Download as pdf or txt
Download as pdf or txt
You are on page 1of 40

23-Jun-20

CE 4023 Construction Practices and


Management
Md. Ashraful Alam
Assistant Professor, Department of CE, UU

Project and its Characteristics

A project is a temporary endeavor involving a connected sequence


of activities and a range of resources, which is designed to achieve
a specific and unique outcome and which operates within time,
cost and quality constraints and which is often used to introduce
change.
Characteristic of a project
• A unique, one-time operational activity or effort

• Requires the completion of a large number of interrelated


activities
• Established to achieve specific objective

• Resources, such as time and/or money, are limited


• Typically has its own management structure

• Need leadership

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Difference Between Project and Operation


Project Mngt Operation Mngt
Non--repetitive
Non Repetitive
Multi-skilled or very highly
Multi- Limited skills, a huge learning
specialized workforce effect
Scope, performance, time Profit generated, cost reduced
and cost quality of product/services
Subcontracting is essential Generally avoided
Very high risk as generally Generally avoided, use of
no chance of recursion improvement always here
Fixed, ceases with Continuous in nature
assignment Maintenance of existing things
Creation of new thing

Important Aspects of a Project:

• Starting Date
• Specific Goals and Conditions
• Defined responsibilities
• A Budget
• A Planning
• A fixed end date
• Parties involvement

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Objectives of Project Management

Dependent on all the 3


Fixed tenure Start to End attributes

C = f (P, T, S)
Time
Expectations

Cost Scope
Within Budget

Performance

Service achieved upto


expectation

Project Stakeholders

Project stakeholders are individuals and organizations that


are actively involved in a project or whose interest may be
+ve/--ve ly affected as a result of project execution or project
+ve/
completion..
completion

Key Stakeholders are:

Project Manager
Customer
Performing Organization
Project Team members
Sponsor

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Examples of Project …

Can this be a project?

Project and its Characteristics …cont

• Most realistic projects are large and complex


• Tens of thousands of steps and millions of dollars may be
involved
• Managing large-scale, complicated projects effectively is a
difficult problem and the stakes are high
• The first step in planning and scheduling a project is to
develop the work breakdown structure (WBS)
• Time, cost, resource requirements, predecessors, and
people required are identified for each activity
• Then a schedule for the project can be developed

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Project Life cycle and its Phases

A project has 4 phases

1. Concept Phase
2. Planning Phase
3. Implementation Phase
4. Termination Phase

CDEF

Overall 85% effort and 40% time of the overall project is consumed
during the implementation phase, whereas planning phase consume 9%
efforts and 30% of time.

Project Life Cycle and its phases

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Influence of Change Vs Cost of Change

Risky aspects of a project. As the project progress, the cost to make


change increases drastically and value addition becomes difficult

Classification of Projects

On the basis of duration, quantum of investment, ownership


nature and risk involvement.

Project Classification based on Risks

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Classification of Projects…cont.

Greenfield Project: Totally a new venture by a fresh


entrepreneur/promoter
Brownfield Project: An existing project goes for addition of
product/capacity. This is 3 types:
a. Expansion Project: An increase in the capacity of existing
plant/project without any other change. Example; A biscuit
industry increasing its capacity from 20 MT/month to 35
MT/month
b. Vertical Integration: When a firm owns its upstream
supplier and downstream customers
i. Forward integration - from construction firm to real estate company
ii. Backward integration – from steel pipe industry plans to manufacture
its raw materials i.e. steel

Classification of Projects…cont.

Diversification Project: By combining two firms one with


better financial resource but poor technical capabilities and
another firm with strong technical capabilities but poor
financial resources (obtain financial synergy). The objective
is to reduce risk in operations.
I. Concentric diversification: The goal is to achieve a complete
range of products. Example; Honda from car to motorcycle
manufacturing.
II. Conglomerate diversification: When a firm diversifies into
areas that are unrelated to its current line of business. This is
due to limited opportunity in the current line of business.
Example; Merger and Acquisitions due to short time to enter
in a new business. Tata entering into consultancy business.

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Classification of Projects…cont.

Divestment Project: Retrenchment of some or all of the


activities in a given business of the firm or sells out some of
the businesses as such. It involves redefining of business.
Causes are:
Obsolescence of product/service
Increase level of competition
Better opportunity of investment
Increased concentration on fewer project lines

Reasons for Project Failure

In general but not limited to the following list:


1. Poorly defined scope/objectives
2. Underestimated time and cost
3. Large project planning
4. Improper technology selection
5. Defective planning process

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Work Breakdown Structure

Work Breakdown Structure (WBS)

Project must be divided into manageable tasks and then logically


order
The definition of tasks and their sequences is referred as the Work
Breakdown Structure (WBS)
WBS is essential in Planning and executing the Project.

• A method of breaking down a project into individual elements


• It defines tasks that can be completed independently of other
tasks, facilitating resource allocation, assignment of
responsibilities and measurement and control of the project
• It is the foundation of project planning
• It is developed before identification of dependencies and
estimation of activity durations

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Work Breakdown Structure (WBS)

WBS Example - Banquet


Banquet WBS
Provide
Level 1 1.0
Banquet

Level 2
1.1 1.2 1.3 1.4 1.5 1.6

Plan and Room and


Dinner Guests Staff Speakers
Supervise Equipment

1.3.1
1.1.1 Create 1.2.1 Make 1.4.1 Make 1.5.1 Hire
Identify Site/ 1.6.1 Invite
Plan Menu Guest List Shoppers
Room
1.2.2
1.4.2
1.1.2 Make Create 1.3.2 Set up 1.5.2 Hire 1.6.2
Receive
Budget Shopping Tables/Chairs Cooks Transport
RSVPs
List
1.1.3 Prepare 1.6.3
1.3.3 Lay out 1.4.3 Create 1.5.3 Hire
Disbursements/ 1.2.3 Shop Coordinate
Settings/Utensils Name Tags Servers
Reconciliation Topics

1.1.4
1.4.4 Review 1.5.4 Hire 1.6.4 Backup
Coordinate 1.2.4 Cook 1.3.4 Decorate
Special Needs Hosts for No-shows
Activities

Level 3 1.3.5 Prepare


1.2.5 Serve 1.5.5 Hire 1.6.5 Send
Equipment, Pots,
Dinner Cleanup Thank Yous
Etc.

Work Breakdown Structure (WBS)

Automobile WBS

Building a Car Level 1

Chassis Body Powertrain Electrical Level 2

Engine Transmission Level 3

Block Pistons Oil Pan Level 4

Design Level 5
Work Packages Build

Test

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

WBS is more than…


Once the WBS has been drawn, a bottom-up cost estimate can
be produced starting at the lowest branch of the family tree. In
this method, each work package is costed and arranged in such
a way that the total cost of the packages on any branch must
add up to the cost of the package of the parent package on the
branch above

WBS Work Package – Level of Detail

• WHO will be the responsible individual or organization?


• How much TIME will the activity take?
• What COST is associated with accomplishing the activity?
• Can PROGRESS be tracked easily?
All the questions need clear answers for proper project
planning.

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Project Management

• It is nothing more (or less) than knowing what


the status of a project is:
☺ when it should be done
☺ how much (and if) it has slipped from the
original schedule
☺ what the bottlenecks are
☺ what you might drop to save some time

Project Management Models History

• One of the earliest techniques was the Gantt chart


(used by US Navy).
• This type of chart shows the start and finish times
of one or more activities, as shown below:

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Project Planning, Scheduling & Controlling

Project Planning:
1. Setting goals.
2. Defining the project.
3. Tying needs into timed project activities.
4. Organizing the team.
Project Scheduling:
1. Tying resources to specific activities.
2. Relating activities to each other.
3. Updating and revising on regular basis.

Before Project
Project Controlling:
During Project 1. Monitoring resources, costs, quality and
budgets.
2. Revising and changing plans.
3. Shifting resources to meet demands.

Project Planning…

• Resource Availability and/or Limits


• Due date, late penalties, early completion
incentives
• Budget
• Activity Information
• Identify all required activities
• Estimate the resources required (time) to complete
each activity
• Immediate predecessor(s) to each activity needed
to create interrelationships

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Project Scheduling and Control


Techniques

Gantt Chart

Critical Path Method (CPM)


Program Evaluation and Review Technique (PERT)

PERT and CPM

• The program evaluation and review technique (PERTPERT)


and the critical path method (CPM
CPM) are two popular
quantitative analysis techniques to help plan, schedule,
monitor, and control projects
• They were developed because there was a critical
need for a better way to manage.
• Originally the approaches differed in how they estimated
activity times
• PERT used three time estimates to develop a
probabilistic estimate of completion time
• CPM was a more deterministic technique
• They have become so similar they are commonly
considered one technique, PERT/CPM

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

From project networks, we determine

• The project duration


• The critical path
• Tasks on the critical path
• Tasks not on the critical path
• Slack or float associated with non-critical
tasks
• Earliest start, earliest finish, latest start
and latest finish times

Six Steps of PERT/CPM

1. Define the project and all of its significant activities or


tasks
2. Develop the relationships among the activities and decide
which activities must precede others
3. Draw the network connecting all of the activities
4. Assign time and/or cost estimates to each activity
5. Compute the longest time path through the network; this is
called the critical path
6. Use the network to help plan, schedule, monitor, and
control the project
 The critical path is important since any delay in these
activities can delay the completion of the project

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Q?
Given the large number of tasks in a project, it is easy
to see why the following questions are important
1. When will the entire project be completed?
2. What are the critical activities or tasks in the project,
that is, the ones that will delay the entire project if
they are late?
3. Which are the non
non--critical activities, that is, the ones
that can run late without delaying the entire project’s
completion?
4. If there are three time estimates, what is the
probability that the project will be completed by a
specific date?

Q?

5. At any particular date, is the project on schedule,


behind schedule, or ahead of schedule?
6. On any given date, is the money spent equal to, less
than, or greater than the budgeted amount?
7. Are there enough resources available to finish the
project on time?
8. If the project is to be finished in a shorter amount of
time, what is the best way to accomplish this at the
least cost?

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Drawing the PERT/CPM Network

• There are two common techniques for drawing PERT


networks
• Activity
Activity--on-
on-node (AON
AON) where the nodes represent
activities
• Activity
Activity--on-
on-arc (AOA
AOA) where the arcs are used to represent
the activities
• The AON approach is easier and more commonly found in
software packages
• One node represents the start of the project, one node for
the end of the project, and nodes for each of the activities
• The arcs are used to show the predecessors for each
activity

Drawing the PERT/CPM Network…(some Basics)

• Use of nodes and arrows


• Arrows  An arrow leads from tail to head directionally
• Indicate ACTIVITY, a time consuming effort that is required to
perform a part of the work.
• Nodes  A node is represented by a circle
• Indicate EVENT, a point in time where one or more activities start
and/or finish.
• Activity
• A task or a certain amount of work required in the project
• Requires time to complete
• Represented by an arrow
• Dummy Activity
• Indicates only precedence relationships
• Does not require any time of effort

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Drawing the PERT/CPM Network…(some Basics)

• Event
• Signals the beginning or ending of an activity
• Designates a point in time
• Represented by a circle (node)
• Network
• Shows the sequential relationships among activities using
nodes and arrows
Activity-on-node (AON)
nodes represent activities, and arrows show
precedence relationships
Activity-on-arrow (AOA)
arrows represent activities and nodes are events for
points in time

Situations in Network Diagram


B
A
A must finish before either B or C
C can start
A
C
Both A and B must finish before C
B can start
A
C Both A and b must finish before
B either of C or D can start
D
A B
A must finish before B can start
Dummy
both A and C must finish before D can
C start
D

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Situations in Network Diagram

Activity-on-Node (AON):
• Uses nodes to represent the activity
• Uses arrows to represent precedence relationships

Interpreting Network into Bar Chart

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

ANC
Example of PERT/CPM

• ANC, Inc. has long been trying to avoid the expense of


installing air pollution control equipment
• The local environmental protection group has recently given
the foundry 16 weeks to install a complex air filter system on
its main smokestack
• ANC was warned that it will be forced to close unless the
device is installed in the allotted period
• They want to make sure that installation of the filtering system
progresses smoothly and on time

ANC
Example of PERT/CPM
• Activities and immediate predecessors for ANC Inc.

IMMEDIATE
ACTIVITY DESCRIPTION
PREDECESSORS
A Build internal components —
B Modify roof and floor —
C Construct collection stack A
D Pour concrete and install frame B
E Build high-temperature burner C
F Install control system C
G Install air pollution device D, E
H Inspect and test F, G

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

ANC
Example of PERT/CPM

• Network for ANC Inc.

A C F
Build Internal Construct Collection Install Control
Components Stack System

E H
Start Inspect Finish
Build Burner
and Test

B D G
Modify Roof Pour Concrete and Install Pollution
and Floor Install Frame Device

Time Activity

• The time estimates in PERT are


Optimistic time (aa) = time an activity will take if
everything goes as well as
possible. There should be only a
small probability (say, 1/100) of this
occurring.
Pessimistic time (b
b) = time an activity would take
assuming very unfavorable
conditions. There should also be
only a small probability that the
activity will really take this long.
Most likely time (m
m) = most realistic time estimate to
complete the activity

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Time Activity

• PERT often assumes time estimates follow a beta probability


distribution
• The beta probability distribution is often used when there is no
solid historical data upon which to activity time base estimates
• Found to be appropriate in many cases for determining an
expected value and variance for activity completion times
Probability of 1 in 100
of a Occurring
Probability

Probability of 1 in 100
of b Occurring

Activity Time
Most Most Most
Optimistic Likely Pessimistic
Time Time Time
(a) (m) (b)

Time Activity

• To find the expected activity time (tt), the beta distribution


weights the estimates as follows
a  4m  b
t
6

• To compute the dispersion or variance of activity


completion time,
time we use the formula
2
ba
Variance   
 6 

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Time Activity

• Time estimates (weeks) for ANC Inc.


EXPECTED
MOST TIME,
OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2
A 1 2 3 2 4/36
B 2 3 4 3 4/36
C 1 2 3 2 4/36
D 2 4 6 4 16/36
E 1 4 7 4 36/36
F 1 2 9 3 64/36
G 3 4 11 5 64/36
H 1 2 3 2 4/36
25

How to find Critical Path?

• We accept the expected completion time for each task as the


actual time for now
• The total of 25 weeks in Table does not take into account the
obvious fact that some of the tasks could be taking place at the
same time
• To find out how long the project will take we perform the
critical path analysis for the network
• The critical path is the longest path through the network

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

How to find Critical Path?

• ANC’s network with expected activity times

A 2 C 2 F 3

E 4 H 2
Start Finish

B 3 D 4 G 5

How to find Critical Path?

• To find the critical path, need to determine the following


quantities for each activity in the network

1. Earliest start time (ES


ES): the earliest time an activity can begin
without violation of immediate predecessor requirements
2. Earliest finish time (EF
EF): the earliest time at which an activity can
end
3. Latest start time (LS
LS): the latest time an activity can begin without
delaying the entire project
4. Latest finish time (LF
LF): the latest time an activity can end without
delaying the entire project

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

How to find Critical Path?

• In the nodes, the activity time and the early and late start
and finish times are represented in the following manner

ACTIVITY t
ES EF
LS LF

• Earliest times are computed as


Earliest finish time = Earliest start time
+ Expected activity time
EF = ES + t
Earliest start = Largest of the earliest finish times of
immediate predecessors
ES = Largest EF of immediate predecessors

EXPECTED
MOST TIME,
OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2

How to find Critical Path? A


B
1
2
2
3
3
4
2
3
4/36
4/36
C 1 2 3 2 4/36
D 2 4 6 4 16/36
E 1 4 7 4 36/36
F 1 2 9 3 64/36
G 3 4 11 5 64/36
H 1 2 3 2 4/36
25

• At the start of the project we set the time to zero


• Thus ES = 0 for both A and B

A t=2
ES = 0 EF = 0 + 2 = 2

Start

B t=3
ES = 0 EF = 0 + 3 = 3

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

EXPECTED
MOST TIME,
OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2

How to find Critical Path? A


B
1
2
2
3
3
4
2
3
4/36
4/36
C 1 2 3 2 4/36
D 2 4 6 4 16/36
E 1 4 7 4 36/36
F 1 2 9 3 64/36
• ANC’s ES and EF times G 3 4 11 5 64/36
H 1 2 3 2 4/36
25

A 2 C 2 F 3
0 2 2 4 4 7

E 4 H 2
Start 4 8 13 15 Finish

B 3 D 4 G 5
0 3 3 7 8 13

EXPECTED
MOST TIME,
A 2 C 2 F 3 OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2
0 2 2 4 4 7
A 1 2 3 2 4/36
B 2 3 4 3 4/36
C 1 2 3 2 4/36
E 4 H 2
D 2 4 6 4 16/36
Start 4 8 13 15 Finish
E 1 4 7 4 36/36
F 1 2 9 3 64/36
G 3 4 11 5 64/36
B 3 D 4 G 5
0 3 3 7 8 13 H 1 2 3 2 4/36
25

• Latest times are computed as

Latest start time = Latest finish time


– Expected activity time
LS = LF – t

Latest finish time = Smallest of latest start times


for following activities
LF = Smallest LS of following activities
 For activity H
LS = LF – t = 15 – 2 = 13 weeks

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

EXPECTED
MOST TIME,
OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2
A 1 2 3 2 4/36

How to find Critical Path? B 2 3 4 3 4/36


C 1 2 3 2 4/36
D 2 4 6 4 16/36
E 1 4 7 4 36/36
• ANC’s LS and LF times F 1 2 9 3 64/36
G 3 4 11 5 64/36
H 1 2 3 2 4/36
25

A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13

E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15

B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13

How to find Critical Path?

• Once ES, LS, EF, and LF have been determined, it is a simple


matter to find the amount of slack time/float that each activity has

Slack = LS – ES, or Slack = LF – EF

• From Table, we see activities A, C, E, G, and H have no slack time


• These are called critical activities and they are said to be on the
critical path
• The total project completion time is 15 weeks
• Industrial managers call this a boundary timetable

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
Slack!
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15

B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13

EARLIES EARLIES LATEST LATEST ON


T START, T FINISH, START, FINISH, SLACK, CRITICAL
ACTIVITY ES EF LS LF LS – ES PATH?
A 0 2 0 2 0 Yes

B 0 3 1 4 1 No

C 2 4 2 4 0 Yes

D 3 7 4 8 1 No

E 4 8 4 8 0 Yes

F 4 7 10 13 6 No

G 8 13 8 13 0 Yes

H 13 15 13 15 0 Yes

A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
CPM
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15

B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
CPM of ANC Inc.

A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13

E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15

B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Probability of Project Completion

• The critical path analysis helped determine the expected project


completion time of 15 weeks
• But variation in activities on the critical path can affect overall
project completion, and this is a major concern
• If the project is not complete in 16 weeks, the foundry will have to
close
• PERT uses the variance of critical path activities to help determine
the variance of the overall project

Project variance = ∑ variances of activities


on the critical path

EXPECTED
MOST TIME,

Probability of Project
OPTIMISTIC PROBABLE PESSIMISTIC t = [(a + 4m + VARIANCE
ACTIVITY a m b b)/6] [(b – a)/6]2
A 1 2 3 2 4/36

Completion B 2 3 4 3 4/36
C 1 2 3 2 4/36
D 2 4 6 4 16/36
E 1 4 7 4 36/36
F 1 2 9 3 64/36
G 3 4 11 5 64/36
ACTIVITY VARIANCE
H 1 2 3 2 4/36
A 4/36 25

B 4/36
C 4/36
D 16/36
E 36/36
F 64/36
G 64/36
H 4/36

 Hence, the project variance is

Project variance = 4/36 + 4/36 + 36/36 + 64/36 + 4/36 = 112/36 = 3.111

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Probability of Project Completion

Project standard deviation   T  Project variance


 3.11  1.76 weeks
• We assume activity times are independent and total project
completion time is normally distributed
• The project’s expected completion date is 15 weeks.
• Assume that the total project completion time follows a normal
probability distribution
• Chart tells us that there is a 50% chance of completing the entire
project in less than 15 weeks and a 50% chance it will exceed 15
weeks
Standard
Deviation = 1.76
Weeks

Probability of Project Completion

• The standard normal equation can be applied as follows

Due date  Expected date of completion


Z
T
16 weeks  15 weeks
  0.57
1.76 weeks

• From Probability Distribution Table we find the probability


of 0.71566 associated with this Z value
• That means there is a 71.6% probability this project can be
completed in 16 weeks or less

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Probability of Project Completion

• Probability of ANC Inc meeting the 16-week deadline

Expected Time is 0.57 Standard


15 Weeks Deviations
Probability
(T ≤ 16 Weeks)
is 71.6%

15 16
Time
Weeks Weeks

Summary of CMP and PERT

CPM PERT
It defines Critical Path Method It denotes Programme Evaluation
and Review Technique
It was first developed by DuPont It was first developed by NASA
for its Chemical Plant Project for its ballistic missiles project
It uses deterministic time It uses probabilistic time
approach approach
It is based on assumption that It uses three time estimates.
exact time of any activity is Optimistic, most likely and
known pessimistic
It does not consider any It can measure the probability of
probabilistic aspect project completion in some
practical time

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Some Definitions

Network: Network is a diagrammatic representation of


various activities showing their interdependencies and
dependencies, without drawing on scale. Network is the
most commonly used tool for planning and controlling any
project.
Critical Activities: The activities which are crucial for
completion of a project on schedule time.
Project Duration: A project is said to be completed only
when all the activities involved are completed.

Exercise

Find the critical path of those activities. Also find the


total float and free float of those

Activity Precedence Activity Duration (days)


a - 8
b - 9
c a 9
d a,b 4
e a 6
f c 5
g c,d,e 7

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Forward and Backward Pass


Forward Pass

Backward Pass

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Free Float and Total Float


Free Float:
Float: The amount of time that a schedule activity can
be delayed without delaying the early start date of any
immediately following schedule activities
Free Float = ESs – EFp - Lag
Total Float:
Float: The total amount of time that a schedule
activity may be delayed from its early start without delaying
the project finish date, or violating a schedule constraint.
It is the amount of time a task can be delayed without delaying the
project end date. Total Float = LS – ES or LF - EF
Practical Definition:
Slack or Float provide flexibility in the project schedule. When
leveraged properly, project managers can shift activities and
resources to meet the project objectives and priorities. It is the
amount of time an activity can be delayed without impacting other
activities or the project end date and changes over the course of the
project implementation

Free Float and Total Float…cont.

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Free Float Example

Free Float and Total Float

A 2 B 1 E 4
0 2 2 3 3 7
0 2 9 10 10 14

C 6 D 6
2 8 8 14
2 8 8 14

F 2
2 4
12 14

H 2 G 3
0 2 14 17
12 14 14 17

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Summary of Float

Slack and Float are the same thing. We differentiate between


Total Float and Free Float to understand the amount of delay
we can tolerate without impacting the project schedule and
successor activities, respectively.

The concept and use of float helps us keep our project on


schedule and use resources more efficiently as the project
progresses. The lack of float or its disappearance gives us
clear indication our project is out of control and corrective
measures must be taken. Additionally, by using what-
what-if
scenarios, we can understand impacts to the project.

Understanding float and its use is one industry trick of


successful project managers.

CPM Exercise

Find the completion time and critical path.

Activity Duration (mins) Predecessor


Make Menu 30 -
Shop for Ingredients 60 Make Menu
Prepare Ingredients 60 Shop for Ingredients
Prepare Appetizers 60 Shop for Ingredients
Cook Food 30 Prepare Ingredients
Wash Tableware 45 Make Menu
Set Table 15 Wash Tableware
Serve Dinner 0 Set Table, Cook Food, Prepare Appetizers

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

Keeping the Project on Track - Control

Two things to know: (1)Where


(1)Where you suppose to be and
(2) where you are
Principle: Unless you know both cost and schedule, you
have absolutely no idea where your project actually is.

C = Cost

C = f (P, T, S) P = Performance
T = Time
S = Scope

PERT – a cost accounting system

• Although PERT is an excellent method of monitoring and


controlling project length, it does not consider the very
important factor of project cost
• PERT/Cost is a modification of PERT that allows a
manager to plan, schedule, monitor, and control cost as well
as time
• PERT/Cost is an accounting information system that helps
management gauge progress against scheduled time and
cost estimates
• It is a project oriented system that is based on analyzing a
segmented project
• Each segment is a collection of work package
• When discrepancies are found between the actual progress
and the expected progress, corrective action can be taken.

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

PERT – a cost accounting system

Assumptions:
Once started a work package is performed continuously until it
is finished
The cost associated with a work package are spread evenly
throughout its duration

• Value of Work to Date = p x [Work Package Budget]


• Expected Remaining Completion Time =
(1-p) x Original Expected Completion Time

PERT – a cost accounting system

• Cost Overrun/Underrun Analysis


• For each work package (completed or in progress)
we calculate

Cost Overrun =
[Actual Expenditures to Date] - [Value of Work to Date]

Corrective Actions:
If a project is found to be
Behind the schedule and or
Experiencing cost overruns

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

PERT – a cost accounting system

Management seeks out the causes for these problems -


• Correct the project completion time or cost estimates.
• Reassess work package completion times and cost estimates.
• Identify departments or contractors that cause delays.
Possible Corrective actions, to be taken whenever needed -
• Focus on uncompleted activities.

• Determine whether crashing activities is desirable.

• In the case of cost underrun, channel more resources to

problem activities.

• Reduce resource allocation to noncritical activities

A 2 C 2 F 3
0 2 2 4 4 7

PERT – a cost accounting 0 2 2 4 10 13

system
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15

B 3 D 4 G 5

Project Completion time = 15 weeks 0


1
3
4
3
4
7
8
8
8
13
13

At the end of 10 weeks a progress assessment is made


IMMEDIATE Expenditure
ACTIVITY DESCRIPTION PREDECES (Actual) Status
SORS

A Build internal components — 2600 Finish

B Modify roof and floor — 5000 Finish

C Construct collection stack A 3000 Finish


Pour concrete and install
D B 5000 Finish
frame
Build high-temperature
E C 700 Finish
burner
F Install control system C 5600 40%

G Install air pollution device D, E 700 Finish

H Inspect and test F, G 2000 25%


Work packages to focus on

Md. Ashraful Alam, Assistant Professor,


23-Jun-20

PERT – a cost • Value of Work to Date = p x [Work Package Budget]


• Cost Overrun = [Actual value to date] –[Estimated value]
accounting
system
Project Cost Control – Cost Analysis

Work Budgeted Values Percentage Estimated Actual Cost


Package Complete Value Vaule Overrun
Time Cost
A 2 2000 100% 2000 2600 600
B 3 3000 100% 3000 5000 2000
C 2 4500 100% 4500 3000 -1500
D 4 2500 100% 2500 5000 2500
E 4 500 100% 500 700 200
F 3 13000 40% 5200 5600 400
G 5 1500 100% 1500 700 -800
H 2 6000 25% 1500 2000 500

Md. Ashraful Alam, Assistant Professor,

You might also like