Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 783

CRYSTAL DREAMS DEVELOPMENT CORPORATION

LIST OF COMPLETED PROJECTS


AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor Area TOILET & BED ROOMS CAR SELLING Remarks
No. No. BATH GARAGE PRICE

20 1 1 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED Completion


GUITNANG BAYAN II, Jan. 2017
SAN MATEO, RIZAL

26 1 7 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED Completion


GUITNANG BAYAN II, Jan. 2017
SAN MATEO, RIZAL

36 8 9 2 ABUAB II ROAD , 101 61.9 2 3 3 3,048,750 RESERVED Completion


GUITNANG BAYAN II, Jan. 2017
SAN MATEO, RIZAL

70 1 21 1 ABUAB II ROAD , 65 60.94 2 3 1 2,638,125 RESERVED Completion


GUITNANG BAYAN II, Dec. 2016
SAN MATEO, RIZAL

73 1 24 1 ABUAB II ROAD , 64 60.94 2 3 1 2,728,125 SOLD 1-9- Completion


GUITNANG BAYAN II, 2017 Dec. 2016
SAN MATEO, RIZAL

74 2 9 1 ABUAB II ROAD , 82 91.65 2 3 1 3,965,625 RESERVED Completion


GUITNANG BAYAN II, Aug. 2016
SAN MATEO, RIZAL

75 2 10 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED Completion


GUITNANG BAYAN II, Jan. 2017
SAN MATEO, RIZAL
76 2 11 1 ABUAB II ROAD , 60 60.94 2 3 1 2,626,875 SOLD 1-14- Completion
GUITNANG BAYAN II, 2017 Dec. 2016
SAN MATEO, RIZAL

Unit Blk. Lot PH LOCATION Lot Area Floor Area TOILET & BED ROOMS CAR SELLING Remarks
No. No. BATH GARAGE PRICE

87 2 6 1 ABUAB II ROAD , 60 60.94 2 3 1 2,626,875 SOLD 1-9- Completion


GUITNANG BAYAN II, 2017 Dec. 2016
SAN MATEO, RIZAL

88 2 7 1 ABUAB II ROAD , 60 60.94 2 3 1 2,626,875 RESERVED Completion


GUITNANG BAYAN II, Dec. 2016
SAN MATEO, RIZAL

89 2 8 1 ABUAB II ROAD , 82 91.65 2 3 1 3,965,625 RESERVED Completion


GUITNANG BAYAN II, Aug. 2016
SAN MATEO, RIZAL
CRYSTAL DREAMS DEVELOPMENT CORPORATION
LIST OF ON-GOING PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Floor TOILET & BED CAR SELLING Remarks
No. No. Area Area BATH ROOMS GARAGE PRICE

1 1 17 1 ABUAB ROAD II, 80 66 2 3 2 3,060,000 RESERVED On-going


GUITNANG BAYAN II,
SAN MATEO, RIZAL

9 1 9 1 ABUAB ROAD II, 116 137 2 3 2 4,083,750 RESERVED On-going


GUITNANG BAYAN II,
SAN MATEO, RIZAL

21 1 2 1 ABUAB ROAD II, 60 61.9 2 3 1 2,626,875 RESERVED On-going


GUITNANG BAYAN II,
SAN MATEO, RIZAL

27 1 8 1 ABUAB ROAD II, 100 97.68 2 3 3 4,246,875 RESERVED On-going


GUITNANG BAYAN II,
SAN MATEO, RIZAL

90 3 9 1 ABUAB ROAD II, 82 96.66 2 3 1 3,965,625 RESERVED On-going


GUITNANG BAYAN II,
SAN MATEO, RIZAL

97 3 16 1 ABUAB ROAD II, 60 61.9 2 3 1 2,565,000 RESERVED On-going


GUITNANG BAYAN II,
SAN MATEO, RIZAL

100 3 3 2 ABUAB ROAD II, 60 61.9 2 3 1 2,649,375 RESERVED On-going


GUITNANG BAYAN II,
SAN MATEO, RIZAL
105 3 8 2 ABUAB ROAD II, 82 96.66 2 3 1 3,965,625 RESERVED On-going
GUITNANG BAYAN II,
SAN MATEO, RIZAL
CRYSTAL DREAMS DEVELOPMENT CORPORATION
LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
2 1 16 1 ABUAB II ROAD , 80 66 2 3 2 3,037,500
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

3 1 15 1 ABUAB II ROAD , 80 66 2 3 2 3,037,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

4 1 14 1 ABUAB II ROAD , 80 66 2 3 2 3,037,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

5 1 13 1 ABUAB II ROAD , 80 66 2 3 2 3,037,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

6 1 12 1 ABUAB II ROAD , 80 66 2 3 2 3,037,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

7 1 11 1 ABUAB II ROAD , 80 66 2 3 2 3,037,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

8 1 10 1 ABUAB II ROAD , 80 66 2 3 2 3,037,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

10 8 19 2 ABUAB II ROAD , 100 82.8 2 3 2 3,521,250 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
11 8 18 2 ABUAB II ROAD , 80 66 2 3 2 3,037,500 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

12 8 17 2 ABUAB II ROAD , 80 66 2 3 2 3,037,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

13 8 16 2 ABUAB II ROAD , 80 66 2 3 2 3,037,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

CRYSTAL DREAMS DEVELOPMENT CORPORATION


LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
14 8 15 2 ABUAB II ROAD , 80 66 2 3 2 3,037,500 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

15 8 14 2 ABUAB II ROAD , 80 66 2 3 2 3,037,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

16 8 13 2 ABUAB II ROAD , 80 66 2 3 2 3,037,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

17 8 12 2 ABUAB II ROAD , 80 66 2 3 2 3,037,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

18 8 11 2 ABUAB II ROAD , 80 66 2 3 2 3,037,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
19 8 10 2 ABUAB II ROAD , 81 70.44 2 3 2 3,172,500 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

22 1 3 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

23 1 4 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

24 1 5 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

25 1 6 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

28 8 1 2 ABUAB II ROAD , 90 97.68 2 3 2 4,117,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

CRYSTAL DREAMS DEVELOPMENT CORPORATION


LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
29 8 2 2 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

30 8 3 2 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
31 8 4 2 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

32 8 5 2 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

33 8 6 2 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

34 8 7 2 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

35 8 8 2 ABUAB II ROAD , 60 61.9 2 3 1 2,497,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

37 7 11 3 ABUAB II ROAD , 60 61.9 2 3 1 2,643,750 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

38 7 10 3 ABUAB II ROAD , 61 61.9 2 3 1 2,649,375


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

39 7 9 3 ABUAB II ROAD , 63 61.9 2 3 1 2,666,250


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

40 7 8 3 ABUAB II ROAD , 64 61.9 2 3 1 2,688,750


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

CRYSTAL DREAMS DEVELOPMENT CORPORATION


LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017
Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
41 7 7 3 ABUAB II ROAD , 65 61.9 2 3 1 2,705,625
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

42 7 6 3 ABUAB II ROAD , 67 61.9 2 3 1 2,722,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

43 7 5 3 ABUAB II ROAD , 68 61.9 2 3 1 2,739,375


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

44 7 4 3 ABUAB II ROAD , 70 61.9 2 3 1 2,756,250


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

45 7 3 3 ABUAB II ROAD , 71 61.9 2 3 1 2,773,125 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

46 7 2 3 ABUAB II ROAD , 73 61.9 2 3 1 2,795,625 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

47 7 1 3 ABUAB II ROAD , 117 61.9 2 3 3 3,346,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

48 4 20 3 ABUAB II ROAD , 60 61.9 2 3 1 2,643,750 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

49 4 19 3 ABUAB II ROAD , 62 61.9 2 3 1 2,643,750 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
50 4 18 3 ABUAB II ROAD , 63 61.9 2 3 1 2,660,625
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

51 4 17 3 ABUAB II ROAD , 64 61.9 2 3 1 2,671,875


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

CRYSTAL DREAMS DEVELOPMENT CORPORATION


LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
52 4 16 3 ABUAB II ROAD , 65 61.9 2 3 1 2,683,125 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

53 4 15 2 ABUAB II ROAD , 66 61.9 2 3 1 2,700,000


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

54 4 14 2 ABUAB II ROAD , 67 61.9 2 3 1 2,711,250 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

55 4 13 2 ABUAB II ROAD , 68 61.9 2 3 1 2,728,125 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

56 4 12 2 ABUAB II ROAD , 69 61.9 2 3 1 2,739,375 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

57 4 11 2 ABUAB II ROAD , 70 61.9 2 3 1 2,756,250


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
58 4 10 2 ABUAB II ROAD , 72 61.9 2 3 1 2,767,500
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

59 4 9 2 ABUAB II ROAD , 73 61.9 2 3 1 2,778,750


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

60 4 8 2 ABUAB II ROAD , 74 61.9 2 3 1 2,795,625


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

61 4 7 2 ABUAB II ROAD , 75 61.9 2 3 1 2,806,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

62 4 6 2 ABUAB II ROAD , 76 61.9 2 3 1 2,823,750 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

CRYSTAL DREAMS DEVELOPMENT CORPORATION


LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
63 4 5 2 ABUAB II ROAD , 77 61.9 2 3 1 2,835,000 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

64 4 4 1 ABUAB II ROAD , 80 61.9 2 3 1 2,880,000 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

65 4 3 1 ABUAB II ROAD , 89 61.9 2 3 1 2,986,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
66 4 2 1 ABUAB II ROAD , 86 61.9 2 3 1 2,947,500 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

67 4 1 1 ABUAB II ROAD , 142 74.5 2 3 3 3,588,750 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

68 1 19 1 ABUAB II ROAD , 84 61.9 2 3 1 2,812,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

69 1 20 1 ABUAB II ROAD , 65 61.9 2 3 1 2,559,375


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

71 1 22 1 ABUAB II ROAD , 64 61.9 2 3 1 2,728,125 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

72 1 23 1 ABUAB II ROAD , 64 61.9 2 3 1 2,728,125 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

77 2 12 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

78 2 13 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

CRYSTAL DREAMS DEVELOPMENT CORPORATION


LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
79 2 14 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

80 2 15 1 ABUAB II ROAD , 60 61.9 2 3 1 2,497,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

81 2 16 1 ABUAB II ROAD , 60 61.9 2 3 1 2,565,000 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

82 2 1 1 ABUAB II ROAD , 60 61.9 2 3 1 2,565,000 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

83 2 2 1 ABUAB II ROAD , 60 61.9 2 3 1 2,497,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

84 2 3 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

85 2 4 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

86 2 5 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

91 3 10 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
92 3 11 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

93 3 12 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

CRYSTAL DREAMS DEVELOPMENT CORPORATION


LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
94 3 13 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

95 3 14 1 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

96 3 15 1 ABUAB II ROAD , 60 61.9 2 3 1 2,497,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

97 3 16 1 ABUAB II ROAD , 60 61.9 2 3 1 2,565,000 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

98 3 1 2 ABUAB II ROAD , 60 61.9 2 3 1 2,565,000 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

99 3 2 2 ABUAB II ROAD , 60 61.9 2 3 1 2,497,500 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
101 3 4 2 ABUAB II ROAD , 60 61.9 2 3 1 2,649,375 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

102 3 5 2 ABUAB II ROAD , 60 61.9 2 3 1 2,649,375 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

103 3 6 2 ABUAB II ROAD , 60 61.9 2 3 1 2,649,375 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

104 3 7 2 ABUAB II ROAD , 60 61.9 2 3 1 2,649,375 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

106 5 9 2 ABUAB II ROAD , 68 61.9 2 3 1 2,621,250 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

CRYSTAL DREAMS DEVELOPMENT CORPORATION


LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
107 5 7 2 ABUAB II ROAD , 83 83.89 2 3 2 3,583,125 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

108 5 6 2 ABUAB II ROAD , 82 83.89 2 3 2 3,594,375 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

109 5 5 2 ABUAB II ROAD , 82 83.89 2 3 2 3,594,375 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
110 5 4 2 ABUAB II ROAD , 82 83.89 2 3 2 3,594,375 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

111 5 3 2 ABUAB II ROAD , 83 83.89 2 3 2 3,583,125 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

112 5 2 2 ABUAB II ROAD , 68 61.9 2 3 1 2,621,250 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

113 5 1 2 ABUAB II ROAD , 68 61.9 2 3 1 2,615,625 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

114 5 8 2 ABUAB II ROAD , 68 61.9 2 3 1 2,615,625 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

115 6 9 3 ABUAB II ROAD , 82 96.66 2 3 1 3,965,625 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

116 6 10 3 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

117 6 11 3 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

CRYSTAL DREAMS DEVELOPMENT CORPORATION


LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
118 6 12 3 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

119 6 13 3 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

120 6 14 3 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

121 6 15 3 ABUAB II ROAD , 60 61.9 2 3 1 2,497,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

122 6 16 3 ABUAB II ROAD , 60 61.9 2 3 1 2,565,000 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

123 6 1 3 ABUAB II ROAD , 60 61.9 2 3 1 2,565,000 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

124 6 2 3 ABUAB II ROAD , 60 61.9 2 3 1 2,497,500


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

125 6 3 3 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

126 6 4 3 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
127 6 5 3 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

128 6 6 3 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL

CRYSTAL DREAMS DEVELOPMENT CORPORATION


LIST OF PROSPECTIVE PROJECTS
AS OF JANUARY 2017

Unit Blk. Lot PH LOCATION Lot Area Floor TOILET & BED CAR SELLING Remarks
No. No. Area BATH ROOMS GARAGE PRICE
129 6 7 3 ABUAB II ROAD , 60 61.9 2 3 1 2,626,875 RESERVED
GUITNANG BAYAN
II, SAN MATEO,
RIZAL

130 6 8 3 ABUAB II ROAD , 82 96.66 2 3 1 3,965,625 RESERVED


GUITNANG BAYAN
II, SAN MATEO,
RIZAL
Unit Blk. Lot No. Phase Lot Floor Title No. Tax Dec. No.
No. Area Area
Land Bldg.

1 1 17 1 80 66 009-2016008456 15-SM-008-07041
2 1 16 1 80 66 009-2016008455 15-SM-008-07040
3 1 15 1 80 66 009-2016008454 15-SM-008-07039
4 1 14 1 80 66 009-2016008453 15-SM-008-07038
5 1 13 1 80 66 009-2016008452 15-SM-008-07037
6 1 12 1 80 66 009-2016008451 15-SM-008-07036
7 1 11 1 80 66 009-2016008450 15-SM-008-07035
8 1 10 1 80 66 009-2016008449 15-SM-008-07034
9 1 9 1 116 137 009-2016008448 15-SM-008-07033
10 8 19 2 100 82.8 009-2016008570 15-SM-008-06923
11 8 18 2 80 66 009-2016008569 15-SM-008-06922
12 8 17 2 80 66 009-2016008568 15-SM-008-06921
13 8 16 2 80 66 009-2016008567 15-SM-008-06920
14 8 15 2 80 66 009-2016008566 15-SM-008-06919
15 8 14 2 80 66 009-2016008565 15-SM-008-06918
16 8 13 2 80 66 009-2016008564 15-SM-008-06917
17 8 12 2 80 66 009-2016008563 15-SM-008-06916
18 8 11 2 80 66 009-2016008562 15-SM-008-06915
19 8 10 2 81 70.44 009-2016008561 15-SM-008-06914
20 1 1 1 60 61.9 009-2016008440 15-SM-008-07025
21 1 2 1 60 61.9 009-2016008441 15-SM-008-07026
22 1 3 1 60 61.9 009-2016008442 15-SM-008-07027
23 1 4 1 60 61.9 009-2016008443 15-SM-008-07028
24 1 5 1 60 61.9 009-2016008444 15-SM-008-07029
25 1 6 1 60 61.9 009-2016008445 15-SM-008-07030
26 1 7 1 60 61.9 009-2016008446 15-SM-008-07031
27 1 8 1 100 97.68 009-2016008447 15-SM-008-07032
28 8 1 2 90 97.68 009-2016008552 15-SM-008-06924
29 8 2 2 60 61.9 009-2016008553 15-SM-008-06925
30 8 3 2 60 61.9 009-2016008554 15-SM-008-06926
Unit Blk. Lot No. Phase Lot Floor Title No. Tax Dec. No.
No. Area Area
Land Bldg.

31 8 4 2 60 61.9 009-2016008555 15-SM-008-06927


32 8 5 2 60 61.9 009-2016008556 15-SM-008-06928
33 8 6 2 60 61.9 009-2016008557 15-SM-008-06929
34 8 7 2 60 61.9 009-2016008558 15-SM-008-06930
35 8 8 2 60 61.9 009-2016008559 15-SM-008-06931
36 8 9 2 101 61.9 009-2016008560 15-SM-008-06913
37 7 11 3 60 61.9 009-2016008551 15-SM-008-06912
38 7 10 3 61 61.9 009-2016008550 15-SM-008-06911
39 7 9 3 63 61.9 009-2016008549 15-SM-008-06910
40 7 8 3 64 61.9 009-2016008548 15-SM-008-06909
41 7 7 3 65 61.9 009-2016008547 15-SM-008-06908
42 7 6 3 67 61.9 009-2016008546 15-SM-008-06907
43 7 5 3 68 61.9 009-2016008545 15-SM-008-06906
44 7 4 3 70 61.9 009-2016008544 15-SM-008-06905
45 7 3 3 71 61.9 009-2016008543 15-SM-008-06904
46 7 2 3 73 61.9 009-2016008542 15-SM-008-06903
47 7 1 3 117 61.9 009-2016008541 15-SM-008-06902
48 4 20 3 60 61.9 009-2016008515 15-SM-008-06961
49 4 19 3 62 61.9 009-2016008514 15-SM-008-06962
50 4 18 3 63 61.9 009-2016008513 15-SM-008-06963
51 4 17 3 64 61.9 009-2016008512 15-SM-008-06964
52 4 16 3 65 61.9 009-2016008511 15-SM-008-06965
53 4 15 2 66 61.9 009-2016008510 15-SM-008-06966
54 4 14 2 67 61.9 009-2016008509 15-SM-008-06967
55 4 13 2 68 61.9 009-2016008508 15-SM-008-06968
56 4 12 2 69 61.9 009-2016008507 15-SM-008-06969
57 4 11 2 70 61.9 009-2016008506 15-SM-008-06970
58 4 10 2 72 61.9 009-2016008505 15-SM-008-06971
59 4 9 2 73 61.9 009-2016008504 15-SM-008-06972
60 4 8 2 74 61.9 009-2016008503 15-SM-008-06973
Unit Blk. Lot No. Phase Lot Floor Title No. Tax Dec. No.
No. Area Area
Land Bldg.

61 4 7 2 75 61.9 009-2016008502 15-SM-008-06974


62 4 6 2 76 61.9 009-2016008501 15-SM-008-06975
63 4 5 2 77 61.9 009-2016008500 15-SM-008-06976
64 4 4 1 80 61.9 009-2016008499 15-SM-008-06977
65 4 3 1 89 61.9 009-2016008498 15-SM-008-06978
66 4 2 1 86 61.9 009-2016008497 15-SM-008-06979
67 4 1 1 142 74.5 009-2016008496 15-SM-008-06980
68 1 19 1 84 61.9 009-2016008458 15-SM-008-06982
69 1 20 1 65 61.9 009-2016008459 15-SM-008-06983
70 1 21 1 65 60.94 009-2016008460 15-SM-008-06984 15-SM-008-07044
71 1 22 1 64 61.9 009-2016008461 15-SM-008-06985
72 1 23 1 64 61.9 009-2016008462 15-SM-008-06986
73 1 24 1 64 60.94 009-2016008463 15-SM-008-06987 15-SM-008-07045
74 2 9 1 82 91.65 009-2016008472 15-SM-008-06990 15-SM-008-07046
75 2 10 1 60 61.9 009-2016008473 15-SM-008-06991
76 2 11 1 60 60.94 009-2016008474 15-SM-008-06992 15-SM-008-07047
77 2 12 1 60 61.9 009-2016008475 15-SM-008-06993
78 2 13 1 60 61.9 009-2016008476 15-SM-008-06994
79 2 14 1 60 61.9 009-2016008477 15-SM-008-06995
80 2 15 1 60 61.9 009-2016008478 15-SM-008-06996
81 2 16 1 60 61.9 009-2016008479 15-SM-008-06997
82 2 1 1 60 61.9 009-2016008464 15-SM-008-06998
83 2 2 1 60 61.9 009-2016008465 15-SM-008-06999
84 2 3 1 60 61.9 009-2016008466 15-SM-008-07000
85 2 4 1 60 61.9 009-2016008467 15-SM-008-07001
86 2 5 1 60 61.9 009-2016008468 15-SM-008-07002
87 2 6 1 60 60.94 009-2016008469 15-SM-008-07003 15-SM-008-07048
88 2 7 1 60 60.94 009-2016008470 15-SM-008-07004 15-SM-008-07049
89 2 8 1 82 91.65 009-2016008471 15-SM-008-07005 15-SM-008-07050
90 3 9 1 82 96.66 009-2016008488 15-SM-008-07007
Unit Blk. Lot No. Phase Lot Floor Title No. Tax Dec. No.
No. Area Area
Land Bldg.

91 3 10 1 60 61.9 009-2016008489 15-SM-008-07008


92 3 11 1 60 61.9 009-2016008490 15-SM-008-07009
93 3 12 1 60 61.9 009-2016008491 15-SM-008-07010
94 3 13 1 60 61.9 009-2016008492 15-SM-008-07011
95 3 14 1 60 61.9 009-2016008493 15-SM-008-07012
96 3 15 1 60 61.9 009-2016008494 15-SM-008-07013
97 3 16 1 60 61.9 009-2016008495 15-SM-008-07014
98 3 1 2 60 61.9 009-2016008480 15-SM-008-07015
99 3 2 2 60 61.9 009-2016008481 15-SM-008-07016
100 3 3 2 60 61.9 009-2016008482 15-SM-008-07017
101 3 4 2 60 61.9 009-2016008483 15-SM-008-07018
102 3 5 2 60 61.9 009-2016008484 15-SM-008-07019
103 3 6 2 60 61.9 009-2016008485 15-SM-008-07020
104 3 7 2 60 61.9 009-2016008486 15-SM-008-07021
105 3 8 2 82 96.66 009-2016008487 15-SM-008-07022
106 5 9 2 68 61.9 009-2016008524 15-SM-008-06952
107 5 7 2 83 83.89 009-2016008522 15-SM-008-06953
108 5 6 2 82 83.89 009-2016008521 15-SM-008-06954
109 5 5 2 82 83.89 009-2016008520 15-SM-008-06955
110 5 4 2 82 83.89 009-2016008519 15-SM-008-06956
111 5 3 2 83 83.89 009-2016008518 15-SM-008-06957
112 5 2 2 68 61.9 009-2016008517 15-SM-008-06959
113 5 1 2 68 61.9 009-2016008516 15-SM-008-06958
114 5 8 2 68 61.9 009-2016008523 15-SM-008-06951
115 6 9 3 82 96.66 009-2016008533 15-SM-008-06949
116 6 10 3 60 61.9 009-2016008534 15-SM-008-06948
117 6 11 3 60 61.9 009-2016008535 15-SM-008-06947
118 6 12 3 60 61.9 009-2016008536 15-SM-008-06946
119 6 13 3 60 61.9 009-2016008537 15-SM-008-06945
120 6 14 3 60 61.9 009-2016008538 15-SM-008-06944
Unit Blk. Lot No. Phase Lot Floor Title No. Tax Dec. No.
No. Area Area
Land Bldg.

121 6 15 3 60 61.9 009-2016008539 15-SM-008-06943


122 6 16 3 60 61.9 009-2016008540 15-SM-008-06942
123 6 1 3 60 61.9 009-2016008525 15-SM-008-06941
124 6 2 3 60 61.9 009-2016008526 15-SM-008-06940
125 6 3 3 60 61.9 009-2016008527 15-SM-008-06939
126 6 4 3 60 61.9 009-2016008528 15-SM-008-06938
127 6 5 3 60 61.9 009-2016008529 15-SM-008-06937
128 6 6 3 60 61.9 009-2016008530 15-SM-008-06936
129 6 7 3 60 61.9 009-2016008531 15-SM-008-06935
130 6 8 3 82 96.66 009-2016008532 15-SM-008-06934
Unit Blk. Lot No. Phase Lot Floor Title No. Tax Dec. No.
No. Area Area
Land Bldg.

OS 1 18 1 672 009-2016008457 15-SM-008-06988


RL1 Lot 1 (8.00 m. wide) 689 009-2016008571 15-SM-008-07023
RL2 Lot 2 (6.50 m. wide) 341 009-2016008572 15-SM-008-07024
RL3 Lot 3 (6.50 m. wide) 326 009-2016008573 15-SM-008-06989
RL4 Lot 4 (6.50 m. wide) 326 009-2016008574 15-SM-008-07006
RL5 Lot 5 (6.50 m. wide) 439 009-2016008575 15-SM-008-06981
RL6 Lot 6 (6.50 m. wide) 328 009-2016008576 15-SM-008-06932
RL7 Lot 7 (6.50 m. wide) 326 009-2016008577 15-SM-008-06950
RL8 Lot 8 (6.50 m. wide) 386 009-2016008578 15-SM-008-06933
RL9 Lot 9 (6.50 m. wide) 266 009-2016008579 15-SM-008-06960
Market Value Real Property Tax
Land Bldg. Land OR # Bldg. OR #

208,000.00 665.60 1151909


208,000.00 665.60 1151908
208,000.00 665.60 1151907
208,000.00 665.60 1151906
208,000.00 665.60 1151904
208,000.00 665.60 1151903
208,000.00 665.60 1151902
208,000.00 665.60 1151901
301,600.00 965.12 1151800
260,000.00 832.00 1151367
208,000.00 665.60 1151366
208,000.00 665.60 1151365
208,000.00 665.60 1151364
208,000.00 665.60 1151363
208,000.00 665.60 1151362
208,000.00 665.60 1151361
208,000.00 665.60 1151360
208,000.00 665.60 1151359
210,600.00 673.92 1151358
156,000.00 499.20 1151792
156,000.00 499.20 1151793
156,000.00 499.20 1151794
156,000.00 499.20 1151795
156,000.00 499.20 1151796
156,000.00 499.20 1151797
156,000.00 499.20 1151798
286,000.00 915.20 1151799
257,400.00 823.68 1151368
156,000.00 499.20 1151369
156,000.00 499.20 1151370
Market Value Real Property Tax
Land Bldg. Land OR # Bldg. OR #

156,000.00 499.20 1151371


156,000.00 499.20 1151372
156,000.00 499.20 1151373
156,000.00 499.20 1151374
156,000.00 499.20 1151375
262,600.00 840.32 1151357
171,600.00 549.12 1151356
158,600.00 507.52 1151355
163,800.00 524.16 1151354
166,400.00 532.48 1151353
169,000.00 540.80 1151352
174,200.00 557.44 1151351
176,800.00 565.76 1151100
182,000.00 582.40 1151099
184,600.00 590.72 1151098
189,800.00 607.36 1151097
304,200.00 973.44 1151096
171,600.00 549.12 1151412
161,200.00 515.84 1151413
163,800.00 524.16 1151414
166,400.00 532.48 1151415
169,000.00 540.80 1151416
171,600.00 549.12 1151417
174,200.00 557.44 1151418
176,800.00 565.76 1151419
179,400.00 574.08 1151420
182,000.00 582.40 1151421
187,200.00 599.04 1151422
189,800.00 607.36 1151423
192,400.00 615.08 1151424
Market Value Real Property Tax
Land Bldg. Land OR # Bldg. OR #

195,000.00 624.00 1151425


197,600.00 632.32 1151426
200,200.00 640.64 1151427
208,000.00 665.60 1151428
231,400.00 740.48 1151429
223,600.00 715.52 1151430
369,200.00 1,181.44 1151431
218,400.00 698.88 1151433
169,000.00 540.80 1151434
185,900.00 567,700.00 594.88 1151435 2,270.88 1151910
166,400.00 532.48 1151436
166,400.00 532.48 1151439
166,400.00 567,700.00 532.48 1151440 2,270.88 1151911
234,520.00 863,130.00 750.40 1151443 4,143.04 1151912
156,000.00 499.20 1151444
156,000.00 567,700.00 499.20 1151445 2,270.88 1151913
156,000.00 499.20 1151446
156,000.00 499.20 1151447
156,000.00 499.20 1151448
156,000.00 499.20 1151449
171,600.00 549.12 1151751
171,600.00 549.12 1151450
156,000.00 499.20 1151752
156,000.00 499.20 1151753
156,000.00 499.20 1151754
156,000.00 499.20 1151755
156,000.00 567,700.00 499.20 1151756 2,270.88 1151914
156,000.00 567,700.00 499.20 1151764 2,270.88 1151915
234,520.00 863,130.00 750.40 1151765 4,143.04 1151916
234,520.00 750.40 1151769
Market Value Real Property Tax
Land Bldg. Land OR # Bldg. OR #

156,000.00 499.20 1151770


156,000.00 499.20 1151771
156,000.00 499.20 1151772
156,000.00 499.20 1151773
156,000.00 499.20 1151774
156,000.00 499.20 1151775
171,600.00 549.12 1151776
171,600.00 549.12 1151777
156,000.00 499.20 1151778
156,000.00 499.20 1151779
156,000.00 499.20 1151780
156,000.00 499.20 1151781
156,000.00 499.20 1151786
156,000.00 499.20 1151787
234,520.00 750.40 1151788
194,480.00 622.40 1151400
215,800.00 690.56 1151404
213,200.00 682.24 1151405
213,200.00 682.24 1151406
213,200.00 682.24 1151407
215,800.00 690.56 1151408
194,480.00 622.40 1151410
194,480.00 622.40 1151409
194,480.00 622.40 1151399
234,520.00 750.40 1151397
156,000.00 499.20 1151396
156,000.00 499.20 1151395
156,000.00 499.20 1151394
156,000.00 499.20 1151393
156,000.00 499.20 1151392
Market Value Real Property Tax
Land Bldg. Land OR # Bldg. OR #

156,000.00 499.20 1151391


171,600.00 549.12 1151389
171,600.00 549.12 1151388
156,000.00 499.20 1151387
156,000.00 499.20 1151386
156,000.00 499.20 1151385
156,000.00 499.20 1151384
156,000.00 499.20 1151383
156,000.00 499.20 1151382
234,520.00 750.40 1151380
Market Value Real Property Tax
Land Bldg. Land Bldg. OR #

524,160.00 1,677.28 1151441


165,360.00 529.12 1151790
81,840.00 261.92 1151791
78,240.00 250.40 1151442
78,240.00 250.40 1151766
386,320.00 337.12 1151432
78,720.00 251.84 1151376
78,240.00 250.40 1151398
92,640.00 296.48 1151377
63,840.00 204.32 1151411
Unit Blk. Lot No. Phase Lot Floor TOILET & BED CAR Contract Date Started
No. Area Area BATH ROOMS GARAGE Price
1 1 17 1 80 66 2 3 2 3,060,000 Nov-16
2 1 16 1 80 66 2 3 2 3,037,500
3 1 15 1 80 66 2 3 2 3,037,500
4 1 14 1 80 66 2 3 2 3,037,500
5 1 13 1 80 66 2 3 2 3,037,500 20-Jul-17
6 1 12 1 80 66 2 3 2 3,037,500 May 25, 2017
7 1 11 1 80 66 2 3 2 3,037,500
8 1 10 1 80 66 2 3 2 3,037,500 May 17, 2017
9 1 9 1 116 137 2 3 2 4,083,750 Nov-16
10 8 19 2 100 82.8 2 3 2 3,521,250
11 8 18 2 80 66 2 3 2 3,037,500
12 8 17 2 80 66 2 3 2 3,037,500 May 17, 2017
13 8 16 2 80 66 2 3 2 3,037,500
14 8 15 2 80 66 2 3 2 3,037,500 May 05, 2017
15 8 14 2 80 66 2 3 2 3,037,500
16 8 13 2 80 66 2 3 2 3,037,500
17 8 12 2 80 66 2 3 2 3,037,500 April 27, 2017
18 8 11 2 80 66 2 3 2 3,037,500 April 27, 2017
19 8 10 2 81 70.44 2 3 2 3,172,500 April 27, 2017
20 1 1 1 60 61.9 2 3 1 2,626,875 Nov-16
21 1 2 1 60 61.9 2 3 1 2,626,875 Janary 2017
22 1 3 1 60 61.9 2 3 1 2,626,875
23 1 4 1 60 61.9 2 3 1 2,626,875
24 1 5 1 60 61.9 2 3 1 2,626,875
25 1 6 1 60 61.9 2 3 1 2,626,875 Jun-17
26 1 7 1 60 61.9 2 3 1 2,626,875 Nov-16
27 1 8 1 100 97.68 2 3 3 4,246,875 Aug-16
28 8 1 2 90 97.68 2 3 2 4,117,500
29 8 2 2 60 61.9 2 3 1 2,626,875
30 8 3 2 60 61.9 2 3 1 2,626,875
31 8 4 2 60 61.9 2 3 1 2,626,875
32 8 5 2 60 61.9 2 3 1 2,626,875
33 8 6 2 60 61.9 2 3 1 2,626,875
34 8 7 2 60 61.9 2 3 1 2,626,875
35 8 8 2 60 61.9 2 3 1 2,497,500
36 8 9 2 101 61.9 2 3 3 3,048,750 Oct-16
37 7 11 3 60 61.9 2 3 1 2,643,750
38 7 10 3 61 61.9 2 3 1 2,649,375
39 7 9 3 63 61.9 2 3 1 2,666,250
40 7 8 3 64 61.9 2 3 1 2,688,750
41 7 7 3 65 61.9 2 3 1 2,705,625
42 7 6 3 67 61.9 2 3 1 2,722,500
43 7 5 3 68 61.9 2 3 1 2,739,375
44 7 4 3 70 61.9 2 3 1 2,756,250
45 7 3 3 71 61.9 2 3 1 2,773,125
46 7 2 3 73 61.9 2 3 1 2,795,625
47 7 1 3 117 61.9 2 3 3 3,346,875
48 4 20 3 60 61.9 2 3 1 2,643,750
49 4 19 3 62 61.9 2 3 1 2,643,750 Jun-17
50 4 18 3 63 61.9 2 3 1 2,660,625
51 4 17 3 64 61.9 2 3 1 2,671,875
52 4 16 3 65 61.9 2 3 1 2,683,125
53 4 15 2 66 61.9 2 3 1 2,700,000
54 4 14 2 67 61.9 2 3 1 2,711,250
55 4 13 2 68 61.9 2 3 1 2,728,125
56 4 12 2 69 61.9 2 3 1 2,739,375
57 4 11 2 70 61.9 2 3 1 2,756,250 Jun-17
58 4 10 2 72 61.9 2 3 1 2,767,500
59 4 9 2 73 61.9 2 3 1 2,778,750 Jun-17
60 4 8 2 74 61.9 2 3 1 2,795,625
61 4 7 2 75 61.9 2 3 1 2,806,875
62 4 6 2 76 61.9 2 3 1 2,823,750
63 4 5 2 77 61.9 2 3 1 2,835,000 Jun-17
64 4 4 1 80 61.9 2 3 1 2,880,000 Jun-17
65 4 3 1 89 61.9 2 3 1 2,986,875
66 4 2 1 86 61.9 2 3 1 2,947,500
67 4 1 1 142 74.5 2 3 3 3,588,750
68 1 19 1 84 61.9 2 3 1 2,812,500
69 1 20 1 65 61.9 2 3 1 2,559,375
70 1 21 1 65 60.94 2 3 1 2,638,125 Sept.2016
71 1 22 1 64 61.9 2 3 1 2,728,125
72 1 23 1 64 61.9 2 3 1 2,728,125
73 1 24 1 64 60.94 2 3 1 2,728,125 Sept.2016
74 2 9 1 82 91.65 2 3 1 3,965,625 Jun-16
75 2 10 1 60 61.9 2 3 1 2,626,875 Aug.2016
76 2 11 1 60 60.94 2 3 1 2,626,875 Jul-16
77 2 12 1 60 61.9 2 3 1 2,626,875 Jun-17
78 2 13 1 60 61.9 2 3 1 2,626,875 Jun-17
79 2 14 1 60 61.9 2 3 1 2,626,875 Jul-17
80 2 15 1 60 61.9 2 3 1 2,497,500
81 2 16 1 60 61.9 2 3 1 2,565,000
82 2 1 1 60 61.9 2 3 1 2,565,000 May-17
83 2 2 1 60 61.9 2 3 1 2,497,500 May-17
84 2 3 1 60 61.9 2 3 1 2,626,875 Mar-17
85 2 4 1 60 61.9 2 3 1 2,626,875 Jul-17
86 2 5 1 60 61.9 2 3 1 2,626,875 Sept.2016
87 2 6 1 60 60.94 2 3 1 2,626,875 Aug.2016
88 2 7 1 60 60.94 2 3 1 2,626,875 Aug.2016
89 2 8 1 82 91.65 2 3 1 3,965,625 Jun-16
90 3 9 1 82 96.66 2 3 1 3,965,625 Dec.2016
91 3 10 1 60 61.9 2 3 1 2,626,875
92 3 11 1 60 61.9 2 3 1 2,626,875 Jul-17
93 3 12 1 60 61.9 2 3 1 2,626,875
94 3 13 1 60 61.9 2 3 1 2,626,875 May-17
95 3 14 1 60 61.9 2 3 1 2,626,875
96 3 15 1 60 61.9 2 3 1 2,497,500
97 3 16 1 60 61.9 2 3 1 2,565,000 Feb.2017
98 3 1 2 60 61.9 2 3 1 2,565,000
99 3 2 2 60 61.9 2 3 1 2,497,500
100 3 3 2 60 61.9 2 3 1 2,649,375 Mar-17
101 3 4 2 60 61.9 2 3 1 2,649,375
102 3 5 2 60 61.9 2 3 1 2,649,375
103 3 6 2 60 61.9 2 3 1 2,649,375
104 3 7 2 60 61.9 2 3 1 2,649,375 Apr-17
105 3 8 2 82 96.66 2 3 1 3,965,625
106 5 9 2 68 61.9 2 3 1 2,621,250
107 5 7 2 83 83.89 2 3 2 3,583,125
108 5 6 2 82 83.89 2 3 2 3,594,375
109 5 5 2 82 83.89 2 3 2 3,594,375
110 5 4 2 82 83.89 2 3 2 3,594,375
111 5 3 2 83 83.89 2 3 2 3,583,125
112 5 2 2 68 61.9 2 3 1 2,621,250
113 5 1 2 68 61.9 2 3 1 2,615,625
114 5 8 2 68 61.9 2 3 1 2,615,625
115 6 9 3 82 96.66 2 3 1 3,965,625
116 6 10 3 60 61.9 2 3 1 2,626,875
117 6 11 3 60 61.9 2 3 1 2,626,875
118 6 12 3 60 61.9 2 3 1 2,626,875
119 6 13 3 60 61.9 2 3 1 2,626,875
120 6 14 3 60 61.9 2 3 1 2,626,875
121 6 15 3 60 61.9 2 3 1 2,497,500
122 6 16 3 60 61.9 2 3 1 2,565,000
123 6 1 3 60 61.9 2 3 1 2,565,000
124 6 2 3 60 61.9 2 3 1 2,497,500
125 6 3 3 60 61.9 2 3 1 2,626,875
126 6 4 3 60 61.9 2 3 1 2,626,875
127 6 5 3 60 61.9 2 3 1 2,626,875
128 6 6 3 60 61.9 2 3 1 2,626,875
129 6 7 3 60 61.9 2 3 1 2,626,875
130 6 8 3 82 96.66 2 3 1 3,965,625
Date Completed Remarks

Feb-17 Full DP no turnover yet


DP still amortize
DP still amortize
DP still amortize
Cash
Aug-17 DP still amortize on-going
DP still amortize
Aug-17 DP still amortize on-going
Feb-17 Cash turnover already
DP still amortize
DP still amortize
Aug-17 DP still amortize on-going
DP still amortize
Aug-17 DP still amortize on-going
DP still amortize
DP still amortize
Aug-17 DP still amortize on-going
Aug-17 DP still amortize on-going
Aug-17 Full DP on-going
Feb-17 Fully Paid turnover already
Apr-17 Fully Paid turnover already
DP still amortize
DP still amortize
DP still amortize
DP still amortize On-going/stop
Feb-17 Fully Paid turnover already
DP still amortize On-going/stop
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
Jan-17 Cash turnover already
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
RESERVED
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
Sep-17 DP still amortize on-going
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize On-going/stop
DP still amortize
DP still amortize On-going/stop
DP still amortize
DP still amortize
DP still amortize
DP still amortize On-going/stop
DP still amortize On-going/stop
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
Dec.2016 Full DP turnover already
DP still amortize
DP still amortize
Dec.2016 DP still amortize turnover already
Aug-16 Full DP turnover already
Nov-16 Full DP turnover already
Oct-16 Fully Paid turnover already
Sep-17 DP still amortize on-going
Sep-17 DP still amortize on-going
Sep-17 DP still amortize on-going
DP still amortize
DP still amortize
Aug-17 Full DP on-going
Aug-17 DP still amortize on-going
Jun-17 Full DP no turnover yet
DP still amortize On-going/stop
Dec.2016 Full DP turnover already
Nov-16 DP still amortize turnover already
Nov-16 Full DP no turnover yet
Aug-16 Fully Paid turnover already
Feb.2017 Fully Paid turnover already
DP still amortize
Sep-17 DP still amortize on-going
DP still amortize
Aug-17 DP still amortize on-going
DP still amortize
DP still amortize
May-17 Cash turnover already
DP still amortize
DP still amortize
Jun-17 Full DP no turnover yet
DP still amortize
DP still amortize
DP still amortize
Jul-17 Full DP On-going
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
DP still amortize
UNIT Name of Client L CONTRACT BANK LOAN Bank Start of
O PRICE 90% Approval Status Target Finish
Construction
T
1 David John Tampes ### 2,720,000 2,448,000 2,448,000 Approved w/ PNB FINISH FINISH
2 Ophalyn Ramos A 2,700,000
### 2,430,000
3 Ronalyn Ramos R 2,700,000
### 2,430,000 awaiting for Approval
E
4 Sps. Edison and Joyce Lalaine Castillejo ###
A 2,700,000 2,430,000
5 Joseph Gomez ### 2,700,000 2,430,000 CASH Sept.11,2017 Dec.6,2017
6 Sps. Carlo & Sarah Jane Coralde ( 2,700,000
### 2,430,000 2,430,000 Approved w/ PNB October 30,2017
S
7 Sps. Michael & Tessie Uydiangco ### 2,700,000 2,430,000 2,430,000 Approved w/ PNB
Q
8 Sps. Maybelle & Julius Caesar Duque ###
. 2,700,000 2,430,000 2,430,000 Approved w/ PNB
9 Joeliza Dela Cruz M 3,630,000
### 3,267,000 CASH FINISH FINISH
Rodolfo Vallestero .
10 ### 3,130,000 2,817,000
)
11 Sps. Teofilo & Helen Calejesan ### 2,700,000 2,430,000 2,430,000 Approved w/ SB & CB
12 Sps. Elmer and Zenaida SO ### 2,700,000 2,430,000 awaiting for Approval
13 Angela Roble ### 2,700,000 2,430,000 awaiting for Approval
14 Mark Agustin Dalimocon ### 2,700,000 2,430,000 2,430,000 Approved w/ MB
15 Noel Noble ### 2,700,000 2,430,000
16 Sps. Christopher & Lara Manalang ### 2,700,000 2,430,000 awaiting for Approval
17 Arbelle Dumayag ### 2,700,000 2,430,000 2,430,000 Approval w/ MB
18 Sps. Rodny & Aileen Malenab ### 2,700,000 2,430,000
19 Sps. Jayson & Catherine Pondevida ### 2,820,000 2,538,000 1,820,000 Approved w/ MB
20 Welmer Marasigan ### 2,335,000 2,101,500 2,101,500 Loan Release PNB FINISH FINISH
21 Rameel Niño Manalo ### 2,335,000 2,101,500 2,101,500 Loan Release PNB FINISH FINISH
22 Khristian Fel Montañez ### 2,335,000 2,101,500 2,101,500 Approved w/ PNB
23 Sps. Francis & Mary Jane Telan ### 2,335,000 2,101,500
24 Rolando Nitura ### 2,335,000 2,101,500 2,101,500 Approved w/ PNB
25 Jenny Rose Abaygar ### 2,335,000 2,101,500 2,101,500 Approved w/ RCBC
26 Vilma Gomez ### 2,335,000 2,101,500 2,101,500 Loan release PNB FINISH FINISH
27 Joy Cruz Florez ### 3,775,000 3,397,500 PAGIBIG
28 Vincent Jeck De Belen ### 3,660,000 3,294,000
29 Arnold Iringco ### 2,335,000 2,101,500 PAGIBIG
30 Haily Aplacador ### 2,335,000 2,101,500 2,101,500 Approved w/ PNB
31 Sps. Ana Wincel & George Obed ### 2,335,000 2,101,500 2,101,500 Approved SB,PNB,RCBC
32 Sps. Constantino & Jovelita Dato ### 2,335,000 2,101,500
33 Dexter Fernandez ### 2,335,000 2,101,500 2,101,500 Approved SB & PNB
34 Rodolf Amn Guerrero ### 2,335,000 2,101,500 2,101,500 Approved SB
35 Marwin De Lima ### 2,335,000 2,101,500
36 Marie Cris Dela Cruz ### 2,710,000 2,439,000 CASH FINISH FINISH
37 Jeffrey Macaraeg ### 2,350,000 2,115,000 2,115,000 Approved PNB
38 Joeffrey Jara ### 2,355,000 2,119,500 2,119,500 Approved PNB
39 Sps. Leonito & Leahmor Dolorito ### 2,370,000 2,133,000 PAGIBIG
40 Sps. David & Perla James ### 2,390,000 2,151,000 2,151,000 Approved PNB
41 Sps. Jayson & Amor Ollero ### 2,405,000 2,164,500 awaiting for Approval
42 Sps. Khristoffer & Rheychelle Tugaon ### 2,420,000 2,178,000 2,178,000 Approved PNB
43 Ma. Anita Gajo ### 2,435,000 2,191,500 2,191,500 Approved SB, PNB & RCBC
44 Gina Laroco & Marlon De Luna ### 2,450,000 2,205,000 2,205,000 Approved PNB
45 Sps. Arpee Ruth Jao ### 2,465,000 2,218,500
46 Joselito Garchitorena ### 2,485,000 2,236,500
47 Sps. Monaliza & Nelson Angeles ### 2,975,000 2,677,500 PagIBIg
48 Jose Carlo Barcelona ### 2,350,000 2,115,000 1,880,000 Approved PNB
49 Sps. Dennis & Mary Grace Mosquera ### 2,350,000 2,115,000 2,115,000 Approved PNB, CB, RCBC,SB
50 Glenn Guillera ### 2,365,000 2,128,500 2,128,500 Approved PNB & MB
51 Sps. Jasmin & Ariston Asilo ### 2,375,000 2,137,500 awaiting for Approval
52 Maria Cecilia Manzano ### 2,385,000 2,146,500
53 Sps. Marietta & Simeon Romero ### 2,400,000 2,160,000 Approved PNB
54 Maria Blesa Beso ### 2,410,000 2,169,000 PAGIBIG
55 Aris Joesph Ginete ### 2,425,000 2,182,500
56 Karen Joven ### 2,435,000 2,191,500
57 Melissa Manuel ### 2,450,000 2,205,000 awaiting for Approval
58 Ma. Angelica Erlano ### 2,460,000 2,214,000 1,000,000 Approved CB
59 Sps. Alexander Cloudualdo & Miriam Cecilia Sales
### 2,470,000 2,223,000 2,223,000 Approved CB
60 Raniel Mendoza ### 2,485,000 2,236,500 Approved SB -Katipunan
61 Irma Mae Salvador ### 2,495,000 2,245,500 2,245,500 Approved PNB
62 Analyn Cenar ### 2,510,000 2,259,000 2,000,000 Approved PNB
63 Loreto Gapas ### 2,520,000 2,268,000 2,268,000 Approved PNB
64 Sps. Jelie & Ronel Barceta ### 2,560,000 2,304,000 1,767,864 Approved SB (ff in increase approval)
65 Ryan Saul Dukinal ### 2,655,000 2,389,500
66 Sps. Aileen & Rolando Villaroman ### 2,620,000 2,358,000 2,358,000 Approved PNB
67 Sps. Joan & Noel Santos ### 3,910,000 3,519,000 3,519,000 Approved SB
68 Sps. Rhomnick Coloma ### 2,500,000 2,250,000 2,250,000 Approved SB
69 Evelyn Cruz ### 2,275,000 2,047,500
70 Sps. Liberato & Miriam Samala ### 2,345,000 2,110,500 1,790,000 PAGIBIG FINISH FINISH
71 Louie Bustamante ### 2,425,000 2,182,500 2,182,500 Approved PNB
72 Sps. Lemuel & Ma Christina Rica Ronamo ### 2,425,000 2,182,500 2,182,500 Approved PNB
73 Sps. Cathrina & Francis Ugay ### 2,425,000 2,182,500 2,180,100 Loan Release SB FINISH FINISH
74 Sps. Rowena & Ricky Pospos ### 3,525,000 3,172,500 2,280,000 awaiting for release PNB FINISH FINISH
75 Sps.Jose & Lorna Cardenas ### 2,335,000 2,101,500 2,101,500 Loan Release SB FINISH FINISH
76 Marius Daniel Lumapas ### 2,335,000 2,101,500 2,101,500 Loan Release SB FINISH FINISH
77 SPS. Emilson John Manalang ### 2,335,000 2,101,500 2,101,500 Approved w/ PNB
78 Sps. Gambie Estuesta ### 2,335,000 2,101,500 2,101,500

79 Florebelle Dayata ### 2,335,000 2,101,500 2,101,500 Approved SB & MB


80 Zerhom Ventura ### 2,220,000 1,998,000
81 Sps. Lily Beth & Ronan Fabre ### 2,280,000 2,052,000 awaiting for Approval
82 Sps. Ronald & Haydeelyn Casuyon ### 2,280,000 2,052,000 2,052,000 Approved PNB (Awaiting for the transferred TCT)
83 Sps. Glyn & Sherna Faith Cleofe Crisostomo ### 2,220,000 1,998,000 1,998,000 Approved SB (Awaiting for the transferred TCT)
84 Cathrina Babon ### 2,335,000 2,101,500 2,101,500 awaiting for Loan Release PNB FINISH FINISH
85 Roberto Marcelo ### 2,335,000 2,101,500 PAGIBIG
86 Sps. Josef Paul & Jamila Rose Dato-On ### 2,335,000 2,101,500 2,101,500 Loan Release (PNB) FINISH FINISH
87 Shayne Bernardo ### 2,335,000 2,101,500 2,101,500 Loan release CB FINISH FINISH
88 Sps. Jan Gabriel & Psyche Pondevida ### 2,335,000 2,101,500 2,101,500 awaiting for Loan Release PNB FINISH FINISH
89 Sps. Melvin & Elizabeth Umoquit ### 3,525,000 3,172,500 3,172,500 Loan Release PNB FINISH FINISH
90 Florebelle Dayata ### 3,525,000 3,172,500 3,172,500 Loan Release MB FINISH FINISH
91 Sps. Cherry & Jimmy Ancheta ### 2,335,000 2,101,500 1,700,000 Approved RCBC
92 Sps. Llubel Angeli & Rowell Saludes ### 2,335,000 2,101,500 2,101,500 Approved SB
93 Juler Andaleon ### 2,335,000 2,101,500 PAGIBIG
94 Micheal Ian Briñez ### 2,335,000 2,101,500 2,101,500 Approved w/ SB FINISH FINISH
95 Bernadette Hernando ### 2,335,000 2,101,500 2,101,500 Approved PNB
96 Sps. Angelo Faustino ### 2,220,000 1,998,000 1,998,000 Approved RCBC
97 Vincent Christopher Trinidad ### 2,800,000 2,520,000 CASH FINISH FINISH
98 Lomen Puso ### 2,280,000 2,052,000
99 Sps. Linus & Maricon King ### 2,220,000 1,998,000 Approved CB
100 Efigen Villariña ### 2,355,000 2,119,500 2,119,500 Loan Release MB FINISH FINISH
101 Sherwin Gerald Rupa ### 2,355,000 2,119,500 2,119,500 Approved RCBC
102 Gleriza Merilos ### 2,355,000 2,119,500
103 Marinel Alapitan ### 2,355,000 2,119,500 2,119,500 Approved SB & PNB
104 John Kenneth Titco ### 2,355,000 2,119,500 2,101,500 Loan Release FINISH FINISH
105 Sps. Rowena Florez ### 3,525,000 3,172,500
106 Elsa Liezel Onita ### 2,330,000 2,097,000
107 Pedro Aquino ### 3,185,000 2,866,500 Approved SB (increase in approval)
108 Sps. Riza & Reynaldo Rivo ### 3,195,000 2,875,500 Approved SB
109 Sps. Prescila & Reynaldo Vano ### 3,195,000 2,875,500 2,875,000 Approved PN & MB
110 Sps. Khristine & Roger Vano ### 3,195,000 2,875,500 2,875,000 Approved PNB & RCBC
111 ### 3,185,000 2,866,500
112 Kris Wyrol Jez & Marivev Astrologo ### 2,330,000 2,097,000 2,097,000 Approved PNB
113 Joanne Sapao ### 2,325,000 2,092,500 2,092,500 Approved SB,PNB
114 Erika Elise Meneza ### 2,325,000 2,092,500
115 Sps. Jose Carido ### 3,525,000 3,172,500 PAGIBIG
116 Denner Corrales ### 2,335,000 2,101,500
117 Sps. Jiecel & Benito Padernal ### 2,335,000 2,101,500 awaiting for bank approval
118 Benedict Bacud ### 2,335,000 2,101,500
119 Sps. Franklin & Maria Fe Abella ### 2,335,000 2,101,500 2,101,500 Approved PNB
120 Rachel Brendia ### 2,335,000 2,101,500 2,101,500 Approved RCBC
121 Mary Ferlyn Santos ### 2,220,000 1,998,000
122 Nino Piatos ### 2,280,000 2,052,000
123 Jose Carrido ### 2,280,000 2,052,000 PAGIBIG
124 Sps. Rofelyn Bolesa & Cleofas Bolesa ### 2,220,000 1,998,000 1,998,000 Approved PNB SB
125 Sps. Medina Ramos ### 2,335,000 2,101,500 2,101,500 Approved SB
126 Fredrick Villamor ### 2,335,000 2,101,500 1,435,000 Approved MB PNB
127 Tomas Ramiro & Osmalyn Ramos ### 2,335,000 2,101,500 2,101,500 Approved SB
128 Camille Victoria Lorenzo ### 2,335,000 2,101,500
129 Alvin Fernandez Dela Cruz ### 2,335,000 2,101,500 2,101,500 Approved SB
130 Charlene Aurellado ### 3,525,000 3,172,500
CRYSTAL HOMES - ABUAB 2 HOUSE CONSTRUCTION SCHEDULE

LAYOUT FORMWORKS FINISHING : MASONRY FINISHING : PAINTING WORKS


Item UNIT Finish Date of Date of Date of Date of Foreman / Date of Date of STATUS
GROUP GROUP GROUP
# Date Start Finish Start Finish Leadman Start Finish
1 82 Sept.20,2017 Oct. 20,2017 Esok Oct.1,2017 Oct.30,2017 Alegre FINISH
2 92 Sept.1,2017 Sep.30 Jessie Sept.15,2017 Oct.15,2017 Alwyn FINISH
3 6 Oct.7,2017 Panoy Sept.19,2017 Oct.19,2017 Eric FINISH
4 14 Airnad Oct.9,2017 Nov.24,2017 FINISH
5 12 Airnad Oct.9,2017 Dec.7,2017
6 8 Airnad Oct.9,2017 Dec.7,2017
7 49 Oct.9,2017 Nov.9,2017 Jessie Oct16,2017 Nov.16,2017 Alwyn FINISH
8 79 Aug.12,2017 Sept.12,2017 Delio Oct.16,2017 Nov.16,2017 Panoy Nov.2,2017 Nov.30,2017 Eric FINISH
9 77 Sept.1,2017 Sept.30,2017 Lanuza Oct.18,2017 Nov.18,2017 Esok Nov.2,2017 Nov.30,2017 Alegre FINISH
10 85 Sept.15,2017 Oct.14,2017 Delio Nov.10,2017 Dec.10,2017 Jessie Nov.15,2017 Dec.15,2017 Alwyn FINISH
11 5 Airnad Sept.11,2017 Dec.8,2017
12 63 Finones Oct.10,2017 Jan.9,2018
13 64 stop const.
14 25 Romy Oct.9,2017 Nov.9,2017 Lanuza Nov.15,2017 Dec.15,2017 Esok Dec1,2017 Dec.30,2017 Eric FINISH
15 22 Romy Oct.19,2017 Jan.10,2018 Jessie Jan.5,2018 Jan.30,2018 Alwyn
16 30 18-Mar Crystalville Oct.10,2017
17 31 Crystalville Oct.10,2017
18 33 Crystalville
19 71 Bigboy Oct.24,2017
20 72 18-Mar Bigboy Oct.24,2017
21 105 18-Jan Delio Oct.18,2017 Dec.30,2017 Delio Jan.2,2018 Jan.30,2018 Eric
22 57 Finones Sept.25,2017 Dec.22,2017
23 59 Finones Sept.19,2017 Dec.16,2017
24 7 Airnad Sept.29,2017 Dec.28,2017
25 99 Romy Nov.10,2017 Jan.15,2018 Esok Jan.22,2018 Feb.28,2018 Eric
26 24 Romy Nov.20,2017 Jan.30,2018 Jessie Feb.28,2018
27 101 Romy Dec.11,2017 Feb.15,2018 Esok Mar.15,2018
28 27 18-Mar Panoy Dec.18,2017 Jan.30,2018 Panoy Jan.29,2018 Feb.28,2018 Alegre
29 50 18-Feb Finones
30 67 18-Feb Romy Dec.20,2017 Jan.30,2018 Mogan Feb.2018
31 68 18-Feb ESOK/ROMY Dec.20,2017 Jan.30,2018 Delio Feb.2018 Alwyn
32 125 18-Apr Romy Jan.21,2018 Mar.30,2018 Jessie April,30,2018
33 81 18-Apr Romy Jan.21,2018 Mar.30,2018 Mogan April,30,2018
34 113 18-Feb Finones

LAYOUT FORMWORKS FINISHING : MASONRY FINISHING : PAINTING WORKS


Item UNIT Finish Date of Date of Date of Date of Foreman / Date of Date of STATUS
GROUP GROUP GROUP
# Date Start Finish Start Finish Leadman Start Finish
35 62 18-Mar Romy Feb.28,2018 Panoy Mar.30,2018
36 96 18-Mar Romy Feb.28,2018 Jessie Mar.30,2018
37 91 18-Mar Romy Feb.28,2018 Mogan Mar.30,2018
38 48 18-Mar Romy Feb.28,2018 Delio Mar.30,2018
39 66 18-Apr Romy Mar.30,2018 Esok April,30,2018
40 95 18-Apr Romy Mar.30,2018 Panoy April,30,2018
LAYOUT FORMWORKS FINISHING : MASONRY FINISHING : PAINTING WORKS
Sked as Date of Date of Date of Date of Foreman / Date of Date of STATUS
UNIT # GROUP GROUP GROUP
per Jazz Start Finish Start Finish Leadman Start Finish
Apr-17
May-17
Mar-17
Apr-17
May-17
Apr-17
Mar-17
May-17
May-17
Apr-17
Jul-17
Apr-17
Apr-17
May-17

May-17

May-17
May-17
May-17
Jun-17
Jun-17

Jul-17
CONSTRUCTION SCHEDULE JANUARY 2018 - DECEMEBER 2018
MONTH: LAYOUT-COLUMN/FOOTING FORMWORKS FINISHING : MASONRY FINISHING : PAINTING WORKS
Item Proposed Unit Date of Date of Date of Date of Foreman / Date of Date of STATUS
GROUP STATUS GROUP GROUP
Start # Start Finish Start Finish Leadman Start Finish
JANUARY
1.0 105 Delio Jan.30,2018
2.0 22 Jessie Jan.30,2018
3.0 5 Jan.2,2018 Jessie Jan.30,2018
4.0 59 Jan.2018
5.0 12 Jan.2,2018 Esok Jan.23,2018
6.0 99 Lanuza Feb.15,2018 Esok Feb.2018
7.0 71 SUBCON-BIGBOY
Feb.2018
8.0 72 SUBCON-BIGBOY
9.0 63 SUBCON-FICS Feb.2018
10.0 50 Feb.2018
11.0 57 SUBCON-FICS Feb.2018
12.0 113 Mar.30,2018
13.0 30
14.0 31 SUBCON-AAJ Feb.2018
15.0 33
16.0 7 Jan.2,2018 Delio Feb-18
17.0 8 Jan.2,2018 Delio Feb-18
18.0 27 Feb.15,2018 Panoy Feb.2018
19.0 67 Feb.28,2018 Mogan Mar.30,2018
20.0 24 Jan.8,2018 Feb.8,2015 Gandia Mar.15,2018 Esok Mar.30,2018
21.0 101 Jan.15,2018 Feb.15,2018 Lanuza Mar.15,2018 Panoy April 15,2018
22.0 68 Feb.1,2018 Mar.30,2018 Jessie April 15,2018
23.0 96 Feb.8,2015 Mar.8,2018 Gandia Mar.30.2018 Delio April 15,2018
24.0 62 Feb.15,2018 Mar.15,2018 Lanuza April 15,2018 Mogan April 30,2018
25.0 125 Mar.8,2018 April 8,2018 Gandia April 30,2018 Esok May 30,2018
26.0 81 Mar.15,2018 April 15,2018 Lanuza April 30,2018 Panoy May 30,2018
27.0 91 April 1,2018 May 15,2018 Jessie June 15,2018
28.0 95 April 1,2018 May 15,2018 Delio June 15,2018
29.0 23 April 15,2018 May 30,2018 Mogan June 30,2018
FEBRUARY
30 34 April 8,2018 May 8,2018 Gandia May 15,2018 Esok June 30,2018
MARCH
31 35 May 1,2018 June 15,2018 Panoy July 15,2018
APRIL
32 41 April 15,2018 May 15,2018 Lanuza May 30,2018 Esok June 30,2018
33 66 May 8,2018 June 8,2018 Gandia June 15,2018 Jessie July 15,2018
MAY
34 18 June 15,2018 Delio July 15,2018
35 51 Ju ne 1,2018 July 15,2018 Mogan Aug.15,2018
36 52 May 15,2018 June 15,2018 Lanuza June 30,2018 Esok Aug.15,2018
37 60 June 8,2018 July 8,2018 Gandia July 15,2018 Panoy Aug.15,2018
38 78 June 15,2018 July 15,2018 Lanuza July 30,2018 Esok Aug.15,2018
39 80 June 15,2018 July 30,2018 Jessie Aug.30,2018
40 103 June 15,2018 July 30,2018 Delio Aug.30,2018
41 112 July 8,2018 Aug.8,2018 Gandia Aug.30,2018 Panoy Sept.30,2018
42 116 July 15,2018 Aug.15,2018 Lanuza Aug.30,2018 Esok Sept.30,2018
JUNE
43 13 July 15,2018 Aug.30,2018 Mogan Sept.30,2018
44 53 Aug.1,2018 Sept.15,2018 Jessie Sept.30,2018
45 58 Aug.1,2018 Sept.15,2018 Delio Sept.30,2018
46 93 Aug.8,2018 Sept.8,2018 Gandia Sept.30,2018 Panoy Oct.30,2018
47 108 Aug.15,2018 Sept.15,2018 Lanuza Sept.30,2018 Esok Oct.30,2018
48 126 Sept.1,2018 Oct.15,2018 Mogan Nov.15,2018
49 127 Sept.15,2018 Oct.30,2018 Jessie Nov.30,2018
JULY Sept.15,2018 Oct.30,2018 Delio Nov.30,2018
50 16 Sept.8,2018 Oct.8,2018 Gandia Oct.30,2018 Panoy Nov.30,2018
51 55 Sept.15,2018 Oct.15,2018 Lanuza Oct.30,2018 Esok Nov.30,2018
52 61 Oct.15,2018 Nov.30,2018 Mogan Dec.30,2018
53 124 Nov.1,2018 Dec.15,2018 Jessie Jan.15,2019
AUGUST Nov.1,2018 Dec.15,2018 Delio Jan.15,2019
54 4 Oct.15,2018 Nov.15,2018 Gandia Nov.30,2018 Panoy Dec.30,2018
55 11 Oct.15,2018 Nov.15,2018 Lanuza Nov.30,2018 Esok Dec.30,2018
56 44 Dec.1,2018 Jan.15,2019 Mogan Feb.15,2019
57 106 Dec.15,2018 Jan.30,2019 Jessie Feb.28,2019
58 119 Dec.15,2018 Jan.30,2019 Delio Feb.28,2019
59 122 Nov.15,2018 Dec.15,2018 Gandia Dec.30,2018 Panoy Jan.30,2019
SEPTEMBER
60 43 Nov.15,2018 Dec.15,2018 Lanuza Dec.30,2018 Esok Jan.30,2019
61 48 Jan.15,2019 Feb.28,2019 Mogan Mar.30,2019
62 57 Jan.30,2019 Mar.15,2019 Jessie April 15,2019
63 111 Jan.30,2019 Mar.15,2019 Delio April 15,2019
OCTOBER
64 15 Dec.15,2018 Jan.15,2019 Gandia Jan.30,2019 Panoy Feb.28,2019
NOVEMBER
65 40 Dec.15,2018 Jan.15,2019 Lanuza Jan.30,2019 Esok Feb.28,2019
66 54 Mar.1,2019 April 15,2019 Mogan May 15,2019
DECEMBER
67 47 Mar.15,2019 April 30,2019 Jessie May 30,2019
68 Jan-19 3 Mar.15,2019 April 30,2019 Delio May 30,2019
69 Jan-19 10 Jan.15,2019 Feb.15,2019 Gandia Feb.28,2019 Panoy Mar.30,2019
70 Jan-19 42 Jan.15,2019 Feb.15,2019 Lanuza Feb.28,2019 Esok Mar.30,2019
71 Jan-19 46 April 15,2019 May 30,2019 Mogan June 30,2019
72 Mar-19 39 May 1,2019 June 15,2019 Jessie July 15,2019
73 May-19 109 May 1,2019 June 15,2019 Delio July 15,2019
74 May-19 110 Feb.15,2019 Mar.15,2019 Gandia Mar.30,2019 Panoy April 30,2019
75 Sep-19 38 Feb.15,2019 Mar.15,2019 Lanuza Mar.30,2019 Esok April 30,2019
76 2 June 1,2019 July 15,2019 Mogan Aug.15,2019
77 28 June 15,2019 July 30,2019 Jessie Aug.30,2019
78 29 June 15,2019 July 30,2019 Delio Aug.30,2019
79 32 Mar.15,2019 April 15,2019 Gandia April 30,2019 Panoy May 30,2019
80 37 Mar.15,2019 April 15,2019 Lanuza April 30,2019 Esok May 30,2019
81 45 July 15,2019 Aug.30,2019 Mogan Sept.30,2019
82 56 Aug.1,2019 Sept.15,2019 Jessie Oct.15,2019
83 64 Aug.1,2019 Sept.15,2019 Delio Oct.15,2019
84 65 April 15,2019 May 15,2019 Gandia May 30,2019 Panoy June 30,2019
85 69 April 15,2019 May 15,2019 Lanuza May 30,2019 Esok June 30,2019
86 98 Sept.1,2019 Oct.15,2019 Mogan Nov.15,2019
87 102 Sept.15,2019 Oct.30,2019 Jessie Nov.30,2019
88 107 Sept.15,2019 Oct.30,2019 Delio Nov.30,2019
89 114 May 15,2019 June 15,2019 Gandia June 30,2019 Panoy July 30,2019
90 115 May 15,2019 June 15,2019 Lanuza June 30,2019 Esok July 30,2019
91 117 Oct.15,2019 Nov.30,2019 Mogan Dec.30,2019
92 118 Nov.1,2019 Dec.15,2019 Jessie Jan.15,2020
93 120 Nov.1,2019 Dec.15,2019 Delio Jan.15,2020
94 121 June 15,2019 July 15,2019 Gandia July 30,2019 Panoy Aug.30,2019
95 123 June 15,2019 July 15,2019 Lanuza July 30,2019 Esok Aug.30,2019
96 128 July 15,2019 Aug.15,2019 Gandia Aug.30,2019 Panoy Sept.30,2019
97 129 July 15,2019 Aug.15,2019 Lanuza Aug.30,2019 Esok Sept.30,2019
98 130 Aug.15,2019 Sept.15,2019 Gandia Sept.30,2019 Panoy Oct.30,2019
99 1 FINISHED
100 6 FINISHED
101 14 FINISHED
102 17 FINISHED
103 19 FINISHED
104 20 FINISHED
105 21 FINISHED
106 25 FINISHED
107 26 FINISHED
108 36 FINISHED
109 70 FINISHED
110 73 FINISHED
111 74 FINISHED
112 75 FINISHED
113 76 FINISHED
114 77 FINISHED
115 79 FINISHED
116 82 FINISHED
117 83 FINISHED
118 84 FINISHED
119 85 FINISHED
120 86 FINISHED
121 87 FINISHED
122 88 FINISHED
123 89 FINISHED
124 90 FINISHED
125 92 FINISHED
126 94 FINISHED
127 97 FINISHED
128 100 FINISHED
129 104 FINISHED
130 49 FINISHED
CONSTRUCTION SCHEDULE JANUARY 2018 - DECEMEBER 2018
MONTH: LAYOUT-COLUMN/FOOTING FORMWORKS FINISHING : MASONRY FINISHING : PAINTING WORKS
Item Proposed Unit Date of Date of Date of Date of Foreman / Date of Date of STATUS
GROUP STATUS GROUP GROUP
Start # Start Finish Start Finish Leadman Start Finish
JANUARY
1.0 105 Delio Jan.30,2018
2.0 22 Jessie Jan.30,2018
3.0 5 Jessie Jan.30,2018
4.0 59 SUBCON-FICS Jan.2018
5.0 12 Jan.2,2018 Esok Jan.23,2018
6.0 99 Lanuza Feb.15,2018 Esok Feb.2018
7.0 71 SUBCON-BIGBOY
Feb.2018
8.0 72 SUBCON-BIGBOY
9.0 63 Feb.2018
10.0 50 Feb.2018
SUBCON-FICS
11.0 57 Feb.2018
12.0 113 Mar.30,2018
13.0 30
14.0 31 SUBCON-AAJ Feb.2018
15.0 33
16.0 7 Feb.28,2018 Delio Mar.30,2018
17.0 8 Feb.15,2018 Delio Feb-18
18.0 27 Feb.15,2018 Panoy Feb.2018
19.0 67 Feb.28,2018 Mogan Mar.30,2018
20.0 24 Jan2,2018 Jan.30,2018 Gandia Feb.28,2018 Esok Mar.15,2018
21.0 101 Jan15,2018 Feb.15,2019 Lanuza Mar.15,2018 Esok Mar.30,2018
22.0 68 Feb.1,2018 Mar.15,2018 Jessie Apr.15,2018
23.0 96 Feb.15,2018 Mar.30,2018 Panoy Apr.30,2018
24.0 62 Mar.1,2018 Apr.15,2018 Mogan May 15,2018
25.0 125 Mar.1,2018 Apr.15,2018 Delio May 15,2018
26.0 81 Feb.1,2018 Mar.1,2018 Gandia Mar.30,2018 Esok Apr.15,2018
27.0 91 Feb.15,2019 Mar.15,2018 Lanuza Apr.15,2018 Esok Apr.30,2018
28.0 95 Mar.15,2018 Apr.30,2018 Jessie May 30,2018
29.0 23 Mar.30,2018 May 15,2018 Panoy June 15,2018
FEBRUARY
30 34 Apr.15,2018 May 30,2018 Mogan June 30,2018
MARCH
31 35 Apr.15,2018 May 30,2018 Delio June 30,2018
APRIL
32 41 Mar.1,2018 April 1,2018 Gandia April 30,2018 Esok May 15,2018
33 66 Mar.15,2018 April 15,2018 Lanuza May 15,2018 Esok May 30,2018
MAY
34 18 5/1/2018 6/15/2018 Jessie 7/15/2018
35 51 5/15/2018 6/29/2018 Panoy 7/29/2018
36 52 6/1/2018 7/15/2018 Mogan 8/15/2018
37 60 6/1/2018 7/15/2018 Delio 8/15/2018
38 78 4/1/2018 5/1/2018 Gandia 5/31/2018 Esok 6/15/2018
39 80 4/15/2018 5/15/2018 Lanuza 6/14/2018 Esok 6/29/2018
40 103 6/15/2018 7/30/2018 Jessie 8/29/2018
41 112 7/1/2018 8/15/2018 Panoy 9/14/2018
42 116 7/16/2018 8/30/2018 Mogan 9/29/2018
JUNE
43 13 7/16/2018 8/30/2018 Delio 9/29/2018
44 53 5/1/2018 5/31/2018 Gandia 6/30/2018 Esok 7/15/2018
45 58 5/15/2018 6/14/2018 Lanuza 7/14/2018 Esok 7/29/2018
46 93 7/30/2018 9/13/2018 Jessie 10/13/2018
47 108 8/15/2018 9/29/2018 Panoy 10/29/2018
48 126 8/30/2018 10/14/2018 Mogan 11/13/2018
49 127 8/30/2018 10/14/2018 Delio 11/13/2018
JULY
50 16 5/31/2018 6/30/2018 Gandia 7/30/2018 Esok 8/14/2018
51 55 6/14/2018 7/14/2018 Lanuza 8/13/2018 Esok 8/28/2018
52 61 9/13/2018 10/28/2018 Jessie 11/27/2018
53 124 9/29/2018 11/13/2018 Panoy 12/13/2018
AUGUST
54 4 10/14/2018 11/28/2018 Mogan 12/28/2018
55 11 10/14/2018 11/28/2018 Delio 12/28/2018
56 44 6/30/2018 7/30/2018 Gandia 8/29/2018 Esok 9/13/2018
57 106 7/14/2018 8/13/2018 Lanuza 9/12/2018 Esok 9/27/2018
58 119 7/30/2018 8/29/2018 Gandia 9/28/2018 Esok 10/13/2018
59 122 8/13/2018 9/12/2018 Lanuza 10/12/2018 Esok 10/27/2018
SEPTEMBER
60 43 10/28/2018 12/12/2018 Jessie 1/11/2019
61 48 11/13/2018 12/28/2018 Panoy 1/27/2019
62 57 11/28/2018 1/12/2019 Mogan 2/11/2019
63 111 11/28/2018 1/12/2019 Delio 2/11/2019
OCTOBER
64 15 12/12/2018 1/26/2019 Jessie 2/25/2019
NOVEMBER
65 40 8/29/2018 9/28/2018 Gandia 10/28/2018 Esok 11/12/2018
66 54 9/12/2018 10/12/2018 Lanuza 11/11/2018 Esok 11/26/2018
DECEMBER
67 47 12/28/2018 2/11/2019 Panoy 3/13/2019
68 Jan-19 3 1/12/2019 2/26/2019 Mogan 3/28/2019
69 Jan-19 10 1/12/2019 2/26/2019 Delio 3/28/2019
70 Jan-19 42 9/28/2018 10/28/2018 Gandia 11/27/2018 Esok 12/12/2018
71 Jan-19 46 10/12/2018 11/11/2018 Lanuza 12/11/2018 Esok 12/26/2018
72 Mar-19 39 1/26/2019 3/12/2019 Jessie 4/11/2019
73 May-19 109 2/11/2019 3/28/2019 Panoy 4/27/2019
74 May-19 110 2/26/2019 4/12/2019 Mogan 5/12/2019
75 Sep-19 38 2/26/2019 4/12/2019 Delio 5/12/2019
76 2 10/28/2018 11/27/2018 Gandia 12/27/2018 Esok 1/11/2019
77 28 11/11/2018 12/11/2018 Lanuza 1/10/2019 Esok 1/25/2019
78 29 3/12/2019 4/26/2019 Jessie 5/26/2019
79 32 3/28/2019 5/12/2019 Panoy 6/11/2019
80 37 4/12/2019 5/27/2019 Mogan 6/26/2019
81 45 4/12/2019 5/27/2019 Delio 6/26/2019
82 56 11/27/2018 12/27/2018 Gandia 1/26/2019 Esok 2/10/2019
83 64 12/11/2018 1/10/2019 Lanuza 2/9/2019 Esok 2/24/2019
84 65 4/26/2019 6/10/2019 Jessie 7/10/2019
85 69 5/12/2019 6/26/2019 Panoy 7/26/2019
86 98 5/27/2019 7/11/2019 Mogan 8/10/2019
87 102 5/27/2019 7/11/2019 Delio 8/10/2019 LAST DAY
88 107 12/27/2018 1/26/2019 Gandia 2/25/2019 Esok 3/12/2019
89 114 1/10/2019 2/9/2019 Lanuza 3/11/2019 Esok 3/26/2019
90 115 1/26/2019 2/25/2019 3/27/2019 4/11/2019
91 117 2/9/2019 3/11/2019 4/10/2019 4/25/2019
92 118 2/25/2019 3/27/2019 5/11/2019
93 120 3/11/2019 4/10/2019 5/25/2019
94 121 3/27/2019 4/26/2019 6/10/2019
95 123 4/10/2019 5/10/2019 6/24/2019
96 128 4/26/2019 5/26/2019 7/10/2019
97 129 5/10/2019 6/9/2019 7/24/2019
98 130 5/26/2019 6/25/2019 8/9/2019
99 1 FINISHED
100 6 FINISHED
101 14 FINISHED
102 17 FINISHED
103 19 FINISHED
104 20 FINISHED
105 21 FINISHED
106 25 FINISHED
107 26 FINISHED
108 36 FINISHED
109 70 FINISHED
110 73 FINISHED
111 74 FINISHED
112 75 FINISHED
113 76 FINISHED
114 77 FINISHED
115 79 FINISHED
116 82 FINISHED
117 83 FINISHED
118 84 FINISHED
119 85 FINISHED
120 86 FINISHED
121 87 FINISHED
122 88 FINISHED
123 89 FINISHED
124 90 FINISHED
125 92 FINISHED
126 94 FINISHED
127 97 FINISHED
128 100 FINISHED
129 104 FINISHED
130 49 FINISHED

MANPOWER DISTRIBUTION :
CONSTRUCTION SCHEDULE JANUARY 2018 - MARCH 2019
MONTH: LAYOUT-COLUMN/FOOTING FORMWORKS FINISHING : MASONRY FINISHING : PAINTING WORKS
Item Proposed Unit Date of Date of Date of Date of Foreman / Date of Date of STATUS
GROUP STATUS GROUP GROUP
Start # Start Finish Start Finish Leadman Start Finish
JANUARY
1.0 105 Delio Jan.30,2018
2.0 22 Jessie Jan.30,2018
3.0 5 Jessie Jan.30,2018
4.0 59 SUBCON-FICS Jan.2018
5.0 12 Jan.2,2018 Esok Jan.23,2018
6.0 99 Lanuza Feb.15,2018 Esok Feb.2018
7.0 71 SUBCON-BIGBOY
Feb.2018
8.0 72 SUBCON-BIGBOY
9.0 63 Feb.2018
10.0 50 Feb.2018
SUBCON-FICS
11.0 57 Feb.2018
12.0 113 Mar.30,2018
13.0 30
14.0 31 SUBCON-AAJ Feb.2018
15.0 33
16.0 7 Feb.28,2018 Delio Mar.30,2018
17.0 8 Feb.15,2018 Delio Feb-18
18.0 27 Feb.15,2018 Panoy Feb.2018
19.0 67 Feb.28,2018 Mogan Mar.30,2018
20.0 24 Jan2,2018 Jan.30,2018 Gandia Feb.28,2018 Esok Mar.15,2018
21.0 101 Jan15,2018 Feb.15,2019 Lanuza Mar.15,2018 Esok Mar.30,2018
22.0 68 2/1/2018 3/18/2018 Jessie 4/17/2018
23.0 96 2/15/2018 4/1/2018 Panoy 5/1/2018
24.0 62 3/1/2018 4/15/2018 Mogan 5/15/2018
25.0 125 3/1/2018 4/15/2018 Delio 5/15/2018
26.0 81 2/1/2018 3/18/2018 G6 4/17/2018
27.0 91 2/1/2018 3/18/2018 G7 4/17/2018
28.0 95 2/1/2018 3/18/2018 G8 4/17/2018
29.0 23 2/1/2018 3/1/2018 Gandia 3/18/2018 Esok 4/17/2018
FEBRUARY
30 34 2/15/2018 3/17/2018 Lanuza 4/1/2018 Esok 5/1/2018
MARCH
31 35 3/18/2018 5/2/2018 Jessie 6/1/2018
APRIL
32 41 4/1/2018 5/16/2018 Panoy 6/15/2018
33 66 4/15/2018 5/30/2018 Mogan 6/29/2018
MAY
34 18 4/15/2018 5/30/2018 Delio 6/29/2018
35 51 3/18/2018 5/2/2018 G6 6/1/2018
36 52 3/18/2018 5/2/2018 G7 6/1/2018
37 60 3/18/2018 5/2/2018 G8 6/1/2018
38 78 3/1/2018 3/31/2018 Gandia 4/15/2018 Esok 5/15/2018
39 80 3/17/2018 4/16/2018 Lanuza 5/1/2018 Esok 5/31/2018
40 103 5/2/2018 6/16/2018 Jessie 7/16/2018
41 112 5/16/2018 6/30/2018 Panoy 7/30/2018
42 116 5/30/2018 7/14/2018 Mogan 8/13/2018
JUNE
43 13 5/30/2018 7/14/2018 Delio 8/13/2018
44 53 5/2/2018 6/16/2018 G6 7/16/2018
45 58 5/2/2018 6/16/2018 G7 7/16/2018
46 93 5/2/2018 6/16/2018 G8 7/16/2018
47 108 3/31/2018 4/30/2018 Gandia 5/15/2018 Esok 6/14/2018
48 126 4/16/2018 5/16/2018 Lanuza 5/31/2018 Esok 6/30/2018
49 127 6/16/2018 7/31/2018 Jessie 8/30/2018
JULY
50 16 6/30/2018 8/14/2018 Panoy 9/13/2018
51 55 7/14/2018 8/28/2018 Mogan 9/27/2018
52 61 7/14/2018 8/28/2018 Delio 9/27/2018
53 124 6/16/2018 7/31/2018 G6 8/30/2018
AUGUST
54 4 6/16/2018 7/31/2018 G7 8/30/2018
55 11 6/16/2018 7/31/2018 G8 8/30/2018
56 44 4/30/2018 5/30/2018 Gandia 6/14/2018 Esok 7/14/2018
57 106 5/16/2018 6/15/2018 Lanuza 6/30/2018 Esok 7/30/2018
58 119 7/31/2018 9/14/2018 Jessie 10/14/2018
59 122 8/14/2018 9/28/2018 Panoy 10/28/2018
SEPTEMBER
60 43 8/28/2018 10/12/2018 Mogan 11/11/2018
61 48 8/28/2018 10/12/2018 Delio 11/11/2018
62 57 7/31/2018 9/14/2018 G6 10/14/2018
63 111 7/31/2018 9/14/2018 G7 10/14/2018
OCTOBER
64 15 7/31/2018 9/14/2018 G8 10/14/2018
NOVEMBER
65 40 5/30/2018 6/29/2018 Gandia 7/14/2018 Esok 8/13/2018
66 54 6/15/2018 7/15/2018 Lanuza 7/30/2018 Esok 8/29/2018
DECEMBER
67 47 9/14/2018 10/29/2018 Jessie 11/28/2018
68 Jan-19 3 9/28/2018 11/12/2018 Panoy 12/12/2018
69 Jan-19 10 10/12/2018 11/26/2018 Mogan 12/26/2018
70 Jan-19 42 10/12/2018 11/26/2018 Delio 12/26/2018
71 Jan-19 46 9/14/2018 10/29/2018 G6 11/28/2018
72 Mar-19 39 9/14/2018 10/29/2018 G7 11/28/2018
73 May-19 109 9/14/2018 10/29/2018 G8 11/28/2018
74 May-19 110 6/29/2018 7/29/2018 Gandia 8/13/2018 Esok 9/12/2018
75 Sep-19 38 7/15/2018 8/14/2018 Lanuza 8/29/2018 Esok 9/28/2018
76 2 10/29/2018 12/13/2018 Jessie 1/12/2019
77 28 11/12/2018 12/27/2018 Panoy 1/26/2019
78 29 11/26/2018 1/10/2019 Mogan 2/9/2019
79 32 11/26/2018 1/10/2019 Delio 2/9/2019
80 37 10/29/2018 12/13/2018 G6 1/12/2019
81 45 10/29/2018 12/13/2018 G7 1/12/2019
82 56 10/29/2018 12/13/2018 G8 1/12/2019
83 64 7/29/2018 8/28/2018 Gandia 9/12/2018 Esok 10/12/2018
84 65 8/14/2018 9/13/2018 Lanuza 9/28/2018 Esok 10/28/2018
85 69 12/13/2018 1/27/2019 Jessie 2/26/2019
86 98 12/27/2018 2/10/2019 Panoy 3/12/2019
87 102 1/10/2019 2/24/2019 Mogan 3/26/2019
88 107 1/10/2019 2/24/2019 Delio 3/26/2019
89 114 12/13/2018 1/27/2019 G6 2/26/2019
90 115 12/13/2018 1/27/2019 G7 2/26/2019
91 117 12/13/2018 1/27/2019 G8 2/26/2019
92 118 8/28/2018 9/27/2018 Gandia 10/12/2018 Esok 11/11/2018
93 120 9/13/2018 10/13/2018 Lanuza 10/28/2018 Esok 11/27/2018
94 121 9/27/2018 10/27/2018 Gandia 11/11/2018 12/11/2018
95 123 10/13/2018 11/12/2018 Lanuza 11/27/2018 12/27/2018
96 128 10/27/2018 11/26/2018 Gandia 12/11/2018 1/10/2019
97 129 11/12/2018 12/12/2018 Lanuza 12/27/2018 1/26/2019
98 130 11/26/2018 12/26/2018 Gandia 1/10/2019 2/9/2019
99 1 FINISHED
100 6 FINISHED
101 14 FINISHED
102 17 FINISHED
103 19 FINISHED
104 20 FINISHED
105 21 FINISHED
106 25 FINISHED
107 26 FINISHED
108 36 FINISHED
109 70 FINISHED
110 73 FINISHED
111 74 FINISHED
112 75 FINISHED
113 76 FINISHED
114 77 FINISHED
115 79 FINISHED
116 82 FINISHED
117 83 FINISHED
118 84 FINISHED
119 85 FINISHED
120 86 FINISHED
121 87 FINISHED
122 88 FINISHED
123 89 FINISHED
124 90 FINISHED
125 92 FINISHED
126 94 FINISHED
127 97 FINISHED
128 100 FINISHED
129 104 FINISHED
130 49 FINISHED

MANPOWER DISTRIBUTION :
CONSTRUCTION SCHEDULE JANUAR
MONTH: LAYOUT-COLUMN/FOOTING FORMWORKS
Item Proposed Unit Date of Date of
GROUP STATUS
Start # Start Finish
JANUARY
1.0 105
2.0 22
3.0 5
4.0 59
5.0 12
6.0 99
7.0 71 SUBCON-BIGBOY
8.0 72 SUBCON-BIGBOY
9.0 FEBRUARY 57
10.0 FEBRUARY 33
11.0 FEBRUARY 8
12.0 FEBRUARY 27
13.0 FEBRUARY 24
14.0 FEBRUARY 101
15.0 march 63
16.0 march 31
17.0 march 30
18.0 march 68
19.0 march 7
20.0 march 50
21.0 march 67
22.0 march 113
23.0 96
24.0 62
25.0 125
26.0 81
27.0 91
28.0 95
29.0 23
FEBRUARY
30 34
31 64
MARCH
32 35
APRIL
33 41
34 66
MAY
35 18
36 51
37 52
38 60
39 78
40 80
41 103
42 112
43 116
JUNE
44 13
45 53
46 58
47 93
48 108
49 126
50 127
JULY
51 16
52 55
53 61
54 124
AUGUST
55 4
56 11
57 44
58 106
59 119
60 122
SEPTEMBER
61 43
62 48
63 57
64 111
OCTOBER
65 15
NOVEMBER
66 40
67 54
DECEMBER
68 47
69 Jan-19 3
70 Jan-19 10
71 Jan-19 42
72 Jan-19 46
73 Mar-19 39
74 May-19 109
75 May-19 110
76 Sep-19 38
77 2
78 28
79 29
80 32
81 37
82 45
83 56
84 65
85 69
86 98
87 102
88 107
89 114
90 115
91 117
92 118
93 120
94 121
95 123
96 128
97 129
98 130
99 1
100 6
101 14
102 17
103 19
104 20
105 21
106 25
107 26
108 36
109 70
110 73
111 74
112 75
113 76
114 77
115 79
116 82
117 83
118 84
119 85
120 86
121 87
122 88
123 89
124 90
125 92
126 94
127 97
128 100
129 104
130 49

MANPOWER DISTRIBUTION :
SCHEDULE JANUARY 2018 - DECEMEBER 2018
RMWORKS FINISHING : MASONRY FINISHING : PAINTING WORKS
Date of Date of Foreman / Date of Date of
GROUP GROUP
Start Finish Leadman Start Finish

Jan.30,2018
Jan.30,2018
Jan.2018
Jan.2,2018 Jan.23,2018
Lanuza Feb.15,2018 Esok Feb.2018
SUBCON-BIGBOY
Feb.2018
SUBCON-BIGBOY
Jessie Feb.25
Feb.18,2018 Esok Feb.28
Feb.10,2018 Delio Feb.28
Feb.15,2018 Panoy Feb.25
Panoy Feb.25
Esok Feb.28
Jessie Mar.15,2018
Panoy Mar. 30,2018
Esok Mar.30,2018
Mogan Mar. 30,2018
Delio Mar.25,2018
Jessie Mar.25,2018
Mar.25,2018
Mar.30,2018
STATUS

FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
FINISHED
No. of
ITEM GROUP Unit SCOPE OF WORK Date Start Date Finish
Days
HOUSE CONSTRUCTION
1.0 ERIC 99 PAINTING 16 24-Feb-18 12-Mar-18
2.0 CASTELO 71 CABINETS,TILING,PAINTING 19 24-Feb-18 15-Mar-18
3.0 CASTELO 72 CABINETS,TILING,PAINTING 19 24-Feb-18 15-Mar-18
4.0 RAUL 57 PAINTING 4 24-Feb-18 28-Feb-18
5.0 asstd 33 PAINTING 4 24-Feb-18 28-Feb-18
6.0 8 PAINTING 4 24-Feb-18 28-Feb-18
7.0 27 PAINTING 4 24-Feb-18 28-Feb-18
8.0 DELIO 24 MASONRY/TILING 24 26-Feb-18 22-Mar-18
RODEL CEILING 9 28-Feb-18 09-Mar-18
RAUL PAINTING 28 01-Mar-18 29-Mar-18
9.0 JESSIE 101 MASONRY/TILING 24 01-Mar-18 25-Mar-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 02-Mar-18 10-Mar-18
RODEL CEILING 8 02-Mar-18 10-Mar-18
ALWYN PAINTING 28 05-Mar-18 02-Apr-18
10.0 RONNIE 63 CEILING 9 05-Mar-18 14-Mar-18
ERIC PAINTING 28 05-Mar-18 02-Apr-18
11.0 RONALD 31 MASONRY/TILING 9 26-Feb-18 07-Mar-18
RODEL CEILING 9 05-Mar-18 14-Mar-18
RAUL PAINTING 29 10-Mar-18 08-Apr-18
12.0 RONALD 30 MASONRY/TILING 24 06-Mar-18 30-Mar-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 09-Mar-18 17-Mar-18
RODEL CEILING 9 14-Mar-18 23-Mar-18
ALEGRE PAINTING 28 20-Mar-18 17-Apr-18
13.0 NOVY 68 MASONRY/TILING 24 26-Feb-18 22-Mar-18
RONNIE CEILING 10 18-Mar-18 28-Mar-18
ALWYN PAINTING 28 20-Mar-18 17-Apr-18
14.0 DELIO 7 MASONRY/TILING 12 24-Feb-18 08-Mar-18
RONNIE CEILING 10 10-Mar-18 20-Mar-18
ALEGRE PAINTING 28 26-Feb-18 26-Mar-18
15.0 ESOK 50 MASONRY/TILING 24 26-Feb-18 22-Mar-18
MOJAKO ROOFING,STAIR AND TERRACE GRILLS 8 05-Mar-18 13-Mar-18
RODEL CEILING 9 23-Mar-18 01-Apr-18
ERIC PAINTING 28 25-Mar-18 22-Apr-18
16.0 NOVY 67 MASONRY/TILING 40 20-Mar-18 29-Apr-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 10-Apr-18 18-Apr-18
RONNIE CEILING 9 18-Apr-18 27-Apr-18
RAUL PAINTING 28 26-Apr-18 24-May-18
17.0 ESOK 113 MASONRY/TILING 40 22-Mar-18 01-May-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 9 09-Apr-18 18-Apr-18
RODEL CEILING 9 11-Apr-18 20-Apr-18
ALWYN PAINTING 28 18-Apr-18 16-May-18
18.0 NOEL 96 CAST-IN-PLACE 25 16-Feb-18 13-Mar-18
DELIO MASONRY/TILING 24 23-Mar-18 16-Apr-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 18-Apr-18 26-Apr-18
RODEL CEILING 8 20-Apr-18 28-Apr-18
ERIC PAINTING 25 23-Apr-18 18-May-18
19.0 BUSTAMANTE 62 84 08-Mar-18 31-May-18
20.0 NOEL 125 CAST-IN-PLACE 25 13-Mar-18 07-Apr-18
RONALD MASONRY/TILING 24 01-Apr-18 25-Apr-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 18-Apr-18 26-Apr-18
RODEL CEILING 8 20-Apr-18 28-Apr-18
ALEGRE PAINTING 25 26-Apr-18 21-May-18
21.0 BUSTAMANTE 81 84 08-Mar-18 31-May-18
22.0 FREDRICK 91 CAST-IN-PLACE 25 20-Feb-18 17-Mar-18
JESSIE MASONRY/TILING 24 25-Mar-18 18-Apr-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 26-Apr-18 04-May-18
RONNIE CEILING 8 28-Apr-18 06-May-18
ALWYN PAINTING 25 17-May-18 11-Jun-18
23.0 CASTELO 95 84 06-Mar-18 29-May-18
24.0 CASTELO 23 84 06-Mar-18 29-May-18
25.0 CASTELO 34 84 06-Mar-18 29-May-18
26.0 BUSTAMANTE 64 84 08-Mar-18 31-May-18
27.0 CASTELO 35 84 06-Mar-18 29-May-18
28.0 BUSTAMANTE 66 84 08-Mar-18 31-May-18
29.0 FREDRICK 41 CAST-IN-PLACE 25 19-Mar-18 13-Apr-18
DELIO MASONRY/TILING 24 16-Apr-18 10-May-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 26-Apr-18 04-May-18
RODEL CEILING 8 28-Apr-18 06-May-18
ERIC PAINTING 25 19-May-18 13-Jun-18
30.0 NOEL 18 CAST-IN-PLACE 25 08-Apr-18 03-May-18
JESSIE MASONRY/TILING 24 19-Apr-18 13-May-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 05-May-18 13-May-18
RONNIE CEILING 8 07-May-18 15-May-18
ALEGRE PAINTING 25 21-May-18 15-Jun-18
31.0 RONALD 51 MASONRY/TILING 40 26-Apr-18 05-Jun-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 9 04-May-18 13-May-18
RODEL CEILING 9 07-May-18 16-May-18
RAUL PAINTING 28 25-May-18 22-Jun-18
32.0 FREDRICK 52 CAST-IN-PLACE 25 14-Apr-18 09-May-18
NOVY MASONRY/TILING 24 30-Apr-18 24-May-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 14-May-18 22-May-18
RONNIE CEILING 8 16-May-18 24-May-18
ALWYN PAINTING 25 11-Jun-18 06-Jul-18
33.0 NOEL 60 CAST-IN-PLACE 25 04-May-18 29-May-18
ESOK MASONRY/TILING 24 15-May-18 08-Jun-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 14-May-18 22-May-18
RODEL CEILING 8 17-May-18 25-May-18
ERIC PAINTING 25 01-Jun-18 26-Jun-18
34.0 FREDRICK 78 CAST-IN-PLACE 25 10-May-18 04-Jun-18
DELIO MASONRY/TILING 24 25-May-18 18-Jun-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 22-May-18 30-May-18
RONNIE CEILING 8 25-May-18 02-Jun-18
ALEGRE PAINTING 25 16-Jun-18 11-Jul-18
35.0 JESSIE 80 MASONRY/TILING 40 14-May-18 23-Jun-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 9 05-Jun-18 14-Jun-18
RODEL CEILING 9 10-Jun-18 19-Jun-18
RAUL PAINTING 28 23-Jun-18 21-Jul-18
36.0 NOVY 103 MASONRY/TILING 40 24-May-18 03-Jul-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 9 15-Jun-18 24-Jun-18
RONNIE CEILING 9 20-Jun-18 29-Jun-18
ERIC PAINTING 28 27-Jun-18 25-Jul-18
37.0 NOEL 112 CAST-IN-PLACE 25 01-Jun-18 26-Jun-18
RONALD MASONRY/TILING 24 20-Jun-18 14-Jul-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 01-Jul-18 09-Jul-18
RODEL CEILING 8 05-Jul-18 13-Jul-18
ALWYN PAINTING 25 10-Jul-18 04-Aug-18
38.0 FREDRICK 116 CAST-IN-PLACE 25 05-Jun-18 30-Jun-18
ESOK MASONRY/TILING 24 27-Jun-18 21-Jul-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 01-Jul-18 09-Jul-18
RONNIE CEILING 8 10-Jul-18 18-Jul-18
ALEGRE PAINTING 25 15-Jul-18 09-Aug-18
39.0 DELIO 13 MASONRY/TILING 40 24-Jul-18 02-Sep-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 9 21-Aug-18 30-Aug-18
RODEL CEILING 9 28-Aug-18 06-Sep-18
RAUL PAINTING 28 01-Sep-18 29-Sep-18
40.0 NOEL 53 CAST-IN-PLACE 25 30-Jun-18 25-Jul-18
JESSIE MASONRY/TILING 24 23-Jul-18 16-Aug-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 27-Jul-18 04-Aug-18
RONNIE CEILING 8 03-Aug-18 11-Aug-18
ERIC PAINTING 25 10-Aug-18 04-Sep-18
41.0 FREDRICK 58 CAST-IN-PLACE 25 02-Jul-18 27-Jul-18
NOVY MASONRY/TILING 24 28-Jul-18 21-Aug-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 05-Aug-18 13-Aug-18
RONNIE CEILING 8 14-Aug-18 22-Aug-18
ALWYN PAINTING 25 15-Aug-18 09-Sep-18
42.0 RONALD 93 MASONRY/TILING 40 16-Jul-18 25-Aug-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 9 13-Aug-18 22-Aug-18
RONNIE CEILING 9 14-Aug-18 23-Aug-18
ALEGRE PAINTING 28 10-Aug-18 07-Sep-18
43.0 NOEL 108 CAST-IN-PLACE 25 26-Jul-18 20-Aug-18
ESOK MASONRY/TILING 24 17-Aug-18 10-Sep-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 21-Aug-18 29-Aug-18
RONNIE CEILING 8 30-Aug-18 07-Sep-18
ERIC PAINTING 25 05-Sep-18 30-Sep-18
44.0 FREDRICK 126 CAST-IN-PLACE 25 28-Jul-18 22-Aug-18
JESSIE MASONRY/TILING 24 20-Aug-18 13-Sep-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 23-Aug-18 31-Aug-18
RODEL CEILING 8 07-Sep-18 15-Sep-18
ALEGRE PAINTING 25 05-Sep-18 30-Sep-18
45.0 NOEL 127 CAST-IN-PLACE 25 21-Aug-18 15-Sep-18
ESOK MASONRY/TILING 24 11-Sep-18 05-Oct-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 16-Sep-18 24-Sep-18
RONNIE CEILING 8 20-Sep-18 28-Sep-18
ALWYN PAINTING 25 05-Sep-18 30-Sep-18
46.0 NOVY 16 MASONRY/TILING 40 22-Aug-18 01-Oct-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 9 17-Sep-18 26-Sep-18
RODEL CEILING 9 25-Sep-18 04-Oct-18
RAUL PAINTING 28 30-Sep-18 28-Oct-18
47.0 RONALD 55 MASONRY/TILING 40 25-Aug-18 04-Oct-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 9 20-Sep-18 29-Sep-18
RONNIE CEILING 9 28-Sep-18 07-Oct-18
ERIC PAINTING 28 01-Oct-18 29-Oct-18
48.0 FREDRICK 61 CAST-IN-PLACE 25 23-Aug-18 17-Sep-18
DELIO MASONRY/TILING 24 15-Sep-18 09-Oct-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 26-Sep-18 04-Oct-18
RODEL CEILING 8 01-Oct-18 09-Oct-18
ALWYN PAINTING 25 01-Oct-18 26-Oct-18
49.0 JESSIE 124 MASONRY/TILING 40 14-Sep-18 24-Oct-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 9 10-Oct-18 19-Oct-18
RONNIE CEILING 9 17-Oct-18 26-Oct-18
ALEGRE PAINTING 28 04-Oct-18 01-Nov-18
50.0 NOEL 4 CAST-IN-PLACE 25 16-Sep-18 11-Oct-18
NOVY MASONRY/TILING 24 10-Oct-18 03-Nov-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 13-Oct-18 21-Oct-18
RODEL CEILING 8 19-Oct-18 27-Oct-18
ALWYN PAINTING 25 26-Oct-18 20-Nov-18
51.0 RONALD 11 MASONRY/TILING 40 05-Oct-18 14-Nov-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 9 03-Nov-18 12-Nov-18
RONNIE CEILING 9 10-Nov-18 19-Nov-18
RAUL PAINTING 28 15-Nov-18 13-Dec-18
52.0 FREDRICK 44 CAST-IN-PLACE 25 18-Sep-18 13-Oct-18
ESOK MASONRY/TILING 24 10-Oct-18 03-Nov-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 15-Oct-18 23-Oct-18
RODEL CEILING 8 21-Oct-18 29-Oct-18
ERIC PAINTING 25 29-Oct-18 23-Nov-18
53.0 DELIO 106 MASONRY/TILING 40 10-Oct-18 19-Nov-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 9 03-Nov-18 12-Nov-18
RODEL CEILING 9 10-Nov-18 19-Nov-18
ALEGRE PAINTING 28 03-Nov-18 01-Dec-18
54.0 NOEL 119 CAST-IN-PLACE 25 12-Oct-18 06-Nov-18
JESSIE MASONRY/TILING 24 03-Nov-18 27-Nov-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 10-Nov-18 18-Nov-18
RONNIE CEILING 8 19-Nov-18 27-Nov-18
ALWYN PAINTING 25 21-Nov-18 16-Dec-18
55.0 FREDRICK 122 CAST-IN-PLACE 25 14-Oct-18 08-Nov-18
ESOK MASONRY/TILING 24 05-Nov-18 29-Nov-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 13-Nov-18 21-Nov-18
RODEL CEILING 8 20-Nov-18 28-Nov-18
ERIC PAINTING 25 24-Nov-18 19-Dec-18
NOVY 43 MASONRY/TILING 40 05-Nov-18 15-Dec-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 9 05-Dec-18 14-Dec-18
RONNIE CEILING 9 15-Dec-18 24-Dec-18
ALEGRE PAINTING 28 15-Dec-18 12-Jan-19
NOEL 48 CAST-IN-PLACE 25 06-Nov-18 01-Dec-18
RONALD MASONRY/TILING 24 02-Dec-18 26-Dec-18
Mojako ROOFING,STAIR AND TERRACE GRILLS 8 05-Dec-18 13-Dec-18
RODEL CEILING 8 10-Dec-18 18-Dec-18
RAUL PAINTING 25 14-Dec-18 08-Jan-19
FREDRICK 111 CAST-IN-PLACE 25 09-Nov-18 04-Dec-18
DELIO MASONRY/TILING 24 05-Dec-18 29-Dec-18
NONONG ROOFING,STAIR AND TERRACE GRILLS 8 08-Dec-18 16-Dec-18
RONNIE CEILING 8 10-Dec-18 18-Dec-18
ALWYN PAINTING 25 15-Dec-18 09-Jan-19
JESSIE 15 MASONRY/TILING 40 28-Nov-18 07-Jan-19
Mojako ROOFING,STAIR AND TERRACE GRILLS 9 28-Dec-18 06-Jan-19
RODEL CEILING 9 07-Jan-19 16-Jan-19
ERIC PAINTING 28 10-Jan-19 07-Feb-19
40
54

47
3
10
42
46
39
109
110
38
2
28
29
32
37
45
56
65
69
98
102
107
114
115
117
118
120
121
123
128
129
130
1.0 1
2.0 5
3.0 6
4.0 8
5.0 9
6.0 12
7.0 14
8.0 17
9.0 19
10.0 20
11.0 21
12.0 22
13.0 25
14.0 26
15.0 27
16.0 33
17.0 36
18.0 49
19.0 57
20.0 59
21.0 70
22.0 73
23.0 74
24.0 75
25.0 76
26.0 77
27.0 79
28.0 82
29.0 83
30.0 84
31.0 85
32.0 86
33.0 87
34.0 88
35.0 89
36.0 90
37.0 92
38.0 94
39.0 97
40.0 100
41.0 104
42.0 105
FEBRUARY
Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu
01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg

gggggg gggggg

gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg

gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
MARCH
W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M
28 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg

gggggg

gggggg

gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg


APRIL
Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su
27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg


MAY
M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S
23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg


JUNE
Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F
20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
JUNE
S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12
gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg


gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
JULY
F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08
gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg

gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg


gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
AUGUST
Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu
09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04
gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
SEPTEMBER
W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M
05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01
gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg

gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
OCTOBER
Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su
02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg


gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
NOVEMBER
M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S
29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg


gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
DECEMBER
Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F
25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21
gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
Jan-19
S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th
22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17
gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg

gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg


9 FEBRUAR
F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W
18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13
gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg gggggg
FEBRUARY
Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 01 02 03 04 05 06 07 08 09 10 11 12
MARCH
W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08
APRIL
Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su
09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05
MAY
M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S
06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01
JUNE
Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F
02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
JULY
S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th
29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
AUGUST
F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W
26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21
SEPTEMBER
Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu
22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17
R OCTOB
W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M
18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14
OCTOBER
Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10
NOVEMBER
M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07
DECEMBER
Su M Tu W Th F S Su M Tu W Th F S Su M Tu W Th F S Su M Tu
08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Proposed Proposed
ITEM GROUP Unit No. of Days
Start Finished Actual Start Actual Finish Remarks( cause of delay: if any )

1.0 71 85
2.0 72 85
3.0 95 85 3/5/2018 5/29/2018 3/6/2018
4.0 23 85 3/5/2018 5/29/2018 3/6/2018
5.0 34 85 3/5/2018 5/29/2018 3/6/2018
6.0 35 85 3/5/2018 5/29/2018 3/6/2018
7.0 Bustamante 64 85 3/8/2018 6/1/2018
8.0 Bustamante 62 85 3/8/2018 6/1/2018
9.0 Bustamante 66 85 3/8/2018 6/1/2018
10.0 Bustamante 81 85 3/8/2018 6/1/2018
11.0 Fiñones 124 85 3/22/2018 6/15/2018
12.0 Fiñones 125 85 3/14/2018 6/7/2018 3/14/2018
13.0 Fiñones 127 85 3/14/2018 6/7/2018 3/14/2018
14.0 99 3/28/2018
15.0 Delio 24 3/28/2018
16.0 Jessie 101 3/28/2018
17.0 63 3/28/2018
18.0 31 3/28/2018
19.0 Panoy 30 35 3/19/2018 4/23/2018
20.0 Mogan 68 30 3/19/2018 4/18/2018
21.0 7 3/28/2018
22.0 Esok 50 40 3/19/2018 4/28/2018 May 15,2018
23.0 Fredrick 67 30 3/19/2018 4/18/2018
Mogan 25 4/20/2018 5/15/2018
30 5/5/2018 6/4/2018
24.0 Jessie 113 45 3/19/2018 5/3/2018
30 5/3/2018 6/2/2018
25.0 Panoy 96 25 4/2/2018 4/27/2018
30 4/17/2018 5/17/2018
26.0 Delio 91 25 3/22/2018 4/16/2018
30 4/6/2018 5/6/2018
27.0 Noel 41 30 3/22/2018 4/21/2018
Esok 25 4/23/2018 5/18/2018
30 5/8/2018 6/7/2018
28.0 Panoy 18 25 4/29/2018 5/24/2018
30 5/14/2018 6/13/2018
29.0 Delio 51 55 4/17/2018 6/11/2018
30 6/1/2018 7/1/2018
30.0 Fredrick 52 30 4/20/2018 5/20/2018
Mogan 25 5/22/2018 6/16/2018
30 6/6/2018 7/6/2018
31.0 Jessie 60 55 5/4/2018 6/28/2018
30 6/18/2018 7/18/2018
32.0 Noel 78 30 4/23/2018 5/23/2018
Esok 25 5/25/2018 6/19/2018
30 6/19/2018 7/19/2018
33.0 Panoy 80 55 5/25/2018 7/19/2018
30 7/9/2018 8/8/2018
34.0 Fredrick 103 30 5/22/2018 6/21/2018
Esok 25 6/23/2018 7/18/2018
30 7/8/2018 8/7/2018
35.0 Noel 112 30 5/25/2018 6/24/2018
Jessie 25 6/29/2018 7/24/2018
30 7/14/2018 8/13/2018
36.0 Delio 116 55 6/12/2018 8/6/2018
30 7/26/2018 8/25/2018
37.0 Mogan 13 55 6/17/2018 8/11/2018
30 8/1/2018 8/31/2018
38.0 Fredrick 53 30 6/23/2018 7/23/2018
Esok 25 7/25/2018 8/19/2018
30 8/9/2018 9/8/2018
39.0 Noel 126 30 6/26/2018 7/26/2018
Panoy 25 7/28/2018 8/22/2018
30 8/12/2018 9/11/2018
40.0 Fredrick 93 30 7/25/2018 8/24/2018
Esok 25 8/26/2018 9/20/2018
30 9/10/2018 10/10/2018
41.0 Jessie 108 55 7/25/2018 9/18/2018
30 9/8/2018 10/8/2018
42.0 Noel 58 30 7/28/2018 8/27/2018
Panoy 25 8/29/2018 9/23/2018
30 9/13/2018 10/13/2018
43.0 Delio 16 55 8/7/2018 10/1/2018
30 9/21/2018 10/21/2018
44.0 Mogan 55 55 8/12/2018 10/6/2018
30 9/26/2018 10/26/2018
45.0 Fredrick 61 30 8/26/2018 9/25/2018
Esok 25 9/27/2018 10/22/2018
30 10/12/2018 11/11/2018
46.0 Noel 4 30 8/29/2018 9/28/2018
Panoy 25 10/1/2018 10/26/2018
30 10/16/2018 11/15/2018
47.0 Jessie 11 55 9/19/2018 11/13/2018
30 11/3/2018 12/3/2018
48.0 Fredrick 44 30 9/27/2018 10/27/2018
Esok 25 10/29/2018 11/23/2018
30 11/13/2018 12/13/2018
49.0 Noel 106 30 10/1/2018 10/31/2018
Panoy 25 11/2/2018 11/27/2018
30 11/17/2018 12/17/2018
50.0 Delio 119 55 10/2/2018 11/26/2018
30 11/16/2018 12/16/2018
51.0 Mogan 122 55 10/7/2018 12/1/2018
30 11/22/2018 12/22/2018
52.0 Fredrick 43 30 10/29/2018 11/28/2018
25 11/15/2018 12/10/2018
30 12/10/2018 1/9/2019
53.0 Noel 48 30 11/1/2018 12/1/2018
25 12/2/2018 12/27/2018
30 12/17/2018 1/16/2019
54.0 111

55.0 15
56.0 40
57.0 54
58.0 47
59.0 3
60.0 10
61.0 42
62.0 46
63.0 39
64.0 109
65.0 110
66.0 38
67.0 Delio May-2018 2
68.0 28
69.0 29
70.0 Oct-18 32
71.0 37
72.0 45
73.0 56
74.0 65
75.0 69
76.0 98
77.0 102
78.0 107
79.0 114
80.0 115
81.0 117
82.0 118
83.0 Finones April-18 120
84.0 Finones April-18 121
85.0 123
86.0 128
87.0 129
88.0 130
89.0 1
90.0 5
91.0 6
92.0 8
93.0 9
94.0 12
95.0 14
96.0 17
97.0 19
98.0 20
99.0 21
100.0 22
101.0 25
102.0 26
103.0 27
104.0 33
105.0 36
106.0 49
107.0 57
108.0 59
109.0 70
110.0 73
111.0 74
112.0 75
113.0 76
114.0 77
115.0 79
116.0 82
117.0 83
118.0 84
119.0 85
120.0 86
121.0 87
122.0 88
123.0 89
124.0 90
125.0 92
126.0 94
127.0 97
128.0 100
129.0 104
130.0 105
131.0
132.0
133.0
134.0
135.0
136.0
137.0
138.0
139.0
140.0
141.0
142.0
143.0
144.0
Number
STATUS
ITEM GROUP Unit of days Proposed Start Proposed Finished Actual Start Actual Finish Remarks( cause of delay: if any )
finished on-going turned over
1.0 Panoy 95 Aug.3,2018 June 2,2018 Taken over from Castelo
2.0 Delio 23 July 16,2018 May 12,2018 Taken over from Castelo
3.0 Jessie 34 Aug.7,2018 May 28,2018 Taken over from Castelo
4.0 Jessie 35 Aug.30,2018 Taken over from Castelo
5.0 Bustamante 64 June 30,2018 Lack of manpower
6.0 Bustamante 62 June 30,2018 Lack of manpower
7.0 Bustamante 66 June 30,2018 Lack of manpower
8.0 Bustamante 81 June 30,2018 Lack of manpower
9.0 Panoy 93 July 30,2018 June 9,2018 Taken over from Castelo
10.0 Esok 41 85 March 22, 2018 July 18, 2018 April 24, 2018
11.0 Romy 125 65 August 6, 2018 June 2, 2018 Taken over from Finones
12.0 Eric 18 July 6, 2018
13.0 Esok 127 60 July 15, 2018 September 13, 2018 Taken over from Finones
14.0 DRC 51 85 April 18, 2018 July 12, 2018 48% as of last week: due to weather
condition and lack of skilled worker
15.0 DRC 52 85 April 18, 2018 July 12, 2018 48% as of last week: due to weather
condition and lack of skilled worker
16.0 DRC 53 85 April 18, 2018 July 12, 2018 45% as of last week: due to weather
condition and lack of skilled worker
17.0 DRC 60 85 April 18, 2018 July 12, 2018 39% as of last week: due to weather
condition and lack of skilled worker
18.0 Mogan 68 85 August 8, 2018 May 15, 2018
19.0 Panoy 126 59 July 15, 2018 September 12, 2018 June 2, 2018
20.0 Lanuza/Romy 120 85 June 18, 2018 September 11, 2018 June 18, 2018 Taken over from Finones
21.0 Delio 2 85 June 11, 2018 September 4, 2018
22.0 Noel/Delio 58 85 July 2, 2018 September 25, 2018 July 2, 2018
23.0 Mogan 78 55 July 8, 2018 September 1, 2018
24.0 Lanuza/Jessie 80 85 July 20, 2018 October 13, 2018
25.0 Noel/Esok 103 85 August 2, 2018 October 26, 2018
26.0 Mogan 39 85 August 8, 2018 November 1, 2018
27.0 Romy 116 85 August 11, 2018 November 4, 2018
28.0 Delio 13 85 August 25, 2018 November 18, 2018
29.0 Lanuza/Panoy 108 85 August 20, 2018 November 13, 2018
30.0 Jessie 124 55 September 13, 2018 November 7, 2018 Taken over from Finones
31.0 Esok 16 85 September 26, 2018 December 20, 2018
32.0 Noel/Mogan 55 85 September 2, 2018 November 26, 2018
33.0 Lanuza/Romy 61 85 September 20, 2018 December 14, 2018
34.0 Noel/Jessie 4 85 October 2, 2018 December 26, 2018
35.0 Panoy 11 85 October 13, 2018 January 6, 2019
36.0 Delio 44 85 October 18, 2018 January 11, 2019
37.0 Lanuza/mogan 106 85 October 20, 2018 January 13, 2019
38.0 Noel/Romy 119 85 November 3, 2018 January 27, 2019
39.0 Esok 122 85 November 20, 2018 February 13, 2019
40.0 Jessie 43 85 November 26, 2018 February 19, 2019
41.0 Lanuza/Panoy 48 85 November 20, 2018 February 13, 2019
42.0 Delio 111 85 December 11, 2018 March 6, 2019
43.0 Mogan 15 85 December 13, 2018 March 8, 2019
44.0 Noel/Romy 40 85 December 3, 2018 February 26, 2019
45.0 Lanuza/Esok 54 85 December 20, 2018 March 15, 2019
46.0 Noel/Jessie 47 85 January 3, 2019 March 29, 2019
47.0 Panoy 3 85 January 14, 2019 April 9, 2019
48.0 Romy 10 85 January 26, 2019 April 21, 2019
49.0 Lanuza/Delio 42 85 January 20, 2019 April 15, 2019
50.0 Mogan 46 85 February 8, 2019 May 4, 2019
51.0 Esok 112 85 February 15, 2019 May 11, 2019
52.0 Noel/Jessie 109 85 February 3, 2019 April 29, 2019
53.0 Lanuza/Panoy 110 85 February 20, 2019 May 16, 2019
54.0 Noel/Delio 38 85 March 3, 2019 May 27, 2019
55.0 Romy 28 85 March 21, 2019 June 14, 2019
56.0 Jessie 29 85 March 29, 2019 June 22, 2019
57.0 Lanuza/mogan 32 85 March 20, 2019 June 13, 2019
58.0 Noel/Esok 37 85 April 3, 2019 June 27, 2019
59.0 Lanuza/Panoy 45 85 April 20, 2019 July 14, 2019
60.0 Noel/Delio 56 85 May 3, 2019 July 27, 2019
61.0 Mogan 65 85 May 13, 2019 August 6, 2019
62.0 Romy 69 85 May 14, 2019 August 7, 2019
63.0 Lanuza/Jessie 98 85 May 20, 2019 August 13, 2019
64.0 Esok 102 85 May 27, 2019 August 20, 2019
65.0 Noel/Delio 107 85 June 3, 2019 August 27, 2019
66.0 Panoy 114 85 June 14, 2019 September 7, 2019
67.0 Lanuza/Mogan 115 85 June 20, 2019 September 13, 2019
68.0 Noel/Esok 117 85 July 3, 2019 September 26, 2019
69.0 Romy 118 85 July 7, 2019 September 30, 2019
70.0 Jessie 121 85 July 14, 2019 October 7, 2019 Taken over from Finones
71.0 Lanuza/Delio 123 85 July 20, 2019 October 13, 2019
72.0 Panoy 128 85 August 7, 2019 October 31, 2019
73.0 Noel/Mogan 129 85 August 3, 2019 October 27, 2019
74.0 Esok 130 85 August 26, 2019 November 19, 2019
75.0 1
76.0 5
77.0 6
78.0 8
79.0 9
80.0 12
81.0 14
82.0 17
83.0 19
84.0 20
85.0 21
86.0 22
87.0 25
88.0 26
89.0 27
90.0 33
91.0 36
92.0 49
93.0 57
94.0 59
95.0 70
96.0 73
97.0 74
98.0 75
99.0 76
100.0 77
101.0 79
102.0 82
103.0 83
104.0 84
105.0 85
106.0 86
107.0 87
108.0 88
109.0 89
110.0 90
111.0 92
112.0 94
113.0 97
114.0 100
115.0 104
116.0 105
117.0 71
118.0 72
119.0 24
120.0 99
121.0 101
122.0 63
123.0 31
124.0 30
125.0 67
126.0 113
127.0 50
128.0 96
129.0 91
130.0 7

Project Start : Apr-16 Scope of works : Perimeter Fence, Road, Drainage


House Units Start: Jul-16
Proposed Finished: Nov-19
Total Months Accumulated : 40 months
Average Units Finished : 3.25 units per month
Problems Encountered:
Prepared by:

Engr. Walter Garcia