kfli)
^
a t Loa
oliacte.
\0