Professional Documents
Culture Documents
Detailed Project Report: Sunkhani - Kanpa Section of Sunkhani - Sangwa - Jiri Road
Detailed Project Report: Sunkhani - Kanpa Section of Sunkhani - Sangwa - Jiri Road
Detailed Project Report: Sunkhani - Kanpa Section of Sunkhani - Sangwa - Jiri Road
August 2016
Prepared by:
Gaurav Integrated Development Associates Nepal (P) Ltd/NEST (P) Ltd/Jaarsa Engineering
Consultancy (P) Ltd. JV, the Consultant would like to extend its gratitude to Decentralized Rural
Infrastructure and Livelihood Project – Additional Financing (DRILP-AF), Central Implementation
Support Consultant (CISC), Ekantakuna, Lalitpur, Nepal for providing an opportunity of Preparation
of Detailed Project Reports for Rehabilitation and Reconstruction of Sunkhani - Kanpa Section of
Sunkhani – Sangwa – Jiri Road, Dolakha. Also, we would like to acknowledege all the members of
CISC for their kind co-operation.
We would further like to acknowledge DDG, SDE of DoLIDAR, DTO, personnel of DDC, CISC
team, Engineer, Sub Engineer, the local people of the project area and all the individuals involved in
with this project for their kind co-operation and help at every step during the preparation of this
report.
Last but not least, team would like to thank technical and supporting staffs of Gaurav Integrated
Development Associates Nepal (P) Ltd/NEST (P) Ltd/Jaarsa Engineering Consultancy (P) Ltd. JV
who have done remarkable assistance to complete the assignment.
The detailed engineering survey, design and cost estimate for rehabilitation and reconstruction of
Sunkhani - Kanpa Section of Sunkhani - Sangwa - Jiri Road has been prepared for ADB funded
Emergency Earthquake Assistance Project (ADB L0an 3260-NEP) following the principles of build back
better. The road traverses through Sunkani, Lapilang, Lamidanda and Baware VDCs of Dolakha District.
The length of the Sunkhani - Kanpa road section proposed for rehabilitation and reconstruction to gravel
standard is 27.373 km.
The existing road starts from Sisagolai, Sunkhani VDC-9 and ends to Damba Khola at Kanpa of Baware
VDC-1, passing via Lapilang and Lamidanda VDCs. Throughout the length the existing road, surface is
earthen and condition is moderate and undulated. Major landslides were observed in chainage 4+630 to
4+780. Other small landslides in the existing alignment are in chainages 1+950, 2+150, 7+660, 24+300.
In chainages 3+250 to 3+400, 6+560 to 6+645, 7+363 to7+750, 9+782 to 9+830 and 22+080 to
22+220, the longitudinal grade of existing road is greater than 12%. The existing road width varies
between 3m to 5m. Narrow sections have minimum road width of 3 m.
During the design, existing road alignment has been followed as far as possible; however the alignment
has been shifted in some places especially at loops to maintain the geometric design parameters and at
problematic areas of steep gradient. Nepal Rural Road Standard (2055) 2nd revision, December 2014 has
been adopted for the design. The maximum and minimum grade adopted in the design is 12% and 0.5%
respectively. The road has been designed to gravel standard.
For pavement design, CBR value is calculated from results of DCP test and from this the required
thickness of sub-base has been calculated. From the results of DCP test and judging economic in gravel
road, the uniform thickness of sub base 175 mm has been adopted. Capping layer of 100 mm has been
provided over sub base in sections where sub base thickness required is higher than 175 mm from result
of DCP test and pavement design. Bio-engineering works have been proposed in places prone to
landslides and erosions. For spoil management, the proper locations along the site have been identified.
The draft design was reviewed during joint field verification by team of Consultant and CISC. The
comments and feedback received by the consultants have been incorporated in preparing the final design.
After the discussion with the CISC team, for the sections having gradient higher than 7%, cobble
pavement has been proposed in the design. On this consideration the total length which requires cobble
pavement is 12.08 km.
The cost estimates are based on applicable DoLIDAR norms. In cases where DoLIDAR norms are not
available, DOR norms have been used. The unit item rates for each item have been calculated on the
basis of approved district rate for fiscal year 2072/73. While calculating item rates, it is assumed that a
qualified contractor will undertake construction following mechanized approach for road works.
The cost estimate for the road has been prepared in two packages. For first package Ch: 0+000 – 16+000,
the cost of civil works has been estimated to be Rs. 207,440,626.71. The total cost for rehabilitation and
reconstruction including contingencies consisting of small miscellaneous expenses, work charge staff and
VAT as per GON rules is calculated to be Rs. 261,375,189.66. The per km cost excluding VAT, dayworks
and contingencies is Rs. 14,650,494.26. For second package Ch: 16+000 – 27+373.27, the cost of civil
works has been estimated to be Rs. 157,505,597.66. The total cost for rehabilitation and reconstruction to
gravel standard including contingencies consisting of small miscellaneous expenses, work charge staff and
VAT as per GON rules is calculated to be Rs. 198,457,053.06. The per km cost excluding VAT, dayworks
and contingencies is Rs. 15,649,461.48. It is envisaged that the construction works can be completed
within 18 months from award of contract and estimates are based on it. Provision of physical contingency
10% has been indicated in the cost estimate.
TABLE OF CONTENTS
1. INTRODUCTION ...............................................................................................................12
1.1. Project Background ....................................................................................................................................... 12
1.2. Project District and Proposed Road ........................................................................................................... 12
1.3. Scope of Works .............................................................................................................................................. 12
2. ENGINEERING SURVEY AND STUDY ..........................................................................14
2.1. Desk Study ...................................................................................................................................................... 14
2.2. Field Survey ..................................................................................................................................................... 14
2.3. The Survey Team ........................................................................................................................................... 14
2.4. Topographical Survey .................................................................................................................................... 14
2.5. Topography and Geomorphology............................................................................................................... 15
2.5.1 Topography ..................................................................................................................................................... 15
2.5.2 Geomorphology ............................................................................................................................................. 15
2.6. Vegetation Survey .......................................................................................................................................... 16
2.7. Construction Material Survey ....................................................................................................................... 16
2.8. General Inventory .......................................................................................................................................... 17
2.9. General Alignment Description................................................................................................................... 20
2.10. Land Use Pattern............................................................................................................................................ 21
2.10.1 Passing Bays and Bus Lay Bys...................................................................................................................... 22
2.10.2 Cross Drainage and Irrigation Crossing ..................................................................................................... 22
2.10.3 Retaining Structures ....................................................................................................................................... 22
2.11. Traffic Safety Measures ................................................................................................................................. 23
2.12. Data Entry and Analysis ............................................................................................................................... 23
3. ROAD CORRIDOR COMMUNITY PROFILE................................................................. 24
3.1. VDCs along Road Corridor.......................................................................................................................... 24
3.2. Cast Ethnicity.................................................................................................................................................. 25
3.3. Occupation ...................................................................................................................................................... 25
3.4. Education and Health Status ........................................................................................................................ 25
4. DESIGN STANDARDS AND PARAMETERS .................................................................. 26
4.1. Geometric Design Standard ......................................................................................................................... 26
5. ENGINEERING DESIGN ................................................................................................. 28
5.1. Road Classification......................................................................................................................................... 28
5.2. Design Speed .................................................................................................................................................. 28
5.3. Right of Way ................................................................................................................................................... 28
5.4. Roadway Width .............................................................................................................................................. 28
5.5. Extra Widening ............................................................................................................................................... 28
5.6. Sight Distance ................................................................................................................................................. 28
5.7. Horizontal Curvature..................................................................................................................................... 28
5.8. Vertical Curvature .......................................................................................................................................... 28
5.9. Longitudinal Section ...................................................................................................................................... 28
5.10. Pavement Surface ........................................................................................................................................... 29
5.11. Cross Section .................................................................................................................................................. 29
5.12. Passing Bays and Bus Lay Bys...................................................................................................................... 29
5.13. Water Management Measures ...................................................................................................................... 29
5.14. Side Drains ...................................................................................................................................................... 29
5.15. Dynamic Cone Penetration Test and Pavement Design ......................................................................... 30
6. ENGINEERING DESIGN AND DRAWINGS ................................................................. 32
7. ENGINEERING ESTIMATES .......................................................................................... 33
7.1. The Project Cost Estimate............................................................................................................................ 33
7.2. Quantity Estimate .......................................................................................................................................... 33
7.3. Analysis of Rates ............................................................................................................................................ 33
8. ENVIRONMENT PROTECTION MEASURES .............................................................. 35
9. CONCLUSION AND RECOMMENDATIONS ............................................................... 36
LIST OF TABLES
Table 1: Physiographic Region ................................................................................................................................ 15
Table 2: Geology and Soil Type Along Road Alignment .................................................................................... 16
Table 3: Geology and Soil Type along Road Alignment ..................................................................................... 16
Table 4: Possible Quarry Sites ................................................................................................................................. 17
Table 5: Existing Retaining Structures Along Road Alignment ......................................................................... 17
Table 6: Existing High Grade Sections and Loops .............................................................................................. 20
Table 7: Land use along the road alignment .......................................................................................................... 21
Table 8: Demographic Features of Influence VDCs ........................................................................................... 24
Table 9: Demographic Features of Settlements along Road Corridor .............................................................. 24
Table 10: DoLIDAR Standard ................................................................................................................................ 26
Table 11: Extra widening .......................................................................................................................................... 28
Table 12: Summary Cost Estimate .......................................................................................................................... 33
Table 13: Proposed Chainages for Bioengineering Works and Area ................................................................ 35
Table 14: Recommended Spoil Disposal Sites ...................................................................................................... 35
LIST OF FIGURES
Figure 1: Map of Nepal showing Dolakha District ............................................................................................. viii
Figure 2: Political Map of District showing VDC boundary ............................................................................... ix
Figure 3: Sunkhani – Kanpa Road Alignment ........................................................................................................ x
Figure 4: Location of Sub-project in Geological Map ......................................................................................... 15
Figure 5: Chainage vs Altitude Graph of Road Alignment ................................................................................. 20
Figure 6: Typical Road Cross Section Showing Gabion Wall............................................................................. 22
Figure 7: Typical Road Cross Section Showing Stone Masonry Wall ............................................................... 23
Figure 8: Typical Drain Proposed ........................................................................................................................... 30
Figure 9: Plan and Profile Sheet Sample ................................................................................................................ 32
Figure 10: Cross Section Sheet Sample .................................................................................................................. 32
ANNEXES
Annex 1: Bench mark List and Description Cards ............................................................................................... 37
Annex 2: Passing Bays and Bus Lay Bys ................................................................................................................ 39
Annex 3: Cross Drainage Structures ....................................................................................................................... 40
Annex 4: Dynamic Cone Penetration Test and Pavement Design .................................................................... 43
Annex 5: Abstract of Cost ........................................................................................................................................ 45
Annex 6: Summary of Quantities ............................................................................................................................ 57
Annex 7: Curve Data ................................................................................................................................................. 65
Annex 8: District Rate ............................................................................................................................................... 66
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
SALIENT FEATURES
Features Description
Name of the Road Sunkhani – Kanpa section of Sunkhani – Sangwa – Jiri Road
Scope Reconstruction and Rehabilitation
DRCN No. 22DR004
Location
Region: Central Development
Zone: Janakpur
District: Dolakha
VDC/Municipality Sunkhani, Lapilang, Lamidanda and Babare VDCs
Sisagolai (Bhadaure), Dudhpokhari, Leptung, Pikhelpa, Gujarpa,
Godun, Kurathali, Thanmaru, Lakaigau, Lapilang, Gumu,
Major Settlements Hilepani, Ghyan, Karamthali, Timure, Sisneri, Dharpani,
Baware, Kusawati, Kotisyang, Tungapa, Niko Bhumi and
Damba
Length 27.373 km
Starting Point Sisagolai/Bhadaure Bazaar, Sunkhani VDC-9
End Point: Damba Khola, Bata (Kanpa), Babare VDC-1
Beneficiaries Population in ZOI
Sunkhani, Lapilang, Lamidanda and Households – 2385, Population – 8671
Babare VDCs
Geographical feature
Terrain Mid-Hills
Altitudinal Range 1474 m to 1782 m
Climate: Sub-tropical to Lower temperate
Lesser Himalayan Rocks (Phyllite and Gneiss), Colluvium,
Geology:
Alluvium and Residual Soil
Meteorology: Unevenly Distributed Precipitation Controlled by Monsoon
Design Standard
Standard NRRS 2055, 2nd Revision December 2014
Existing Surface: Earthen
Proposed Pavement: Gravel, Cobble for grade >7%
Geometrics
Right Of Way: 10 m on either sides (Center line)
Formation Width: 6.25 m (includes 1m drainage & 0.75 m Shoulder)
Carriage Way Width: 3.75 m
Shoulder Width: 0.75 m on either side
Maximum Gradient 12%
Minimum Gradient 0.5%
Lane Single
vi | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Features Description
Package 1 (Ch. 0+000 – Package 2 (Ch. 16+000 –
16+000) 27+373)
Gravel / Cobble for grade Gravel / Cobble for grade
Pavement Standard
>7% >7%
Gravel Length 8.8 km 6.48 km
Cobble Length 7.2 km 4.9 km
Structures (Qty/No.)
Drainage Structures
a) Side Drain Throughout the alignment at hill side.
b) Causeway 6 (RCC) 2 (RCC)
c) Slab Culvert 1 4
d) Pipe Culvert 52 41
e) Irrigation Crossing 12 8
Retaining Structures
a) Stone masonry Wall 590.34 cu.m. 251.81 cu.m.
b) Gabion Retaining and Breast
5,800.00 cu.m. 7,395.00 cu.m.
Walls
Earth Work Road works
a) Excavation/Cutting 68,072.74cu.m. 40,412.3cu.m.
b) Embankment/Filling 5,488.24cu.m. 5,054.96cu.m.
Pavement
a) Gravel 11,065.03 cu.m. 8,529.68 cu.m.
b) Cobble 2,410.85 cu.m. 1,617.89 cu.m.
Cost Estimate (Rs)
a) Civil Works (Base cost) 207,440,626.71 157,505,597.66
b) 13% VAT (of a) 26,967,281.47 20,475,727.70
c) Total (a+b) 234,407,908.18 177,981,325.36
d) Per km Cost (excluding VAT, 14,650,494.26 15,649,461.48
day works and contingencies)
e) Work Charge Staff and Small 6,223,218.80 4,725,167.93
Miscellaneous Expenses @
3% (of a)
f) Physical contingency @ 10% 20,744,062.67 15,750,559.77
(of a)
g) Grand Total (c+e+f) 261,375,189.66 198,457,053.06
vii | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
viii | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
ix | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
x|Page
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
ACRONYMS/ ABBREVIATIONS
ADB Asian Development Bank
BM Bench Mark
BOQ Bill of Quantities
c/c Center to Center
DCP Dynamic Cone Penetration
DCPI Dynamic Cone Penetration Index
DDC District Development Committee
DoLIDAR Department of Local Infrastructure Development and Agriculture Roads
DoR Department of Roads
DRCN District Road Core Network
DRILP Decentralized Rural Infrastructure and Livelihood Project
DTO District Technical Office
FY Fiscal Year
GON Government of Nepal
Km Kilometer
MT Metric Tonne
m Meter
mm Millimeter
m2 Square Meter
m3/cum Cubic Meter
NRRS Nepal Rural Road Standard
NA Not Applicable
PCC Plain Cement Concrete
RCC Reinforced Cement Concrete
Rs. Nepalese Rupees
rm Running Meter
SDC Swiss Agency for Development and Co-operation
TOR Terms of Reference
VDC Village Development Committee
VAT Value Added Tax
xi | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
1. INTRODUCTION
1.1. Project Background
The rehabilitation and reconstruction of local roads network damaged due to major earthquake of 25
April 2015 and May 12 2015 has high priority for the Government of Nepal (GoN) . The Asian
Development Bank (ADB) funded Earthquake Emergency Assistance by Project (ADB Loan 3260-
NEP) is aimed to accelerate the recovery and reconstruction of the local roads damaged by the
earthquake. The rehabilitation and reconstruction of about 385 km of rural roads damaged by the
earthquake and landslides in 10 of the earthquake hit districts (Dolakha,Kavrepalanchowk, Laitpur,
Chitwan, Sindhuli, Solukhumbu, Okhaldhunga, Ramechhap, Gorkha and Lamjung). 27.373 km long
Sunkhani-Kanpa section of Sunkhani – Sangwa – Jiri road of Dolakha district is one of the roads
proposed for rehabilitation and reconstruction under EEAP.
As part of the Technical Assistance from Swiss Agency for Development and Cooperation (SDC) also
provided technical assistance to EEAP. AF-Iteco, Switzerland,currently providing services as Central
Implementation Support Consultants (CISC) for Decentralized Rural Infrastructure and Livelihood
Project-Additional Financing has been entrusted to act as Consultant for this project and has given the
assignment for preparation of Detailed Project Reports for rehabilitation and reconstruction of
selected rural road subprojects of Dolakha and Ramechhap to Joint Venture of Gaurav Integrated
Development Associates Nepal (P) Ltd, NEST (P) Ltd and Jaarsa Engineering Consultancy (P) Ltd.
1.2. Project District and Proposed Road
The Sunkhani – Kanpa Road, section of Sunkhani - Sangwa - Jiri Road lies in Dolakha district.
Dolakha, the project district, is located in the Janakpur Zone of the Eastern Development Region of
Nepal. The district is located within 27 28’ to 28 0’ latitude and 85 50’ to 86 32’ longitude. The
district borders with Ramechhap District in South, Ramechhap & Solukhumbu Districts in East,
Sindhupalchowk District in West and Tibet (China) in North.
The total area of Dolakha district is 2,191 km2, among which 26.45% is agricultural land, 47.37% is
forest area, and 13.77% is cattle pasture land, 2.64% is snow covered, 3.33% is covered by water and
rest 6.44% is others. The total population of the Dolakha district is 186557 as per last census of 2011,
out of which 87003 are male and 99554 are female. The population density is 85 people per sq. km,
household size is 4.08 person. The Lamosangu – Jiri Road is connected to Araniko Highway at
Khadichaur of Sindhupalchowk connecting Dolakha to Kathmandu.
The road passes through Sunkhani, Lapilang, Lamidada and Babare VDCs of Dolakha District. DDC
has proposed to upgrade the 27.338 km section of the road. The road section starts from Sisagolai
(Bhadaure Bazaar) of Sunkhani VDC-9 along Dolakha – Singati Road (2742’25” N Latitude and
8606’32”E Longitude) and ends at Damba of Babare VDC-1 (2747’35” N Latitude and 8605’36”E
Longitude), passing via about 21 settlements along the alignment. The major settlements along the
road alignment are Sisagolai (Bhadaure), Dudhpokhari, Leptung, Pikhelpa, Gujarpa, Godun,
Kurathali, Thanmaru, Lakaigau, Lapilang, Gumu, Hilepani, Ghyan, Karamthali, Timure, Sisneri,
Dharpani, Baware, Kusawati, Kotisyang, Tungapa, Niko Bhumi and Damba The DDC Dolakha had
made it trafficable under RRRSDP few years ago. The status of the road of the project along the
alignment is earthen existing track. Stone soling is present in some of the high grade loop sections and
in few sections in settlement areas.
1.3. Scope of Works
The detailed engineering survey, design and cost estimate for rehabilitation and reconstruction. of
Sunkhani- Kanpa Road section has been carried out by the Consultants.
Accordingly the scope of works covers:
a. Detailed engineering survey of the road including fixing centreline.
b. Detail design the road to DOLIDAR’s NRRS 2055, 2nd Revision December 2014.
c. Prepare drawings including alignment plan, design profile, design cross-section and typical
drawings
12 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
13 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
14 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
15 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
16 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
table below shows the location of different quarry sites and market for procurement of construction
materials.
Table 4: Possible Quarry Sites
Material Site Distance
Gravel Tamakoshi River at Nayapul 25 km blacktopped and 18 km earthen road
Kharidhunga 30 km blacktopped and 18 km earthen road
Singati Khola 13 km earthen/gravel road
Sand Tamakoshi River at Nayapul 25 km blacktopped and 18 km earthen road
Singati Khola 13 km earthen/gravel road
Boulder Gumu Khola and Lapse Khola Ch 7+350
At site of roadway cutting
Aggregate Gumu Khola and Lapse Khola Ch 7+350
Roadway Cutiing
2.8. General Inventory
During the survey, no side drains were observed along the existing road alignment. However, retaining
structures like gabion walls, gravity wall and breast wall along, several chainage were observed. During
the design, priority has been given to protect the existing gabion walls as much as possible. Despite
this, the retaining structures have to be dismantled while improving the grade of alignment as per
NRRS.
The table below shows the locations of existing retaining structures in the existing alignment.
Table 5: Existing Retaining Structures Along Road Alignment
Chainage Retaining Wall Type Remarks
0+220 Gabion Dismantle not required
0+650 – 0+660 Gabion
0+690 – 0+700 Dry
0+780 Gabion
0+810 – 0+820 Gabion
1+380 Gabion
1+540 Gabion
1+710 Gabion
1+760 – 1+770 Gabion
1+820 Gabion
1+980 – 1+990 Gabion
2+220 Gabion
2+210 Masonry
2+230 Masonry Dismantle required
2+410 – 2+420 Gabion Dismantle not required
2+450 – 2+470 Dry wall Gabion wall proposed
2+840 Gabion Dismantle not required
2+900 – 2+910 Gabion
2+950 Gabion
3+020 Gabion Dismantle required
3+100 – 3+110 Gabion Dismantle not required
3+180 – 3+190 Gabion Dismantle required
3+200 – 3+220 Gabion Breast Dismantle not required
3+280 – 3+300 Gabion Breast Masonry wall proposed
3+330 – 3+350 Gabion Breast Dismantle required
3+390 – 3+400 Gabion Dismantle not required
3+740 Gabion
4+020 – 4+050 Gabion Breast
17 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
18 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Also, it was observed that in the road section didn’t have any pipe culvert for cross drainage.
However, at chainage 7+355, there is one slab culvert, which is in good working condition. The
existing earthen drains are proposed to be replaced by masonry side drains. Further, the existing
gradient of road profile lies within the limiting gradient permitted by NRR standards.
19 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
The existing high grade obtained beyond permissible gradient from survey are considered and reduced
to limiting gradient as per NRRS in upgraded design. The gradient has been maintained below 10%
wherever possible. In stretches where the grade exceeds 10%, the grade has been maintained below
12% as per NRRS. The chainage vs. altitude is presented in following figure 5.
20 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
21 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
22 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
more than 3m. For the slope and foundation width of the wall, DoLIDAR approach manual,
Overseas Road Note 16, DRSP and RAIDP manual is followed.
23 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
24 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
25 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
26 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
14. Passing zone/Bus lay Passing zones: width of carriage way width 5.5m and length
Byes about 12 m along outside edge and 30 m along inside ie. Towards
the carriageway side and each end tapered gradually towards the
carriageway.
Bus Lay Bys: minimum width additional 3 m (ie. total minimum
carriageway width is 6m) and and length about 12 m along outside
edge and 30 m along inside ie. Towards the carriageway side and
each end tapered gradually towards the carriageway.
15. Traffic Signs and Road
As detailed in the NRRS 2013
Safety
16. Carriageway Width ( cross-drainage structures)
Culvert 4.5 Distance between parapet walls
17. Road side drains Hill roads: trapezoidal drain with masonry (1:4) back wall and
10cm thick M-15 grade concrete sloped bed throughout the road
length as required
Built up areas: Drain as specified in DoLIDAR Technical
Guideline with adequate cover slabs for crossings.
Surfacing Options
1. Gravel Surface Hill roads :
15cm gravel surfacing in carriageway to be extended in the hill side
shoulder up to inner edge of the drain. Tapering gravel hard
shoulder (15cm to 6cm) in the valley side with slope towards the
valley.
27 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
5. ENGINEERING DESIGN
The design parameters adopted for Sunkhani-Kanpa Section of Sunkhani – Sangwa – Jiri Road follow
DoLIDAR Nepal Rural Road Standard (2055), 2nd Revision December 2014.
5.1. Road Classification
The proposed road has been classified as District Road Core Network (DRCN) and assigned Code
No. is 22DR004.
5.2. Design Speed
The design speed has a crucial role in geometric parameters of the roads. The design speed depends
on various factors like; super elevation, sight distance, radius and length of horizontal curve, , extra
widening of pavement, and the length of vertical curve (summit and valley) etc. According to the
design standards followed, the ruling design speed adopted 25km/hr in flat section. However at
hairpin bends, horizontal curve and steep sections, the adopted design speed as per NRRS is
20km/hr.
5.3. Right of Way
As per the design standard of DoLIDAR, right of way adopted for Sunkhani - Kanpa Section of
Sunkhani - Sangwa - Jiri Road is 10 m either side.
5.4. Roadway Width
Roadway width adopted for the proposed road is 5.25m. It includes 3.75 m width Carriageway width
and 0.75m of shoulder on either side.
5.5. Extra Widening
It is necessary to widen the carriage way at sharp horizontal curves for the free movement of vehicles.
Only mechanical widening has been proposed to compensate the extra width occupied by the vehicle
on the sharp curve. For this, the inner part of the curve is proposed for widening as per NRRS as
listed below in table 11.
Table 11: Extra widening
Radius
SN. Extra widening(m)
From To
1 0 20 1.5
2 20 60 0.6
3 60 1000 0
28 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
29 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Pavement performance depends greatly upon the quality and uniformity of materials incorporated into
the pavement structure. Careful monitoring of material quality and the dimensions of pavement layers
during construction improves overall compliance with specifications as well as in-service performance
of the pavement.
30 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
In this project for pavement design, Overseas Road Note 8 is used for calculation of CBR value. After
calculation of CBR value by Overseas Road Note 8, it is classified in six classes according to Road
Note 31. The required thickness of gravel is calculated based on classes. The details of the pavement
design calculations are attached in Annex 4. For the design, considering the results of DCP test and
judging economic in gravel road, the uniform thickness of sub base 175 mm has been adopted.
Further on, the road having gradient higher than 7% will not be suitable for gravel pavement only,
because it has been observed from the past experiences, that there is high possibility to rutting of road
surface due to rain water as well as tractive force of vehicles plying along the road. To minimize the
problem in the project road, cobble pavement has been proposed for the high gradient above gradient
7% in 12.08 km stretch out of total 27.37 km.
31 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
32 | P a g e
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
7. ENGINEERING ESTIMATES
7.1. The Project Cost Estimate
The cost estimate for the road has been prepared in two packages. For first package Ch: 0+000 –
16+000, the cost of civil works has been estimated to be Rs. 207,440,626.71. The total cost for
rehabilitation and reconstruction including contingencies consisting of small miscellaneous expenses,
work charge staff and VAT as per GON rules is calculated to be Rs. 261,375,189.66. The per km cost
excluding VAT, dayworks and contingencies is Rs. 14,650,494.26. For second package Ch: 16+000 –
27+373.27, the cost of civil works has been estimated to be Rs. 157,505,597.66. The total cost for
rehabilitation and reconstruction to gravel standard including contingencies consisting of small
miscellaneous expenses, work charge staff and VAT as per GON rules is calculated to be Rs.
198,457,053.06. The per km cost excluding VAT, dayworks and contingencies is Rs. 15,649,461.48. It
is envisaged that the construction works can be completed within 18 months from award of contract
and estimates are based on it. Provision of physical contingency 10% has been indicated in the cost
estimate. The abstract of costs is presented as Annex 5 of this report. The summary cost estimate is
presented in table 12 below.
Table 12: Summary Cost Estimate
S.
Description Package 1 (NRs.) Package 2 (NRs.)
No.
1. Civil Works 207,440,626.71 157,505,597.66
1.1 General Works 12,724,000.00 3,524,000.00
1.2 Site clearance, Earthworks 15,862,638.18 8,460,360.32
1.3 Structures- Stone Masonry 79,241,786.28 58,717,263.71
1.4 Structures- Gabion 30,888,341.48 35,495,063.69
1.5 Drains, Cross drainage structures 21,410,192.47 18,624,795.16
1.6 Pavement 37,025,170.11 27,372,089.99
1.7 Road furniture, Traffic Signs 4,245,047.22 3,169,593.15
1.8 Bio engineering 5,585,450.96 1,684,431.65
1.9 Day works 458,000.00 458,000.00
2. 13% VAT (of 1) 26,967,281.47 20,475,727.70
3. Sub-Total (1+2) 234,407,908.18 177,981,325.36
4 Per km Cost (Including Base Cost and VAT) 14,650,494.26 15,649,461.48
5 Work Charge Staff and Small Miscellaneous
6,223,218.80 4,725,167.93
Expenses @ 3% (of 1)
6 Physical contingency @ 10% (of 1) 20,744,062.67 15,750,559.77
7 Grand Total (3+5+6) 261,375,189.66 198,457,053.06
7.2. Quantity Estimate
For estimating the cost of the project, detailed quantity estimation had been done for each item of
works to be included in the project activities. The detail quantity estimates have been provided in
Volume 2 cost estimate and the summary sheet of quantity estimation. (Refer Annex 6 for summary of
quantities)
7.3. Analysis of Rates
For estimating the cost of each item of works, prevailing norms of DoLIDAR and DOR for rate
analysis has been used throughout. Rate analysis of each of the items has been carried out according
to the approved norms of DoLIDAR and approved district rates of Dolakha District and as
mentioned there in the. Kathmandu District rates for materials (cement, Steel, Hume Pipe etc.) for
the Fiscal Year 2072/2073 with transportation have been followed.
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
For rate of earthwork quantities, rate for earthwork excavation by machine and manually for roadway
and drain and for foundation of structure is adopted 95% and 5% as carried out by DOR. The
detailed analysis of rate and the approved district rates are provided in Volume 2, The Cost Estimate.
.
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
8. ENVIRONMENT PROTECTION MEASURES
The road alignment passes along a hilly terrain which contains slides at different chainages. The rainy
season following April 25 and May 12 earthquake has triggered landslides along the road corridor at
Ramche and Dudhpokhari area of Lapilang-9 and Chiuri Kharka to Ratmate of Lamidada) which
require proper bio-engineering works and landslide rehabilitation.
Table 13: Proposed Chainages for Bioengineering Works and Area
During field visit, it was observed that the nature of landslide at chainage 4+630 to 4+780,
Dudhpokhari area is large and sensitive. The location requires special consideration during
construction period. Gabion walls and toe walls have been proposed in the design as noted essential
during the site visit Bioengineering is mandatory in this location. Also, bioengineering works has been
proposed in other locations where landslides have occurred though small in scale. In many locations,
where erosion has been witnessed, gabion breast walls have been proposed.
Suitable materials obtained from excavation will be used for embankment filling, and backfilling of
structures. Despite this, the surplus excavated materials obtained will be disposed at construction site
as required. Wherever possible, the surplus spoil will be used to fill eroded gullies, quarries and
depressed areas. Dry stone toe walls are required in some locations for disposal of spoils. The main t
sites recommended for spoil disposal are listed in table 14 below:
Table 14: Recommended Spoil Disposal Sites
Chainages Recommended Spoil Disposal Sites
1+900 Damai Khoriya, Sunkhani; At the ridge within 500 m of excavation site. Tipping site
lies in Ramche CF
2+400 At the ridge of the hill witin 1 km of excavation site. Tipping site lies in Ramche CF
7+300 At the alluvial fan of Lapse Khola (Gumu Lapse Confluence)
8+400 Lapse Khola bank
15+750 Thalaripakha CF, hill ridge
24+500 Private land (uncultivated pakha) filling in depression
Source: Field Survey, 2016
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
9. CONCLUSION AND RECOMMENDATIONS
The Sunkhani- Kanpa section of Sunkhani – Sangwa road is presently earthen track and its
rehabilitation and reconstruction to gravel standard will provide better access to the people of
settlements along road corridor and it will help in getting the better benefit of the road which results
in better living standard of the local people.
All the settlements along the proposed road alignment and its neighborhood have immense potential
of vegetable, fruit and other cash crops (like amriso and cardamom) production. People can increase
the production of cereal crops and cash crops so that it can be exported. This will increase the cash
flow in the area.
While considering the improvement of the road to gravel standard, provisions have been made for
adequate cross drainage as well as side drains. However for the preservation of gravel surface it is
important that surface water does not flow through the road surface. As such it is recommended that
during rainy season in construction phase the adequacy of side drains and cross drainage shall be
observed and modification as required shall be made to preserve the road asset.
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Package 1
Width Transition
SN Chainage Length (m)
Left(m) Right (m) Length (m)
1 0+740 12 1.75 0 9
2 1+030 12 1.75 0 9
3 1+330 12 1.75 0 9
4 1+660 12 1.75 0 9
5 1+920 12 0 1.75 9
6 2+600 12 0 3 9
7 3+565 12 1.75 0 9
8 3+770 12 1.75 0 9
9 4+310 12 0 1.75 9
10 5+260 12 3 0 9
11 6+135 12 1.75 0 9
12 6+820 12 0 1.75 9
13 7+050 12 0 3 9
14 7+575 12 1.75 0 9
15 8+815 12 0 1.75 9
16 10+205 12 3 0 9
17 10+785 12 1.75 0 9
18 11+480 12 0 3 9
19 11+860 12 1.75 0 9
20 12+110 12 0 3 9
21 12+330 12 1.75 0 9
22 13+655 12 1.75 0 9
23 14+520 12 1.75 0 9
24 15+035 12 1.75 0 9
25 15+615 12 1.75 0 9
26 15+870 12 1.75 0 9
Package 2
1 16+885 12 1.75 0 9
2 18+390 12 1.75 0 9
3 19+325 12 1.75 0 9
4 19+975 12 1.75 0 9
5 20+400 12 1.75 0 9
6 21+530 12 0 3 9
7 23+285 12 1.75 0 9
8 23+830 12 1.75 0 9
9 26+020 12 3 0 9
10 26+745 12 1.75 0 9
11 27+170 12 3 0 9
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Annex 3: Cross Drainage Structures
Package 1
Proposed Pipe Culverts
Diameter
SN Chainage Length (m)
(m)
1 0+241 7.5 0.6
2 0+539 7.5 0.6
3 0+666 7.5 0.9
4 0+875 7.5 0.9
5 1+078 7.5 0.6
6 1+311 7.5 0.9
7 1+398 7.5 0.6
8 1+491 7.5 0.9
9 1+535 7.5 0.9
10 1+649 7.5 0.6
11 2+203 7.5 0.9
12 2+484 7.5 0.9
13 2+643 7.5 0.6
14 3+242 7.5 0.6
15 3+361 7.5 0.6
16 4+053 7.5 0.9
17 4+151 7.5 0.9
18 4+661 7.5 0.9
19 4+768 7.5 0.9
20 5+018 7.5 0.6
21 5+306 7.5 0.6
22 5+502 7.5 0.6
23 5+696 7.5 0.6
24 5+808 7.5 0.9
25 6+022 7.5 0.9
26 6+401 7.5 0.9
27 6+784 7.5 0.9
28 8+295 7.5 0.9
29 8+727 7.5 0.9
30 8+899 7.5 0.9
31 9+475 7.5 0.9
32 9+545 7.5 0.9
33 9+914 7.5 0.6
34 10+158 7.5 0.6
35 10+381 7.5 0.6
36 11+211 7.5 0.9
37 11+688 7.5 0.6
38 11+786 7.5 0.9
39 12+001 7.5 0.6
40 12+149 7.5 0.6
41 12+449 7.5 0.6
42 12+612 7.5 0.6
43 12+699 7.5 0.6
44 12+895 7.5 0.6
45 13+003 7.5 0.9
46 13+176 7.5 0.9
47 13+428 7.5 0.6
48 13+716 7.5 0.6
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Diameter
SN Chainage Length (m)
(m)
49 14+581 7.5 0.6
50 15+141 7.5 0.9
51 15+208 7.5 0.9
52 15+469 7.5 0.6
Proposed Causeways
SN Chainage Length (m)
1 3+020 8
2 3+728 8
3 6+888 6
4 8+417 10
5 9+385 8
6 11+532 6
Package 2
Proposed Pipe Culverts
Diameter
SN Chainage Length (m)
(m)
1 16+327 7.5 0.9
2 16+665 7.5 0.9
3 17+149 7.5 0.9
4 17+391 7.5 0.9
5 17+559 7.5 0.9
6 17+795 7.5 0.9
7 18+292 7.5 0.9
8 18+441 7.5 0.6
9 18+658 7.5 0.9
10 18+936 7.5 0.6
11 19+273 7.5 0.9
12 19+751 7.5 0.9
13 19+939 7.5 0.6
14 20+019 7.5 0.9
15 20+459 7.5 0.9
16 20+742 7.5 0.9
17 20+879 7.5 0.6
18 21+152 7.5 0.9
19 21+368 7.5 0.9
20 21+777 7.5 0.6
21 21+848 7.5 0.9
22 22+743 7.5 0.9
23 23+001 7.5 0.6
24 23+303 7.5 0.6
25 23+395 7.5 0.9
26 23+609 7.5 0.9
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Diameter
SN Chainage Length (m)
(m)
27 24+139 7.5 0.9
28 24+587 7.5 0.9
29 24+647 7.5 0.9
30 24+931 7.5 0.6
31 25+029 7.5 0.9
32 25+184 7.5 0.9
33 25+532 7.5 0.6
34 25+793 7.5 0.6
35 25+945 7.5 0.9
36 26+335 7.5 0.9
37 26+504 7.5 0.9
38 26+869 7.5 0.6
39 27+051 7.5 0.6
40 27+228 7.5 0.9
41 27+338 7.5 0.9
Proposed Causeways
SN Chainage Length (m)
1 20+148 6
2 23+720 6
Data
i. Single lane carriageway
ii. Number of commercial vehicles as per last count(P)= 10 veh/day (including both direction)
iii. Number of years between the last count and the year of completion of construction= 2 years
iv. Traffic growth rate per annum(r) = 7.5 (according to Guidelines- IRC-37-2001, in the absence of
adequate data, it is recommended that an average annual growth rate of 7.5 percent may be
adopted.)
v. Design life(n) = 10 years
vi. Vehicle damage factor (F) = 0.5 (according to Guidelines- IRC-37-2001, in the absence of
adequate information on axle load, VDF may be adopted from the following table.)
Indicative VDF Values
Initial traffic volume in terms of Number of Terrain
commercial vehicles per day Rolling/Plain Hilly
0-150 1.5 0.5
150-1500 3.5 1.5
More than 1500 4.5 2.5
vii. Lane Distribution factor(D) = 1 i.e 100% of total traffic in both direction, (according to
Guidelines- IRC-37-2001, for single lane road the design should be based on total number of
commercial vehicles in both directions).
Traffic forecasting
Initial traffic in the year of completion of construction (A)
A = P (1+r) n
=10(1+0.075)2
=11.556 commercial vehicles per day
Cumulative number of standard axles (sa) to be carried for in the design (N)
N = 365x ((1+r) n-1) x A x D x F
r
= 365x((1+0.075)10-1)x11.556x1x0.5
0.075
= 59671.57 sa
= 0.5967 msa
However with the upgrading of roads the additional traffic may be attracted or diverted through this
road. The diverted traffic for the road is assumed 50%. This makes the design traffic value as
1.5*0.5967 = 0.89 msa.
Hence as per Overseas Road Note 31, this traffic falls into Class T3 (0.7 msa to 1.5 msa).
Therefore, referring to ORN 31, the pavement thicknesses for granular road-base materials is calculated
with this traffic class T3 and sub grade strength classes based on the range of CBR values.
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Summary of Pavement Thickness
From Overseas Road Note 31, Chart 1
Package 1
Chainage Adopted Sub
Capping
Base Thickness Remarks
From To Layer (mm)
(mm)
0+000 6+500 175 -
6+500 7+000 175 100
7+000 8+000 175 -
8+000 8+300 175 100
8+300 10+000 175 -
10+000 10+500 175 100
10+500 13+000 175 -
13+000 13+500 175 100
13+500 16+000 175 -
Package 2
Chainage Adopted Sub
Capping
Base Thickness Remarks
From To Layer (mm)
(mm)
16+000 17+000 175 -
17+000 17+500 175 100
17+500 19+000 175 -
19+000 20+500 175 100
20+500 25+500 175 -
25+500 27+373 175 100
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Annex 5: Abstract of Cost
Package 1
Pay
Item Amount
Description Unit Quantity Rate (NRs.)
No. (NRs.)
1 General
1.1 Insurance of works, plants, materials, loss L.S. 1.00 7,000,000.00 7,000,000.00
and damage to equipment’s, Contractor's
workmen and employees and third party
insurance against damage to other persons
and property as per GCC clause 13.
1.2 Provide site office at mid-section of the month 18.00 30,000.00 540,000.00
road having rooms size: 3m*4m each at
location acceptable to the project manager
within the contract package with
accommodation facilities as specified in
special provision
1.3 Carry out additional tests for material and PS 1.00 200,000.00 200,000.00
works as required and instructed by the
Engineer.(GCC Clause No. 33.1)
1.4 Relocation of the utilities (water supply, PS 1.00 400,000.00 400,000.00
telephone, etc,) and services as instructed
by the Engineer as per DoLIDAR-
Technical Specifications for Labour Based
Construction Work of Agricultural & Rural
Roads (Tech. Spec. for LBCWARR Clause
No. G-10.
1.5 Carry out maintenance of the existing road month 18.00 38,000.00 684,000.00
to keep the road serviceable throughout the
contract period. Also provide and maintain
traffic safety, control measures and
temporary diversions during construction
including water spraying thrice a week to
avoid dust pollution as per DoLIDAR-
Tech. Spec. for LBCWARR Clause No. G-
12.
1.6 Supply and provide rental Four Wheel month 18.00 150,000.00 2,700,000.00
Drive Double cap Pickup Vehicle with full
option including fuel, driver' wages, major
& minor maintenances etc. for the
Engineer for supervision works as
specified
1.7 Provide and installation of project No. 3.00 10,000.00 30,000.00
information board of size 1.80 mx1.2 m
along with iron posts including excavation,
concreting, backfilling etc. all complete as
per DoR Standard Specification for Road
and Bridge Works (SSRBW) July
2001,Section-108
1.8 Provision and maintenance of labour month 18.00 20,000.00 360,000.00
camps payable monthly in equal instalments
as per DoR Standard Specification for
Road and Bridge Works (SSRBW) July
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Pay
Item Amount
Description Unit Quantity Rate (NRs.)
No. (NRs.)
2001,Section-109 (3)
1.9 Establish, maintain and operate laboratory month 18.00 20,000.00 360,000.00
at the site with equipment’s furnishing
required for testing specified quality of the
materials as per DoR-SSRBW, Section-511
1.10 Environmental Mitigation Works as per P.S. 1.00 300,000.00 300,000.00
EMP and as Instructed by the
Engineer(DOR Section 109)
1.11 Social Compliance and safeguards as per P.S. 1.00 150,000.00 150,000.00
Resettlement Action Plan and GESI and as
instructed by the Engineer(DOR Section
109)
Sub-Total 12,724,000.00
2 Site Clearance
2.1 Site Clearance : Clearing and Grubbing m2 64,000.00 21.56 1,379,705.60
including cutting of all types of plants as
per DoLIDAR-Technical Specifications for
Labour Based Construction of Agricultural
and Rural Roads (Tech. Spec. for
LBCWARR) Clause No.: 1-1.5(a), 1-1.5(b)
& 1-1.6
Sub-Total 1,379,705.60
3 Earthworks
3.1 Excavation in roadway and drain in all m3 73,936.36 122.01 9,021,162.24
types of soil and rock materials including
removal and satisfactory disposal of all
materials at approved environmentally safe
tipping area as per DoLIDAR-Tech. Spec.
for LBCWARR Clause No. 2-1
3.2 Excavation in foundation in structure in all m3 6,025.85 226.21 1,363,099.94
types of soil materials including removal
and satisfactory disposal of all materials at
approved environmentally safe tipping area
as per DoLIdar-Tech. Spec, for
LBCWARR Clause No. 2-5
3.3 Construction of embankments, shoulders m3 5,488.24 99.97 548,646.26
and other miscellaneous filling and
backfilling in structure with approved
materials as per design and drawing as per
DoLIDAR-Tech. Spec. for LBCWARR
Clause No.2-5
3.4 Transportation of material beyond the m4 70,633.83 50.26 3,550,024.15
initial lead within 1 km distance with safe
disposal sites as instructed by the engineer.
Sub-Total 14,482,932.58
4 Structural/ Side Drain/Cross Drainage
Works
Stone Masonry
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Pay
Item Amount
Description Unit Quantity Rate (NRs.)
No. (NRs.)
4.1 Supply & place un-coursed random rubble m3 13,080.63 6,057.95 79,241,786.28
stone masonry works in MM 5 cement sand
mortar in the line & level all complete stone
masonry work including full compensation
for all labour, materials and other
incidentals required to complete the work
as per the specifications and drawings. It
includes full compensation for using
specially dressed stones on the face of wall
with batter and provisions for weep hole as
necessary as per DoLIDAR-Tech. Spec. for
LBCWARR Clause No. 8
Sub-Total 79,241,786.28
Gabion Works
4.2 Supply machine made fabrication of gabion m3 7,601.53 3,937.01 29,927,309.22
boxes of different sizes with hexagonal
mesh size of 100 mm x 120 mm including
rolling, cutting and weaving (mesh wire 3.0
mm, selvedge wire 3.9 mm, binding wire
2.4 mm, all heavy zinc coated
wires),assembling, placing in position,
packing and filling of gabion create with
rubble stone and tying by 2.4 mm binding
wires all complete as per DoLIDAR-Tech.
Spec. for LBCWARR Clause No. 17-1.4,
17-5 & 17-6
4.3 Provide and place Geo-textile all complete m2 5,904.80 162.75 961,032.26
as per drawing and specifications as per
(DOR-SSRBW Section No.: 2404)
Sub-Total 30,888,341.48
5 Cross Drainage, Side Drainage and
Protection
Plain and Reinforced Cement Concrete
5.1 Supply & place P.C.C. works M 10/20 as m3 365.26 8,717.56 3,184,154.73
per DoLIDAR-Tech. Spec. for LBCWARR
Clause No. 11
5.2 Supply & place P.C.C. works M 15/20 as m3 4.04 11,009.08 44,492.10
per DoLIDAR-Tech. Spec. for LBCWARR
Clause No. 11
5.3 Supply & place P.C.C. works M 20/20 as m3 120.00 13,450.88 1,614,105.03
per DoLIDAR-Tech. Spec. for LBCWARR
Clause No. 11
5.4 Supply & place P.C.C. works M 25/20 as m3 147.76 16,659.54 2,461,679.70
per DOR-SSRBW, July 2001,Section 2000
5.5 Supply and place formwork for concrete m2 671.56 686.04 460,718.72
works with all complete as per
DoLIDAR-Tech. Spec. for LBCWARR
Clause No. 9
5.6 Supply & place TMT high tensile strength T 37.21 106,290.70 3,954,549.61
steel reinforcement of specified grade ( Fe
500) for RCC works including bending,
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Pay
Item Amount
Description Unit Quantity Rate (NRs.)
No. (NRs.)
Package 2
Pay
Amount
Item Description Unit Quantity Rate (NRs.)
(NRs.)
No.
1 General
1.1 Insurance of works, plants, materials, loss L.S. 1.00 600,000.00 600,000.00
and damage to equipment, Contractor's
workmen and employees and third party
insurance against damage to other persons
and property as per GCC clause 13.
1.2 Provide site office at mid-section of the month 18.00 30,000.00 540,000.00
road having rooms size: 3m*4m each at
location acceptable to the project manager
within the contract package with
accommodation facilities as specified in
special provision
1.3 Carry out additional tests for material and PS 1.00 200,000.00 200,000.00
works as required and instructed by the
Engineer.(GCC Clause No. 33.1)
1.4 Relocation of the utilities (water supply, PS 1.00 300,000.00 300,000.00
telephone, etc,) and services as instructed
by the Engineer as per DoLIDAR-
Technical Specifications for Labour Based
Construction Work of Agricultural & Rural
Roads (Tech. Spec. for LBCWARR Clause
No. G-10.
1.5 Carry out maintenance of the existing road month 18.00 38,000.00 684,000.00
to keep the road serviceable throughout the
contract period. Also provide and maintain
traffic safety, control measures and
temporary diversions during construction
including water spraying thrice a week to
avoid dust pollution as per DoLIDAR-
Tech. Spec. for LBCWARR Clause No. G-
12.
1.6 Provide and installation of project No. 3.00 10,000.00 30,000.00
information board of size 1.80 mx1.2 m
along with iron posts including excavation,
concreting, backfilling etc all complete as
per DoR Standard Specification for Road
and Bridge Works (SSRBW) July
2001,Section-108
1.7 Provision and maintenance of labour month 18.00 20,000.00 360,000.00
camps payable monthly in equal instalments
as per DoR Standard Specification for
Road and Bridge Works (SSRBW) July
2001,Section-109 (3)
1.8 Establish, maintain and operate laboratory month 18.00 20,000.00 360,000.00
at the site with equipment furnishing
required for testing specified quality of the
materials as per DoR-SSRBW, Section-511
1.9 Environmental Mitigation Works as per P.S. 1.00 300,000.00 300,000.00
EMP and as Instructed by the
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Pay
Amount
Item Description Unit Quantity Rate (NRs.)
(NRs.)
No.
Engineer(DOR Section 109)
1.10 Social Compliance and safeguards as per P.S. 1.00 150,000.00 150,000.00
Resettlement Action Plan and GESI and as
instructed by the Engineer(DOR Section
109)
Sub-Total 3,524,000.00
2 Site Clearance
2.1 Site Clearance : Clearing and Grubbing m2 45,493.08 21.56 980,735.27
including cutting of all types of plants as
per DoLIDAR-Technical Specifications for
Labour Based Construction of Agricultural
and Rural Roads (Tech. Spec. for
LBCWARR) Clause No.: 1-1.5(a), 1-1.5(b)
& 1-1.6
Sub-Total 980,735.27
3 Earthworks
3.1 Excavation in roadway and drain in all m3 47,590.57 82.33 3,918,264.67
types of soil and rock materials including
removal and satisfactory disposal of all
materials at approved environmentally safe
tipping area as per DoLIDAR-Tech. Spec.
for LBCWARR Clause No. 2-1
3.2 Excavation in foundation in structure in all m3 5,124.28 163.46 837,631.61
types of soil materials including removal
and satisfactory disposal of all materials at
approved environmentally safe tipping area
as per DoLIdar-Tech. Spec, for
LBCWARR Clause No. 2-5
3.3 Construction of embankments, shoulders m3 5,054.96 99.97 505,332.64
and other miscellaneous filling and
backfilling in structure with approved
materials as per design and drawing as per
DoLIDAR-Tech. Spec. for LBCWARR
Clause No.2-5
3.4 Transportation of material beyond the m4 44,138.80 50.26 2,218,396.13
initial lead within 1 km distance with safe
disposal sites as instructed by the engineer.
Sub-Total 7,479,625.05
4 Structural/ Side Drain/Cross Drainage
Works
Stone Masonry
4.1 Supply & place un-coursed random rubble m3 9,675.42 6,068.70 58,717,263.71
stone masonry works in MM 5 cement sand
mortar in the line & level all complete stone
masonry work including full compensation
for all labour, materials and other
incidentals required to complete the work
as per the specifications and drawings. It
includes full compensation for using
specially dressed stones on the face of wall
with batter and provisions for weep hole as
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Pay
Amount
Item Description Unit Quantity Rate (NRs.)
(NRs.)
No.
necessary as per DoLIDAR-Tech. Spec. for
LBCWARR Clause No. 8
Sub-Total 58,717,263.71
Gabion Works
4.2 Supply machine made fabrication of gabion m3 8,705.49 3,940.64 34,305,181.45
boxes of different sizes with hexagonal
mesh size of 100 mm x 120 mm including
rolling, cutting and weaving (mesh wire 3.0
mm, selvedge wire 3.9 mm, binding wire
2.4 mm, all heavy zinc coated
wires),assembling, placing in position,
packing and filling of gabion create with
rubble stone and tying by 2.4 mm binding
wires all complete as per DoLIDAR-Tech.
Spec. for LBCWARR Clause No. 17-1.4,
17-5 & 17-6
4.3 Provide and place Geo-textile all complete m2 7,296.80 163.07 1,189,882.24
as per drawing and specifications as per
(DOR-SSRBW Section No.: 2404)
Sub-Total 35,495,063.69
5 Cross Drainage, Side Drainage and
Protection
Plain and Reinforced Cement Concrete
5.1 Supply & place P.C.C. works M 10/20 as m3 309.18 8,709.65 2,692,818.43
per DoLIDAR-Tech. Spec. for LBCWARR
Clause No. 11
5.2 Supply & place P.C.C. works M 15/20 as m3 15.85 11,030.71 174,847.78
per DoLIDAR-Tech. Spec. for LBCWARR
Clause No. 11
5.3 Supply & place P.C.C. works M 20/20 as m3 90.00 13,493.80 1,214,441.97
per DoLIDAR-Tech. Spec. for LBCWARR
Clause No. 11
5.4 Supply & place P.C.C. works M 25/20 as m3 93.02 16,712.45 1,554,652.87
per DOR-SSRBW, July 2001,Section 2000
5.5 Supply and place formwork for concrete m2 572.50 686.13 392,808.67
works with all complete as per
DoLIDAR-Tech. Spec. for LBCWARR
Clause No. 9
5.6 Supply & place TMT high tensile strength T 35.72 106,568.62 3,807,057.42
steel reinforcement of specified grade ( Fe
500) for RCC works including bending,
centering & binding in position as per
DoLIDAR-Tech. Spec. for LBCWARR
Clause No. 10
5.7 Supply, Laying, fitting and fixing of hume
pipe class NP3. It includes all operations
required to complete the work and the
jointing of pipes with 1:2 cement sand
mortar as per DoLIDAR-Tech. Spec. for
LBCWARR Clause No. 15-5 and 15-6
a 450mm (for irrigation purpose) rm 60.00 6,461.78 387,706.79
b 600mm rm 90.00 7,485.99 673,739.19
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Pay
Amount
Item Description Unit Quantity Rate (NRs.)
(NRs.)
No.
c 900mm rm 217.50 14,001.05 3,045,229.14
5.8 Supply & place100 mm Dia. HDPE Pipe (6 rm 294.00 545.57 160,397.46
kg/cm2) for weep hole as per Nepal
Standard & directed by Engineer
5.9 Supply & place Heavy Duty Steel pipe (Dia rm 296.00 321.87 95,273.66
50 mm) for railing as per Nepal Standard &
directed by the Engineer
5.10 Backfilling works with approved soil m3 3,131.24 1,177.58 3,687,280.19
materials with compaction as per
DoLIDAR-Tech. Spec. for LBCWARR
Clause No-2.5.4
5.11 Supply and Place graded filter in backfilling m3 389.85 1,894.44 738,541.59
in structures and cross drainage works as
per (DOR-SSRBW Section No.: 2404,3110)
Sub-Total 18,624,795.16
6 Pavement Works
6.1 Preparation of subgrade for rehabilitation m2 63,748.40 15.88 1,012,275.87
works as per DoR-SSRBW (Standard
Specification for Road & Bridge Works,
2001) SECTION No.1003
6.2 Providing, laying, spreading, watering, m3 7,616.84 1,907.98 14,532,805.75
leveling and compaction of natural sand
gravel sub base grading as specified and
according to the designed camber all
complete as per DoR-SSRBW SECTION
No. 1201
6.3 Providing, laying, spreading, watering, m3 912.83 1,599.93 1,460,473.05
leveling and compaction of capping layer of
approved materials according to the
designed camber all complete asper DoR-
SSRBW, Section 1004
6.4 Supplying and preparing 20 cm thick stone m3 391.86 1,819.70 713,071.99
pitching work on the prepared granular
bedding with stone available at site
6.5 Providing, laying, spreading, watering, m3 2,426.83 1,907.98 4,630,348.93
leveling and compaction of 12 cm thick
natural sand gravel sub base grading for
cobble pavement as specified and according
to the designed camber all complete as per
DoR-SSRBW SECTION No. 1201
6.6 Supplying and preparation of 5 cm thick m2 20,223.58 67.83 1,371,684.21
granular material and sand with mixing red
soil and spreading in layer, watering,
compacting and all complete.
6.7 Supplying and construction of 8 cm thick m3 1,617.89 951.82 1,539,933.65
coble pavement ( Breaked Coble ) on the
prepared granular material bedding with
spreading the spall/ Granular material and
compacting with Steel Roller with all
complete
6.8 Breaking and supplying of rock for cobble m3 1,617.89 1,305.10 2,111,496.54
manually and chisel dressing it in the 8 cm
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Pay
Amount
Item Description Unit Quantity Rate (NRs.)
(NRs.)
No.
sizes with all complete
Sub-Total 27,372,089.99
7 Road Furniture/Traffic Sign Boards
7.3 Supplying and placing standard RCC Nos. 2.00 2,732.21 5,464.42
kilometer post (place at each km) all
complete including painting, and writing
etc. all complete as per specification and
drawings (DOR-SSRBW SECTION No.
1501)
7.4 Supplying and placing standard RCC Nos. 10.00 6,104.90 61,049.02
kilometer post (place at 5km interval ) all
complete including painting, and writing
etc. all complete as per specification and
drawings (DOR-SSRBW SECTION No.
1501)
7.5 Supplying and fixing in place R.C.C. Nos. 2,350.00 1,210.96 2,845,766.69
delineator and guard post including
excavation, painting, and erection etc. all
complete as final drawing (DOR-SSRBW
SECTION No. 1504)
7.1 Supplying and erecting traffic sign in place
including 50 mm dia steel tube, 2mm thick
steel plate, cement concrete, painting,
writing and supporting steel angle nut and
bolt etc complete as per DoR-SSRBW
SECTION No. 1501)
a 60 cm dia circular, 60 cm equilateral triangle Nos. 70.00 1,631.03 114,172.10
and 60 x 45 cm rectangular shaped sign
(Single post)
b 1.2m x 0.75 m size bigger traffic sign with Nos. 44.00 3,253.20 143,140.92
back support and two or more post
Sub-Total 3,169,593.15
8 Bio-engineering Work
8.1 Slope trimming work DoLIDAR : 4 Spec. m2 400.00 62.79 25,116.00
Clause No.: 2-1.3.2,2-1.8 and 2-1.95
8.2 Construction of Rip-rap drain with the rm 100.00 481.81 48,180.76
stone pitching work of 20 cm thick and 1.2
m wide as per DoLIDAR-Tech. Spec. for
LBCWARR Clause No. 8
8.3 Dry stone check/toe walls for m3 582.40 2,540.93 1,479,837.95
segmentation and support of slopes
DoLIDAR Tech. Spec. clause No. 8
8.4 Brush layering work: including preparation rm 500.00 100.28 50,142.44
of terraces of 30 - 40 cm wide and laying
live cuttings of selected Species along the
terrace @ 5 cm c/c with 2/3 of cuttings in
to terrace and leaving one bud and up to
1/3 of the cuttings sticking beyond the
terrace edge
( Cutting can be of assuro, simali etc of 45
- 60 m length) DoLIDAR Spec. Clause
no.70-6.7 b
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Pay
Amount
Item Description Unit Quantity Rate (NRs.)
(NRs.)
No.
8.5 Planting rooted grass slips on slopes < 45˚ m2 400.00 198.90 79,559.30
including preparation of slips on site.
Operation includes digging planting holes
to a maximum of 5 cm depth with metal or
hardwood peg, depending on nature of soil.
The planting drills should be spaced 10 cm
apart as per Bio engineering information of
DOR
8.6 Planting containerized tree and shrub Nos. 27.00 59.08 1,595.19
seedlings, including pitting, transplanting,
composting and placing tree guards, on toe
of embankment slopes in plain areas, not
less than 8 m from the road center line. Pit
size 30 cm diameter×30 cm depth.
Compost volume ⅟₄ of the volume of pit,
mixed with original soil as per Bio
engineering information of DOR
Sub-Total 1,684,431.65
9 Day works
9.1 Supply of labour as required as per
preamble and as instructed by the Engineer.
b) Skilled labour day 150 640.00 96,000.00
c) Unskilled labour day 400 455.00 182,000.00
9.2 Supply of excavator for maintenance of hr 180 1,000.00 180,000.00
road as required and instructed by engineer
Sub-Total 458,000.00
Total Base Cost 157,505,597.66
13% VAT 20,475,727.70
Sub Total 177,981,325.36
Per Km Cost (Including Base Cost and 15,649,461.48
VAT)
Work Charge Staff and Small 4,725,167.93
Miscellaneous Expenses @ 3.0%
Physical Contingency @10% 15,750,559.77
Grand Total 198,457,053.06
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail
Annex 6: Summary of Quantities
Package 1
S No. Description Unit Total
1 General
1.1 Insurance of works, plants, materials, loss and damage to equipment, L.S. 1.00
Contractor's workmen and employees and third party insurance against
damage to other persons and property as per GCC clause 13.
1.2 Provide site office at mid-section of the road having rooms size: 3m*4m mth 18.00
each at location acceptable to the project manager within the contract
package with accommodation facilities as specified in special provision .
1.3 Carry out additional tests for material and works as required and PS 1.00
instructed by the Engineer.(GCC Clause No. 33.1)
1.4 Relocation of the utilities (water supply, telephone, etc,) and services as PS 1.00
instructed by the Engineer as per DoLIDAR-Technical Specifications
for Labour Based Construction Work of Agricultural & Rural Roads
(Tech. Spec. for LBCWARR Clause No. G-10.
1.5 Carry out maintenance of the existing road to keep the road serviceable mth 18.00
throughout the contract period. Also provide and maintain traffic safety,
control measures and temporary diversions during construction including
water spraying thrice a week to avoid dust pollution as per DoLIDAR-
Tech. Spec. for LBCWARR Clause No. G-12.
1.6 Supply and provide rental Four Wheel Drive Double cap Pickup Vehicle mth 18.00
with full option including fuel, driver' wages, major & minor
maintenances etc for the Engineer for supervision works as specified
1.7 Provide and installation of project information board of size 1.80 mx1.2 No. 3.00
m along with iron posts including excavation, concreting, backfilling etc
all complete as per DoR Standard Specification for Road and Bridge
Works (SSRBW) July 2001,Section-108
1.8 Provision and maintenance of labour camps payable monthly in equal mth 18.00
instalments as per DoR Standard Specification for Road and Bridge
Works (SSRBW) July 2001,Section-109 (3)
1.9 Establish, maintain and operate laboratory at the site with equipment mth 18.00
furnishing required for testing specified quality of the materials as per
DoR-SSRBW, Section-511
1.10 Environmental Mitigation Works as Instructed by the Engineer(DOR P.S. 1.00
Section 109)
1.11 Social Compliance and safeguards as instructed by the Engineer(DOR P.S. 1.00
Section 109)
2 Site Clearance
2.1 Clearing and Grubbing including cutting of all types of plants as per Sqm 64,000.00
DoLIDAR-Technical Specifications for Labour Based Construction of
Agricultural and Rural Roads (Tech. Spec. for LBCWARR) Clause No.:
1-1.5(a), 1-1.5(b) & 1-1.6
3 Earthwork
3.1 Excavation in roadway and drain in all types of soil and rock materials Cum 73,936.36
including removal and satisfactory disposal of all materials at approved
environmentally safe tipping area as per DoLIDAR-Tech. Spec. for
LBCWARR Clause No. 2-1
Sunkhani - Kanpa Road – Dolakha
Rehabilitation and Reconstruction Project
Engineering Survey, Design and Cost Estimate – Main Report Detail