2.0 EARTHWORKS
Layout/staking
2x3 Coco Lumber pcs 50 150.00 7,500.00 1,500.00 9,000.00
CWN 4 kgs 5 90.00 450.00 90.00 540.00
Tansi rolls 5 30.00 150.00 30.00 180.00
8,100.00 1,620.00 9,720.00
Excavation Column/Footing
13.824 cu.m Bareta pcs 4 450.00 1,800.00 6,912.00 8,712.00
8 col Pala pcs 4 450.00 1,800.00 1,800.00
3,600.00 6,912.00 10,512.00
Excavation FTB
5.76 cu.m - 2,880.00 2,880.00
32 m - -
- 2,880.00 2,880.00
Excavation Septic Tank -
5.40 cu.m - 2,700.00 2,700.00
- -
- 2,700.00 2,700.00
Backfill and Compaction
30.57 cu.m Escombro cu.m 82.25 240.00 19,740.00 13,982.50 33,722.50
19,740.00 13,982.50 33,722.50
Soil Poisoning
32 sq.m Soil Guard gal 1 3,500.00 3,500.00 525.00 4,025.00
3,500.00 525.00 4,025.00
Gravel Bedding
1.6 cu.m 3/4 Gravel cu.m 4.1 1,950.00 7,995.00 820.00 8,815.00
Kartilya pcs 1 3,000.00 3,000.00 3,000.00
10,995.00 820.00 11,815.00
TOTAL EARTHWORKS/BARRACKS 95,879.00
LABOR COST 32,114.00 50.36%
MATERIALS COST 63,765.00
3.0 CONCRETE WORKS
Footing -
3.456 cu.m Cement bags 28 210.00 5,806.08 1,451.52 7,257.60
5.608 hrs Sand cu.m 2.985984 950.00 2,836.68 709.17 3,545.86
3/4 Gravel cu.m 4.478976 1,950.00 8,734.00 2,183.50 10,917.50
Gasoline liters 5 50.00 250.00 62.50 312.50
17,626.77 4,406.69 22,033.46
Labor 6 2419.2
1 cu.m/man-day 0.96 days
Labor 2
1 cu.m/man-day 2.7 days
Foreman 1 700 700 87.5 5.608 490.700
Leadman 1 600 600 75 5.608 420.600
Mason 2 550 1100 137.5 5.608 771.100
Labor 8 450 3600 450 5.608 2,523.600
6 bags/hr 0 4,206.000
21,606.000
Foreman 1 700 700 87.5 5 437.5
Leadman 1 600 600 75 5 375
Mason/Carpenter 4 550 2200 275 5 1375
Labor 6 420 2520 315 5 1575
3,762.50
Foreman 700 0 0 8 0
Leadman 1 600 600 75 8 600
Mason/Carpenter 2 550 1100 137.5 8 1100
Labor 2 420 840 105 8 840
2,540.00
Foreman 700 0 0 0
Leadman 1 600 600 75 3 225
Mason/Carpenter 2 550 1100 137.5 3 412.5
Labor 2 420 840 105 3 315
952.50
Foreman 700 0 0 0
Leadman 600 0 0 0
Mason/Carpenter 1 550 550 68.75 2 137.5
Labor 2 420 840 105 2 210
347.50
52,752.50
Foreman 700 0 0 0
Leadman 600 0 0 0
Mason/Steelman 1 550 550 68.75 48 3300
Labor 2 420 840 105 48 5040
8,340.00
Foreman 700 0 0 0
Leadman 600 0 0 0
Mason/Steelman 2 550 1100 137.5 55 7562.5
Labor 3 420 1260 157.5 55 8662.5
16,225.00
TRUSSES
40,780.33
14,680.92
ROOF 24,576.41
27,487.46
9,895.49
37,382.95
Thank you.
o.com
Remarks
MATERIALS DESCRIPTION UNIT QTY PRICE MATERIALS LABOR TOTAL AMOUNT
AMOUNT AMOUNT
1.0 BARRACKS/ FENCE 2x3 Coco Lumber pcs 30 140 4,200.00 630.00 4,830.00
CWN 2 kgs 3 60 180.00 27.00 207.00
CWN3 kgs 5 70 350.00 52.50 402.50
Corr.roof pcs 10 320 3,200.00 480.00 3,680.00
U.Nail kgs 5 120 600.00 90.00 690.00
3/8 Formply pcs 10 580 5,800.00 870.00 6,670.00
Bluesack roll 1 3500 3,500.00 525.00 4,025.00
17,830.00 2,674.50 20,504.50
2.0 EARTHWORKS
Layout/staking
2x3 Coco Lumber pcs 50 150.00 7,500.00 1,500.00 9,000.00
CWN 4 kgs 5 90.00 450.00 90.00 540.00
Tansi rolls 5 30.00 150.00 30.00 180.00
8,100.00 1,620.00 9,720.00
Excavation Column/Footing
13.824 cu.m Bareta pcs 4 450.00 1,800.00 6,912.00 8,712.00
8 col Pala pcs 4 450.00 1,800.00 1,800.00
3,600.00 6,912.00 10,512.00
Excavation FTB
5.76 cu.m - 2,880.00 2,880.00
32 m - -
- 2,880.00 2,880.00
Excavation Septic Tank -
5.40 cu.m - 2,700.00 2,700.00
- -
- 2,700.00 2,700.00
Backfill and Compaction
30.57 cu.m Escombro cu.m 82.25 240.00 19,740.00 13,982.50 33,722.50
19,740.00 13,982.50 33,722.50
Soil Poisoning
32 sq.m Soil Guard gal 1 3,500.00 3,500.00 525.00 4,025.00
3,500.00 525.00 4,025.00
Gravel Bedding
1.6 cu.m 3/4 Gravel cu.m 4.1 1,950.00 7,995.00 820.00 8,815.00
Kartilya pcs 1 3,000.00 3,000.00 3,000.00
10,995.00 820.00 11,815.00
TOTAL EARTHWORKS/BARRACKS 95,879.00
LABOR COST 32,114.00 50.36%
MATERIALS COST 63,765.00
3.0 CONCRETE WORKS
Footing -
3.456 cu.m Cement bags 28 210.00 5,806.08 1,451.52 7,257.60
5.608 hrs Sand cu.m 2.98598 950.00 2,836.68 709.17 3,545.86
3/4 Gravel cu.m 4.47898 1,950.00 8,734.00 2,183.50 10,917.50
Gasoline liters 5 50.00 250.00 62.50 312.50
17,626.77 4,406.69 22,033.46
Labor 6 2419.2
1 cu.m/man-day 0.96 days
Labor 2
1 cu.m/man-day 2.7 days
Foreman 1 700 700 87.5 5.608 490.700
Leadman 1 600 600 75 5.608 420.600
Mason 2 550 1100 137.5 5.608 771.100
Labor 8 450 3600 450 5.608 2,523.600
6 bags/hr 0 4,206.000
21,606.000
Foreman 1 700 700 87.5 5 437.5
Leadman 1 600 600 75 5 375
Mason/Carpenter 4 550 2200 275 5 1375
Labor 6 420 2520 315 5 1575
3,762.50
Foreman 700 0 0 8 0
Leadman 1 600 600 75 8 600
Mason/Carpenter 2 550 1100 137.5 8 1100
Labor 2 420 840 105 8 840
2,540.00
Foreman 700 0 0 0
Leadman 1 600 600 75 3 225
Mason/Carpenter 2 550 1100 137.5 3 412.5
Labor 2 420 840 105 3 315
952.50
Foreman 700 0 0 0
Leadman 600 0 0 0
Mason/Carpenter 1 550 550 68.75 2 137.5
Labor 2 420 840 105 2 210
347.50
52,752.50
Foreman 700 0 0 0
Leadman 600 0 0 0
Mason/Steelman 1 550 550 68.75 48 3300
Labor 2 420 840 105 48 5040
8,340.00
Foreman 700 0 0 0
Leadman 600 0 0 0
Mason/Steelman 2 550 1100 137.5 55 7562.5
Labor 3 420 1260 157.5 55 8662.5
16,225.00
TRUSSES
40,780.33
14,680.92
ROOF 24,576.41
27,487.46
9,895.49
37,382.95