Detailed Estimation

S.No. Description No. Length (m) Breadth (m) Height (m) Quantity Explanatory Notes

1 EARTHWORK IN EXCAVATION

a) Foundation Trenches
Center Line Method 29.6
L Wall Method 18.2
S Wall Method 11.4
Long walls 2 10 0.9 0.9 10.00 = 9.1 + 2 X 80/2
Short walls 2 3 0.9 0.9 3.00= 3.90 -2 X 80/2
T.L. 29 0.9 0.9 31,O5
b) Steps 1 2,6 0.8 0.15 0.31 .80= 0.9 - 0.15 (trench)
Total = 31.36 cu.m.

2 EARTHWORK IN FILLING

a) Foundation Trenches 1/3 of excavation approx. = 6.27


b) For Plinth 1 3.9 3.5 0.6 6.62 0.60 = 0.8 - 0.20
Total = 12.89 cu.m. (L.C. and soling)

3 CEMENT CONCRETE ( 1 : 3 : 6 )

a) Foundation Trenches
Center Line Method
L & S Wall Method
Long Walls 2 10 0.9 0.3
Note that the total length is
Short Walls 2 3 0.9 0.3
same by any method
T.L. 29 0.9 0.3 3.44
b) Steps 1 2.6 0.8 0.1 0.11
Total = 3.55 cu.m.

4 BRICKWORK IN CEMENT MORTAR

(1:4) in foundation and plinth


a) Walls
Center Line Method 1 33.8 0.4 1.4
L & S Wall Method
Long Walls 2 5.5 0.4 1.4
Short Walls 2 3.9 0.4 1.4
T.L. 9.4 0.4 1.4 9.18
b) Steps 1 1.2 0.6 0.6 0.43 0.6 = 1/3 (0.9 + 0.3)
Total = 9.61 cu.m.

5 2.5 cm THICK D. P. C. ( 1 : 2 : 4 )

Center Line Method 1 33.8 0.3 4.92


L & S Wall Method
Long Walls 2 9.4 0.3 5.64 9.40=9.1+ 2 x .30/2
Short Walls 3 3.6 0.3 3.24 3.6=2.9-2 x .30/2
Deduction for -
Door sill 1 1.2 0.3 1.08
Total = 8 sq.m.

6 BRICKWORK IN SUPERSTRUCTURE

a) Walls
Center Line Method 1 33.8 0.3 3.1
L & S Wall Method
Long Walls 2 9.4 0.3 3.6 20.3 9.4+9.1+2 x .3/2
Short Walls 3 3.6 0.3 3.6 11.67 3.6 = 3.90 - 2 X 0.30/2
T.L. 9.4 0.3 3.1 15.25
b) Parapet
Long sides ( out to out ) 2 9.4 - 0.7 8.4
Short sides ( in to in ) 2 6 - 0.7 9.4
29.6 is the total length of the
Deduction for - superstructure wall. No
Door Opening 3 1.2 0.3 2.1 2.27 deduction for ends of lintel and
vent holes.
R. C. Lintel 1 1.2 0.3 0.15 -0.05
Net Total = 15.45 cu.m.

7 R. C. C. WORK ( excluding reinforcement and shuttering )

a) Roof Slab 1 9.4 6.1 0.12 2.99


b) Lintel 1 1.8 0.3 0.15 0.08 Bearing of lintel is 30 cm
Total = 3.07 cu.m.

8 SHUTTERING AND CENTERING

a) Roof Bottom 1 3 4.8 24.96


b) Edges 1 20 0.12 2.4 No deduction for the area of
walls to minimise the extra
c) Lintel (sides) 2 1.8 0.15 0.54
charge for cantilever shuttering
d) Lintel Bottom 1 1.2 0.3 0.36 for cornica.
Total = 28.26 sq.m.

9 LIME TERRACING
The inserted portions have been
a) 7.5 cm thick Lime Terracing 1 9.4 6.1 45.98 sq.m. considered as if brickwork in
TOTAL 181 X 45.98 = 8,332

10 WOOD AND STEEL WORK DOORS AND VENTS

a) 15 cm X 8 cm Vent Holes 3 Nos.


b) Sal woodwork doorframe 3 5.43 0.1 0.08 0.132 cu.m.
Door frames are out still,2 vents
with intersection in floor
2x2.14+1.2=5.8 / 5.20=2(1.10+1.5)
Sal woodwork windows 8 5.2 0.1 0.08 0.333 cu.m.
c) Battened Door 25mm thick 1 1.07 1.97 2.108 sq.m.
d) Steel grafted(50
M.S. Clamps door
mm X 6mm and 40cm 1 1.2 2.1 2.52 sq.m.
e) long) 2 X 3 = 6 @ 1/2 kg each 3 kg
3 % to 0.6 % and
0.8 / 100(0.47 +
f) Steel bars 8.50 0.6 per cu.m 2 cu.m (c) 0.8% vol. & 0.6% for order
g) 35mm thick indian teak door 3 1.07 - 2.03 6.52
indian teak window panel shutters 8 0.97 - 1.37 10.63
h) steelwork (window gratings) 8x9 1.5
i) 40x12 mm stiffer plates 8 0.94
j) clamps 50x6 mm (windows) 32

11 12 mm THICK CEMENT PLASTER (1 : 2)

a) For steps -
Riser 1 1.2 0.8 0.96
Tread 3 1.2 1.08 1.08
Sides 2 0.6 0.72 0.72 0.60 = 1/2(0.3 + 0.9)
Total = 2.76 sq.m.

12 6 mm THICK CEMENT PLASTER (1 : 4)

a) Ceiling 1 4 3.6 14.4


b) Cornice (both faces)
Long sides 2X2 5.2 0.3 6.24 5.2 out to out
Short sides 2X2 4.2 0.3 5.04 4.2 in to in
c) Cornice (edges)
Long sides 2 5.2 0.12
Short sides 2 4.8 0.12
Total = 28.08 sq.m.
d) flooring 1 4 3.6 14.4
13 10 cm THICK LIME CONCRETE

(1(1/2) : 2 : 7) floor over brick flat soling


rooms bigger 1 4.4 3.5 15.4
rooms smaller 1 3.9 3.5 13.65 4.40=4.50-2x
rooms bigger 1 8.7 1.5 13.05 0.05 (offset)
total 42.1 8.70=9.50(outer to
sqm 4.40=4.50-2x
14 2.5 cm ARTIFICIAL STONE

( 1: 2 : 4) flooring
room bigger 1 4.5 3.6 16.2
room smaller 1 4 3.6 14.4
verandah 1 9.5 1.85 17.58
deduction of pillars 5 0.2 0.2 0.2
total 47.08 sqm

15 WHITE WASHING AND PAINTING


white washing three coats to outside same as item
and ceiling numbers 16(b) 18
two coats colour washover a coat of 111.56 + 54.4
same as item= 165.96 sqm
white wash numbers 16(a) 160.08 sqm

painting to wood work two coat


bothside
a door ( pannels ) 3x2 1.2 2.1 19.66 Multiplying Factor for each side =
x1.3 1.3 times including frame ( SP : 27 -
b windows (*) 8x2 1.1 1.5 34.3 0
x1.3 total 53.98
sqm