Urgent repairs to Bailey Bridge across Salt Creak in Km. 11/4-6 of Tallapalem -
Narayanapuram Road including painting, repairs of plates, cost and supply of bolts and nuts
SPECIFICATION REPORT
This estimate is prepared for Urgent repairs to bailey bridge including painting
of the bailey bridge and other repairs with the following provisions.
1 Painting to iron work with 2-coats of Ready Mixed First Quality Synthetic Enamel Paint of
approved brand for bailey bridge components.
2 Painting to Iron work with 2-coats of Anti Corrosive bitumen paint (Black ) grade1 of approved
brand for deck plates.
3 Supply and fixing of M.S Plates of 6 mm thick in place of damaged end deck plates over the
bailey bridge
4 Providing and fixing Cautionary/Warning sign Boards of size 900mm triangular made out of
Retro reflective sheeting of Engineering grade as per MoRT&H Specification
5 Provision for VAT @ 4%
6 Provision for Price Adjustment
7 L.S Provision for Unforeseen items, Stationery, Xerox etc. and rounding off.
The rates are adopted as per 2008-09 AP State Common SSR and as per the local minimum
market rates and the work will be carried out as per rule in force.
Executive Engineer
(R&B), Division, Machilipatnam
Dr No. 116/11-12
DETAILED CUM ABSTRACT ESTIMATE
N.W : Urgent repairs to Bailey Bridge across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road including
painting, repairs of plates, cost and supply of bolts and nuts
1 Painting to iron work with 2-coats of Ready Mixed First Quality Synthetic Enamel
Paint of approved brand and shade approved brand making 2 coats in all including
cost and conveyance of all materials to work site, all operational, incidental, labour
charges, etc. complete for finished item of work as per SS 1207 & SS 1212
For Panel(Type 1)
Chords(Channel Section) 8 3.000 2 x 0.180 8.640
Horizontals(Channel Section) 3 1.500 2 x 0.145 1.305
Cross Bars( I-Section) 8 0.950 2 x 0.290 4.408
Plates 2 0.230 0.230 0.106
" 4 0.120 0.230 0.110
(For one Panel) 14.57
For Panel(Type 2)
Chords(Channels) 4 3.000 2 x 0.180 4.320
Horizontals( Channels) 3 1.500 2 x 0.145 1.305
Cross Bars( I-Section) 8 0.950 2 x 0.290 4.408
Plates 2 0.230 0.230 0.106
" 4 0.120 0.230 0.110
(For one Panel) 10.25
Sqm
S. No Description of Item Nos L B D Quantity Rate per Amount
3 Supply and fixing of M.S Plates of 6 mm thick in place of damaged end deck plates
over the bailey bridge including cost and conveyance of all materials to site and all
labour charges for cutting to required sizes, erecting in position, welding charges
and all operational, incidental charges for fixing in position etc., complete as
directed by the engineer-in-charge.
Executive Engineer
(R&B), Division, Machilipatnam
112782
2% less
115084
Name of Work :
Urgent repairs to Bailey Bridge across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road
including painting, repairs of plates, cost and supply of bolts and nuts
DATA SHEET
1 Painting to Iron work with 2-coats of Ready Mixed First Quality Synthetic
Enamel Paint of approved brand and shade over an existing steel primer/paint
including cost and conveyance of all materials to work site, all operational, incidental,
labour charges, etc. complete for finished item of work as per SS 2207 & SS 1212
2 Painting to Iron work with 2-coats of Anti Corrosive bitumen paint (Black )
grade1 of approved brand and shade over an existing steel primer including cost and
conveyance of all materials to work site, all operational, incidental, labour charges,
etc. complete for finished item of work as per SS 2207 & SS 1212
1.10 LTR Anti Corrosive bitumen paint (Black ) 360.00 1 LTR 396.00
379/24 grade1
0.33 NOS I CLASS PAINTER 206.00 EACH 67.98
0.77 NOS II CLASS PAINTER 188.00 EACH 144.76
TOTAL 608.74
ADD FOR L S FOR BRUSHES 1.26
610.00
ROUNDING OFF RS. 610.00 / 10 SQM
3 Supply and fixing of M.S Plates of 6 mm thick in place of damaged end deck plates over
the bailey bridge including cost and conveyance of all materials to site and all labour
charges for cutting to required sizes, erecting in position, welding charges and all
operational, incidental charges for fixing in position etc., complete as directed by the
engineer-in-charge.
64.50
Executive Engineer
(R&B), Division, Machilipatnam
L.S. FIRST AND FINAL BILL
NAME OF WORK:- Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Naraya
Krishna District.
Sub Estimate 3:- Maintenance of Bailey Bridge including painting, repairs of plates, cost and suply
nuts etc.
QUANTITY
DESCRIPTION OF WORK
Up to Date Since Last
1 2 3
Painting to iron work with 2-coats of Ready
Mixed First Quality Synthetic Enamel Paint of
approved brand and shade approved brand
making 2 coats in all including cost and
conveyance of all materials to work site, all
operational, incidental, labour charges, etc.
complete for finished item of work as per SS
1207 & SS 1212
D.R.Agt.No.
D.H.S.
D.F.C.
AMOUNT
Rate/Per
Up to Date Since Last
4 5 6