PT PEMBANGKITAN JAWA BALI SERVICES No.

Doc :
SIAP INTEGRATED MANAGEMENT SYSTEM No. Revisi :
PLTD SUPPA Tgl Berlaku :
TIME LINE PELAKSAAN KEKURANGAN PENDING ITEM RE SLO Halaman :
120.00%

No Date Rencana Realisasi


100.00%
1 23 February 2021 0.00% 0.00%
2 24 February 2021 10.00% 25.42%
80.00% 3 25 February 2021 20.00% 33.33%
4 26 February 2021 30.00% 50.00%
PROSENTASE

5 27 February 2021 40.00% 59.72%


60.00% Rencana
6 28 February 2021 50.00%
Realisasi
7 01 March 2021 60.00%
40.00% 8 02 March 2021 70.00%
9 03 March 2021 80.00%
10 04 March 2021 90.00%
20.00%
11 05 March 2021 100.00%
TOTAL PROGRES 40.00% 59.72%
0.00%
1 2 3 4 5 6 7 8 9 10 11

Date Hari ke Note


HARI KE 4 (Empat)
PUKUL 16.00 WITA

PROGRESS LEADING 19.72%