Time Sheet TTB2003 - TBG309 0150121

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

TIME SHEET TB. TTB. 2003 /BG.

TBG 309
Samarinda, 15 Jan 2021
Date Working Remarks
time
29 Dec 2020 00.00-24.00 - 06.00 Proceed to jetty NCI 14.30
- 09.30 arrival and berthed at Jetty NCI
- 11.45 Commenced loading

30 Dec 2020 00.00-24.00 Loading Process 24

31 Dec 2020 00.00-24.00 - 15.30 Stop loading waiting cargo 24


- 15.30-24.00 No activity

01 Jan 2021 - 00.00-24.00 No activity 24

02 Jan 2021 - 00.00-24.00 No activity 24

03 Jan 2021 - 00.00-24.00 No activity 24

04 Jan 2021 - 00.00-24.00 No activity 24


- 15.30 Intermediate draft ttl cargo on board 4.121,726
MT

05 Jan 2021 - 00.00-08.40 No activity 24


- 08.40 Cash off
- 08.40-09.50 Shifting fm Jetty NCI to Jetty Gamaheida
- 09.50 Alongside at jetty Gamaheida
- 13.55 Continues loading
- 21.00 Stop loading due to waiting cargo
- 21.00-24.00 No activity

06 Jan 2021 16.00 Final draft 16


Total cargo loading 5.982,270MT
16.00 document Cargo on board
15 Jan 2021 - 14.00 Arrival at anchorage Bitung 10
- 14.00-24.00 No activity due to wait for shipper
instruction

16 Jan 2021 - 00.00-08.00 No activity 24


- 09.00 alongside
- 10.00 Commenced disch

17 Jan 2021 - Discharging process Process 24

18 Jan 2021 - Loading process 24


- 24.00 Completed disch

11 hr 16 jam
Keterangan :

Hari prorata : 8 Hari


Waktu berjalan di pelabuhan muat/bongkar : 11Hari 16 jam
Jumlah Demmurage : 11 Hr 16Jam – 8 hr = 3hr 16
jam

Demurrage @ Rp. 20.000.000 / Hari


perhitungan : 3 hari 16jam x Rp. 20.000.000 = Rp. 73.300.000
Terbilang : # Tujuh Puluh Tiga Juta Tiga Ratus Ribu Rupiah#
Hormat kami,

CS Agus Susanto