SMS-H-90-A02

Drydock Work Order

Vessel Name: Sakhalin Island Report Date: Spec No:


Location of Repairs: BLS Housing support to Side Shell cracks
Job Description: This job Requires:
Gas Free Certificate
The web and welding to be repaired.
Hot Work
Lighting
Ventilation
Staging
Cleaning before
Cleaning after
Crane
Transport inside yard
Transport outside yard
Access
Pressure testing
Corrosion Protection
Paint Work
Materials by Owner
Materials by yard supply
Heating
Others
Attached:
Drawing
Sketch
Sample
The work to be surveyed by:
Class
Manufacturers
Others

Special Remarks:
1. All jobs to be arrange in the Safe manner – Safety Comes First!
2. The new details shown in RED.
3. All base information using for present Spec add to ANNEX.
4. All jobs have to be provide according IACS No. 47 Shipbuilding and Repair Quality Standard and
Class rules.

Controlled Revision: 09/09/2013


Approved by MR/COO
Page 1 of 6
SMS-H-90-A02
Drydock Work Order

Sketch1. Destroyed area.

Sketch2.

Controlled Revision: 09/09/2013


Approved by MR/COO
Page 2 of 6
SMS-H-90-A02
Drydock Work Order

Sketch3.

Sketch4. Welding details

Controlled Revision: 09/09/2013


Approved by MR/COO
Page 3 of 6
SMS-H-90-A02
Drydock Work Order

Repairer to allow:
1. Hang stages to be provide for the cutting of existing structure, installation, welding and
painting of the new structure. The size to be recognized on spot.
2. Take measure of existing construction, produce new plate.
3. Cut the vertical plate.
4. Prepare all edges for new plate installation.
5. Fit new plate by tack welding.
6. Start welding.
7. The welding shape to be the same as on existing construction.
8. The vertical batt joint is to be flash ground.

Material calculation table.


Calculation done with approximate weight.
Description / View / Section / Weight,
No. Size, mm Quantity Remark
location Det. No. kg
1 Vertical plate PORT 20x500x1000 1 80.00 AH
Total: 80.00

9. Material of the new structures: Steel grade is “AH”.


10. Welding is to be provide with Low Hydrogen electrodes “SPECIAL-303N” – UNITOR
Manufacturer (for example) or alternative approved by Class WPS.
Welder is to be qualified and certified.
All completed welding to be 100% visually inspected and confirmed by Owner
representative.
11. Materials and welding in accordance with Class Rules to Surveyor’s satisfaction.
12. Painting.
The new steel plate and damaged coating of hull structures due to hot works shell be coat /
recoat in compliance with the vessel’s Painting Specification. The paint colour shall be as
surround.

Controlled Revision: 09/09/2013


Approved by MR/COO
Page 4 of 6
SMS-H-90-A02
Drydock Work Order

ANNEX

A1.

A2.

A3.

Controlled Revision: 09/09/2013


Approved by MR/COO
Page 5 of 6
SMS-H-90-A02
Drydock Work Order

Controlled Revision: 09/09/2013


Approved by MR/COO
Page 6 of 6