Professional Documents
Culture Documents
Construction Service Project Scheduling Analysis Using Critical Path Method (CPM), Project Evaluation and Review Technique (PERT)
Construction Service Project Scheduling Analysis Using Critical Path Method (CPM), Project Evaluation and Review Technique (PERT)
ISSN No:-2456-2165
Abstract:- The success or failure of a project is largely To overcome this problem, the researcher makes a
determined by the planning and control of the project. study using the Critical Path Network (CPM) and Project
The failure of project implementation was due to lack of Evaluation and Review Technique (PERT) Methods. By
planning and lack of ineffective control so that project using the CPM and PERT methods, it can be seen in more
activities became inefficient. This resulted in delays, detail about the time difference between the initial
reduced quality of work, and unexpected costs of conditions and the repair conditions, when the initial
implementation. Problems in this research object is a conditions often experience delays in processing time from
delay in completing a gondola project because there are preparation to completion and result in poor quality [5].
several obstacles or problems that occur. Optimization of Therefore, it must be noted which work should get more
working time is quite important for companies in attention because if the work is delayed it will affect the
working on projects, because in this work time efficiency results of other work [6]. This research will answer the
is needed because the gondola is needed by the client. question of how to determine the optimal time for project
The implementation of the project requires optimal completion and how to determine the critical path to get
project planning using the CPM (Critical Path Method) more attention compared to other activities on the
and PERT methods. With the CPM method, 13 critical contrusction service project.
activities were obtained, with total duration of 55 days
was also applied to the Gantt Chart. And with the PERT II. METHODS
method (Program Evaluation and Review Technique)
obtained 13 critical activities, and a total duration of 53 The situation faced here is that there is a difference
days with a probability of project completion is 86.65%. between the project implementation time and the
predetermined project plan time. The project planning time
Keywords:- Project Management, CPM,PERT, Activities is usually shorter than the project implementation time [7].
The analysis technique used in this research is the CPM
I. INTRODUCTION (Critical Path Method) and PERT (Project Evaluation and
Review Technique) approaches.
The construction of a construction project has
objective goals that must be in line with strategic goals, thus A. Stage 1 : CPM analysis
the performance of a project will affect its achievement [1] . At this stage a network analysis is carried out using the
Projects generally have a deadline, which must be completed CPM method. To be able to set up a CPM network, research
before or at the agreed time. However, in reality in the field, requires several steps [8]. The steps in compiling a CPM
there are still many project completion times that are network are:
delayed or not completed on schedule [2]. Projects are Review and identify the project scope, describe it, break
dynamic, non-routine, multi-activity with varying intensity, it down into activities or groups of activities that are
short cycles, have starting and ending points, and limited project components.
funds [3]. According to [4] in a project it is necessary to Rearrange the components in point 1, into links in the
confirm the relationship between activities to plan a project. order according to the dependency logic.
CV. KCT collaborates with PT. GKL in working on gondola Provide an estimated timeframe for each of the activities
projects, which is usually when PT. GKL won the project resulting from the breakdown of the project scope.
tender, entrusted to CV. KCT. The problem in this company Identify the critical path (critical path) and float on the
is an internal problem, namely the implementation of the network.
gondola project that was not completed on time.During the
implementation of the gondola project in 2019-2020 there Perform forward and backward calculations. From the
were 5 projects that have been completed, but 3 of the 5 two calculations, it is identified which activities are on the
projects have experienced delays / delays. critical path.
5
3
3
5
5
13 8
of activities that are project components. This H1 H2
F 3 5 3 5
arrangement is done based on experience and or data in 3
3
10
5
5 3
6
5 3
4
5
G4 I
the project in the past [9].The details of its activities are A B C D E F1 F2
5
5
10
10 G6 H3
5
5
10
10
3 3 4 7 5 5 3
0 1 0 1 0 1 0 1 1 3 3
as shown in Table 1 below : 0
5
1 0
2
1 0
2
1 0
5
1 1
1
3 4
8
5
5
5
4
10
10
G5
3
3
5 3
2
5
5 10
5 10
F3 6
3 4
Type of work 7
A 5 3 9 5
3 5 3 5
13 8
Measurement of setting 1
G1 3 H1 H2
plate & anchor plate 15
3
F
25
5
42
3
48
5
48
3
52
5
10 6 4
Drilling and planting of - 27
G4
34 52
I
55
G2 9 5 10 5 10
angkur 0
A
5 5
B
7 7
C
9 9
D
14 14
E
15 15
F1
23 23
F2
27
7
39
G6
42 48
H3
50 3
0 1 0 1 0 1 0 1 1 3 4 5 5 10 3 5 3 5
5 10
F3 6
4
7
22
44
38
44
8
46
52
following is the Activity On Node (AON) network diagram
F H1
48
H2
52
for the project's critical path in Figure 5:
15 25 42 48
21 31 42 48 48 52
10 6 4
G4 I
27 34 52 55 G H
25 38 38 46
A B C D E F1 F2 32 39 G6 H3 52 55
15 15 23 7 42 50 3 29 42 42 50
0 5 5 7 7 9 9 14 14 23 27 39 48
13 8
0 5 5 7 7 9 9 14 14 15 20 28 28 32 39 42 50 52
5 2 2 5 1 8 4 G5 3 2
27 33
F H1 H2
15 25 40 46 46 50
33 39
F3 6
15 22 19 29 40 46 46 50
10 6 4
15 22 G4 I
7 27 34 50 53
A B C D E F1 F2 30 37 G6 H3 50 53
15 15 23 7 40 48 3
0 5 5 7 7 9 9 14 14 23 27 37 46
G1 G2 G3
22 25 25 34 34 39 14 18 26 37 40 48 50
0 5 5 7 7 9 9 14 15 26 30
5 2 2 5 1 8 4 G5 3 2
22 25 25 34 34 39 27 33
3 9 5
31 37
F3 6
Fig 3:- The countdown network diagram Activity On Node 15
15
21
21
6
(AON)
G1 G2 G3
21 24 24 32 32 37
21 24 24 32 32 37
31
13
44 44
8
52
From the figures above, the figure is 0.8665 in table Z
15
F
25 42
H1
48 48
H2
52 normal distribution, then the possibility of completing the
21
10
31
27
G4
34
42
6
48 48
4
52
52
I
55
project in 53 days is 86.65%. This means that the completion
0
A
5 5
B
7 7
C
9 9
D
14 14
E
15 15
F1
23 23
F2
27
32
7
39
39
G6
42 48
H3
50
52
3
55 of the project analyzed using the CPM method has a great
0
5
5 5
2
7 7
2
9 9
5
14 14
1
15 20
8
28 28
4
32
27
G5
33
39
3
42 50
2
52
chance of being completed with the duration given by the
15
F3
22
33
6
39
company.
15 22
7
22
G1
25 25
G2
34 34
G3
39 3. Results of Comparative Analysis of CPM and PERT.
22
3
25 25
9
34 34
5
39
In this research, the methods used for scheduling are
Fig 4:- AON Critical Path Network Diagram CPM and PERT. The comparison of the working time of the
gondola project with these two methods can be seen in the
2. PERT (Project Evaluation Review Technique) Method. table 2 and figure 6 below:
Like the CPM method, PERT also uses an arrow chart to
illustrate the project trajectory. In terms of understanding
and calculation, critical activity is the same, the critical Description CPM PERT Difference
path or float in PERT is known as slack. The difference
Time (days) 55 53 2
between CPM and PERT which is clearly visible is in the
Table 2:- Comparison of Time Using the CPM and PERT
estimation of activity duration [12]. If in CPM the time is
Methods
estimated with certainty (deterministically), then in
PERT there are 3 time estimates, namely:
By using PERT network planning to improve the
a. Optimistic time (To), namely the possibility that
project work system, each related section can understand the
activities can be completed in a shorter time.
process flow in detail, know which activities can be carried
b. The most frequent occurrence (Tm), namely the
out in parallel / concurrently, and prioritize activities that are
estimated time that usually occurs under normal
considered critical so that they do not affect the overall
conditions.
project delay. When compared with the results of the
c. Time pessimistic (Tp), which is the possibility that the
completion of this gondola project, which was completed in
activity can be completed in a longer time.
113 days, with the improvement of the work system and the
use of the PERT method, this time efficiency was 60 days
Referring to the information above, time estimation
faster.By using the PERT method, a Gantt Chart for project
data for optimistic time and pessimistic time are needed.
implementation can be made.
This data was obtained through interviews and discussions
with field parties. Based on the calculation of slack using the
PERT method, 13 critical trajectories were found, namely:
A, B, C, D, E, F3, G1, G2, G3, G6, H1, H2, and I. day. The