Concepcion Uno-Roof Deck
Concepcion Uno-Roof Deck
Name of the project : PROPOSED MULTI-PURPOSE TWO STOREY BUILDING,CHAMPACA II HOA INC.
Name of the Procuring Entity Location of the project : CHAMPACA ST., BRGY. FORTUNE, MARIKINA CITY
DETAILED ESTIMATE
Item Description Quantity Unit Unit Cost Direct Cost OCM(12%) Profit (13%) Total Mark-Up VAT(12% of B,C,D) Total Indirect Total Cost
No.
I. Mobilization 1 lot 30,000.00 30,000.00 3,600.00 3,900.00 7,500.00 1,875.00 9,375.00 39,375.00
II. General Requirements 1 lot 555,023.34 555,023.34 66,602.80 72,153.03 138,755.84 34,688.96 173,444.79 728,468.13
III. Preparation Works 1 lot 42,131.69 42,131.69 5,055.80 5,477.12 10,532.92 2,633.23 13,166.15 55,297.84
IV. Civil Works 1 lot 1,732,482.77 1,732,482.77 207,897.93 225,222.76 433,120.69 108,280.17 541,400.87 2,273,883.64
V. Architectural Works 1 lot 2,257,131.43 2,257,131.43 270,855.77 293,427.09 564,282.86 141,070.71 705,353.57 2,962,485.00
VI. Metal Works 1 lot 759,726.43 759,726.43 91,167.17 98,764.44 189,931.61 47,482.90 237,414.51 997,140.94
VII. Plumbing Works 1 lot 239,992.83 239,992.83 28,799.14 31,199.07 59,998.21 14,999.55 74,997.76 314,990.59
VIII. Electrical Works 1 lot 305,279.10 305,279.10 36,633.49 39,686.28 76,319.78 19,079.94 95,399.72 400,678.82
1,480,441.90 74,022.09
Submitted by: MA. CRISTINA B. SANTOS
(Print Name & Signature)
Designation: President
Date: June 20, 2018
Name of the Procuring Entity
DETAILED E
Item Description Quantity Unit Unit Cost ESTIMATED
No. Direct Cost
(1) (2) (3) (4) (5)
DETAILED ESTIMATE
MARK-UPS IN PERCENT Total Mark-Up VAT
OCM(15%) Profit (10%) % VALUE 5%[(5)+(6)+(7)]
(6) (7) (8) (9) (10)
TOTAL TOTAL
DIRECT COST COST
(11) (12)
9,375.00 39,375.00
62,305.47 261,682.97
7,476.33 31,400.60
133,327.93 559,977.30
239,425.05 1,005,585.22
96,627.77 405,836.62
58,610.98 246,166.11
65,625.00 275,625.00
672,773.53 2,825,648.82
Contract Reference Number
Name of the project
Name of the Procuring Entity
Location of the project
Standard Form Number: SF-INFR-05
BILL OF QUANTITIES
Item Description Quantity Unit Unit Cost VAT TOTAL TOTAL Amount in Words
No. DIRECT COST COST
I. Mobilization 1 lot 30,000.00 1,875.00 9,375.00 39,375.00 Thirty Nine Thousand Three Hundred Seventy Five
II. General Requirements 1 lot 199,377.50 12,461.09 62,305.47 261,682.97 Two Hundred Sixty One Thousand Six Hundred Eighty Two and 97/100
III. Preparation Works 1 lot 23,924.27 1,495.27 7,476.33 31,400.60 Thirty One Thousand Four Hundred and 60/100
IV. Civil Works 1 lot 426,649.37 26,665.59 133,327.93 559,977.30 Five Hundred Fifty Nine Thousand Nine Hundred Seventy Seven and 30/100
V. Architectural Works 1 lot 766,160.17 47,885.01 239,425.05 1,005,585.22 One Million Five Thousand Five Hundred Eighty Five and 22/100
VI. Metal Works 1 lot 309,208.85 19,325.55 96,627.77 405,836.62 Four Hundred Five Thousand Eight Hundred Thirty Six and 62/100
VII. Plumbing Works 1 lot 187,555.13 11,722.20 58,610.98 246,166.11 Two Hundred Forty Six Thousand One Hundred Sixty Six and 11/100
VIII. Electrical Works 1 lot 210,000.00 13,125.00 65,625.00 275,625.00 Two Hundred Seventy Five Thousand Six Hundred Twenty Five
Two Million Eight Hundred Twenty Five Thousand Six Hundred Forty Eight and 82/10
Total 2,152,875.29 134,554.71 672,773.53 2,825,648.82
Amount in Words
ght Hundred Twenty Five Thousand Six Hundred Forty Eight and 82/100