Professional Documents
Culture Documents
Lecture-6 - Project Planning Technique
Lecture-6 - Project Planning Technique
• Need leadership
• Starting Date
• Specific Goals and Conditions
• Defined responsibilities
• A Budget
• A Planning
• A fixed end date
• Parties involvement
C = f (P, T, S)
Time
Expectations
Cost Scope
Within Budget
Performance
Project Stakeholders
Project Manager
Customer
Performing Organization
Project Team members
Sponsor
Examples of Project …
1. Concept Phase
2. Planning Phase
3. Implementation Phase
4. Termination Phase
CDEF
Overall 85% effort and 40% time of the overall project is consumed
during the implementation phase, whereas planning phase consume 9%
efforts and 30% of time.
Classification of Projects
Classification of Projects…cont.
Classification of Projects…cont.
Classification of Projects…cont.
Level 2
1.1 1.2 1.3 1.4 1.5 1.6
1.3.1
1.1.1 Create 1.2.1 Make 1.4.1 Make 1.5.1 Hire
Identify Site/ 1.6.1 Invite
Plan Menu Guest List Shoppers
Room
1.2.2
1.4.2
1.1.2 Make Create 1.3.2 Set up 1.5.2 Hire 1.6.2
Receive
Budget Shopping Tables/Chairs Cooks Transport
RSVPs
List
1.1.3 Prepare 1.6.3
1.3.3 Lay out 1.4.3 Create 1.5.3 Hire
Disbursements/ 1.2.3 Shop Coordinate
Settings/Utensils Name Tags Servers
Reconciliation Topics
1.1.4
1.4.4 Review 1.5.4 Hire 1.6.4 Backup
Coordinate 1.2.4 Cook 1.3.4 Decorate
Special Needs Hosts for No-shows
Activities
Automobile WBS
Design Level 5
Work Packages Build
Test
Project Management
Project Planning:
1. Setting goals.
2. Defining the project.
3. Tying needs into timed project activities.
4. Organizing the team.
Project Scheduling:
1. Tying resources to specific activities.
2. Relating activities to each other.
3. Updating and revising on regular basis.
Before Project
Project Controlling:
During Project 1. Monitoring resources, costs, quality and
budgets.
2. Revising and changing plans.
3. Shifting resources to meet demands.
Project Planning…
Gantt Chart
Q?
Given the large number of tasks in a project, it is easy
to see why the following questions are important
1. When will the entire project be completed?
2. What are the critical activities or tasks in the project,
that is, the ones that will delay the entire project if
they are late?
3. Which are the non
non--critical activities, that is, the ones
that can run late without delaying the entire project’s
completion?
4. If there are three time estimates, what is the
probability that the project will be completed by a
specific date?
Q?
• Event
• Signals the beginning or ending of an activity
• Designates a point in time
• Represented by a circle (node)
• Network
• Shows the sequential relationships among activities using
nodes and arrows
Activity-on-node (AON)
nodes represent activities, and arrows show
precedence relationships
Activity-on-arrow (AOA)
arrows represent activities and nodes are events for
points in time
Activity-on-Node (AON):
• Uses nodes to represent the activity
• Uses arrows to represent precedence relationships
ANC
Example of PERT/CPM
ANC
Example of PERT/CPM
• Activities and immediate predecessors for ANC Inc.
IMMEDIATE
ACTIVITY DESCRIPTION
PREDECESSORS
A Build internal components —
B Modify roof and floor —
C Construct collection stack A
D Pour concrete and install frame B
E Build high-temperature burner C
F Install control system C
G Install air pollution device D, E
H Inspect and test F, G
ANC
Example of PERT/CPM
A C F
Build Internal Construct Collection Install Control
Components Stack System
E H
Start Inspect Finish
Build Burner
and Test
B D G
Modify Roof Pour Concrete and Install Pollution
and Floor Install Frame Device
Time Activity
Time Activity
Probability of 1 in 100
of b Occurring
Activity Time
Most Most Most
Optimistic Likely Pessimistic
Time Time Time
(a) (m) (b)
Time Activity
Time Activity
A 2 C 2 F 3
E 4 H 2
Start Finish
B 3 D 4 G 5
• In the nodes, the activity time and the early and late start
and finish times are represented in the following manner
ACTIVITY t
ES EF
LS LF
EXPECTED
MOST TIME,
OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2
A t=2
ES = 0 EF = 0 + 2 = 2
Start
B t=3
ES = 0 EF = 0 + 3 = 3
EXPECTED
MOST TIME,
OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2
A 2 C 2 F 3
0 2 2 4 4 7
E 4 H 2
Start 4 8 13 15 Finish
B 3 D 4 G 5
0 3 3 7 8 13
EXPECTED
MOST TIME,
A 2 C 2 F 3 OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2
0 2 2 4 4 7
A 1 2 3 2 4/36
B 2 3 4 3 4/36
C 1 2 3 2 4/36
E 4 H 2
D 2 4 6 4 16/36
Start 4 8 13 15 Finish
E 1 4 7 4 36/36
F 1 2 9 3 64/36
G 3 4 11 5 64/36
B 3 D 4 G 5
0 3 3 7 8 13 H 1 2 3 2 4/36
25
EXPECTED
MOST TIME,
OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2
A 1 2 3 2 4/36
A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
Slack!
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
B 0 3 1 4 1 No
C 2 4 2 4 0 Yes
D 3 7 4 8 1 No
E 4 8 4 8 0 Yes
F 4 7 10 13 6 No
G 8 13 8 13 0 Yes
H 13 15 13 15 0 Yes
A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
CPM
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
CPM of ANC Inc.
A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
EXPECTED
MOST TIME,
Probability of Project
OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2
A 1 2 3 2 4/36
Completion B 2 3 4 3 4/36
C 1 2 3 2 4/36
D 2 4 6 4 16/36
E 1 4 7 4 36/36
F 1 2 9 3 64/36
G 3 4 11 5 64/36
ACTIVITY VARIANCE
H 1 2 3 2 4/36
A 4/36 25
B 4/36
C 4/36
D 16/36
E 36/36
F 64/36
G 64/36
H 4/36
15 16
Time
Weeks Weeks
CPM PERT
It defines Critical Path Method It denotes Programme Evaluation
and Review Technique
It was first developed by DuPont It was first developed by NASA
for its Chemical Plant Project for its ballistic missiles project
It uses deterministic time It uses probabilistic time
approach approach
It is based on assumption that It uses three time estimates.
exact time of any activity is Optimistic, most likely and
known pessimistic
It does not consider any It can measure the probability of
probabilistic aspect project completion in some
practical time
Some Definitions
Exercise
Backward Pass
A 2 B 1 E 4
0 2 2 3 3 7
0 2 9 10 10 14
C 6 D 6
2 8 8 14
2 8 8 14
F 2
2 4
12 14
H 2 G 3
0 2 14 17
12 14 14 17
Summary of Float
CPM Exercise
C = Cost
C = f (P, T, S) P = Performance
T = Time
S = Scope
Assumptions:
Once started a work package is performed continuously until it
is finished
The cost associated with a work package are spread evenly
throughout its duration
Cost Overrun =
[Actual Expenditures to Date] - [Value of Work to Date]
Corrective Actions:
If a project is found to be
Behind the schedule and or
Experiencing cost overruns
problem activities.
A 2 C 2 F 3
0 2 2 4 4 7
system
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5