OFFICE OF THE MUNICIPAL CORPORATION OKARA

(PCP PROJECT Phase-II, 2020-2021)

BID SCHEDULE

NAME OF REHABILITATION OF MUNICIPAL SERVICES INFRASTRUCTURE


SCHEME (PHASE II) IN OKARA CITY

District Development Committee Okara Vides No. 1(5)/ DDC/ Minutes/


A.A by the :-
2021/38 Dated: 19-01-2021 For Rs.31.153 Million
Approx. Cost:- Rs. 31.153 Million Earnest Money:- Rs. 1.557 Million
Time Limit:- 06 Month
A-
STANDARDIZE MRS.BI-ANNUAL PERIOD (1st January 2021 To 30th June 2021)
ITEMS

Rehabilitation of Sewerage Work (PCP) Phase II


MRS-1st Rate of Contractor
item
2021 Description Unit Quantity
No. Unit Rate In Words Amount
Ref.
Dismantling brick or
1 4/29 flagged flooring without Sft 1410
concrete foundation.
Dismantling and removing
road pavement, etc.,
including screening and
2 4/46 Cft 45525
stacking of byproducts
upto one chain lead
(30 meter).
Dismentling cement
3 4/19(c ) concrete 1:2:4 plain. etc Cft 1980
complete in all respect.
Earthwork excavation in
open cutting for sewers
and manholes as shown in
drawings including
shuttering and timbering,
dressing to correct section
4
and dimensions according
to templates and levels,
and removing surface
water, in all types of soil
except shingle, gravel and
rock:-
0 ft. to 7.0 ft. (0 to 2.10 m)
i 3/42(i) Cft 221406
depth
7-01 ft. to 15.0 ft. (2.15 to
ii 3/42(ii) Cft 52563
4.5 m) depth
MRS-1st Rate of Contractor
item
2021 Description Unit Quantity
No.
Ref. Unit Rate In Words Amount

Contractor
above 15.0 ft (4.5 m)
iii 3/42(iii) depth Cft 2192

Disjoining R.C.C. pipes


inside the trench and
dismantling and removing
5 4/31(a) Rft 6080
the pipes from the trench
and stacking them
outside:-
Supply and filling sand
6 7/30 under floor or plugging in Cft 1827
wells,
Providing and laying of
Rate bujer /base course of
7 Cft 35533
Analysis crush stone etc complete
in all respect
Providing and laying
R.C.C. pipe sewers,
moulded with cement
concrete 1:1½:3
conforming to ASTM
Specification C-76-79,
Class IV, Wall B, including
8 carriage of pipes from
factory to site of work,
lowering in trenches to
correct alignment and
grade, jointing with
rubber ring, cutting pipes
where necessary, testing,
etc. complete:-
i 21/5(vii) 760 mm (30") dia Rft 150
ii 21/5(v) 610 mm (24") i/d Rft 4300
iii 21/5(ii) 460mm (18") i/d Rft 2100
iv 21/5(ii) 310 mm (12") i/d Rft 755
Construction of manhole
Rate
9 as per specification etc
Analysis
complete in all respect.
i 4.5 depth No 13
5` depth
ii No 9
6` depth
iii No 13
7` depth
iv No 5

iv 8` depth No 18
MRS-1st Rate of Contractor
item
2021 Description Unit Quantity
No. Unit Rate In Words Amount
Ref.
9` depth
v No 14
10` depth
vi No 13

vii 11` depth No 2


Contractor
making connection from
Rate
10 repair line to existing line No 28
Analysis
etc complete in all respect.
Rehandling of earthwork:
11 3/13(a) Lead upto a single throw of Cft 219175
Kassi, phaorah or shovel
Providing and laying sub-
base course of brick
aggregate, including
12 18/2 compacting of sub-base Cft 436
course material to required
depth, camber, grade &
density.
Providing and laying sub-
base course of stone
product of approved quality
and grade, including placing,
mixing, spreading and
compaction of sub-base
Rate material to required depth,
13 camber, grade to achieve
Cft 15175
Analysis
100% maximum modified
AASHO dry density,
including carriage of all
material to site of work
except gravel and.
aggregate.
Providing and laying sub-
base course of stone
product of approved quality
and grade, including placing,
mixing, spreading and
compaction of sub-base
Rate material to required depth,
14 camber, grade to achieve
Cft 10983
Analysis
100% maximum modified
AASHO dry density,
including carriage of all
material to site of work
except gravel and.
aggregate.
Providing and laying Tuff
pavers,having7000PSI,crushi
ngstrengthofapprovedmanu
facturer,over2"to3"sandcus
10/43
15 hioni/c groutingwithsand in
(b) joints i/c finishing to require
slope complete in all
respect. (50% Grey / 50%
Coloured) 60-mm thick
Labour Rate For Laying Tuff
i Sft 846
Tile
MRS-1st Rate of Contractor
item
2021 Description Unit Quantity
No. Unit Rate In Words Amount
Ref.
ii P/Laying Tuff Tile Sft 564
Providing and laying plant
18/10 premixed bituminous
16 Sft 30350
(vii) carpet, including
compaction and finishing
Contractor
to required camber, grade
and density. With 6%
Bitumen and 2" thick
Cement concrete plain
including placing,
compacting, finishing and
17 6/5(f) Cft 330
curing complete(including
screening and washing of
stone aggregate) Ratio 1:2:4
Construction of
Rate
18 chamberies 2x4 etc No 3
Analysis
complete in all respect
Removal of malba from
Rate
19 site lead upto three mile Cft 58039
Analysis
etc complete in all respect
unexpected damage
services like (Sui Gas,
20 water supply line, ptcl Job 1
,optical fiber cables etc )
Required if any
Rehabilitation of suction pipe at Disposal 2/4L
Providing, laying, cutting,
jointing, testing and
disinfecting high density,
21 23/42 (d) polyethyene pipe Rft 8
(HDPE.100) working
pressure pipe in trench etc
complete in all respect
Replacement of bend 18"
22 NS dia with HDPE etc No 1
complete in all respect.
Labour charges for fixing
of pipe and bend with
23 NS Job 1
special arrangements
(30' to 35' deep in well)

Contractor
Contractor