Activity to # of Weeks to Total Crash Incremental Path:“1,2,3,5 Path:“1,2,4,5,

Step # Crash Crash Cost ($) Cost ,9,13” 9,13”

51 49
1 1 1 $3,000.00 $3,000.00 50 48
2 11 2 $8,000.00 $11,000.00 50 50
3 2 2 $10,000.00 $21,000.00 48 48
4 12 2 $16,000.00 $37,000.00 48 48
5 7 4 $44,000.00 $81,000.00 48 48
6 6 3 $45,000.00 $126,000.00 48 48
7 10,6 1 $22,000.00 $148,000.00 48 48
8 8,6 2 $58,000.00 $206,000.00 48 48
9 5,6 6 $390,000.00 $596,000.00 42 42
CANNOT CRASH FARTHER- PATH "1,2,4,5,8,10,11,12,13" IS FULLY CRASHED

Shortest Time to Complete 45 Weeks


Total Costs to Fully Crash $596,000.00
Path:“1,2,4,5,
Path:“1,2,3,5,8 Path:“1,2,4,6,7
,10,11,12,13” 8,10,11,12,13 ,11,12,13”

63 61 68
62 60 67
60 58 65
58 56 63
56 54 61
48 54 57
48 54 54
47 53 53
45 51 51
39 45 45
3" IS FULLY CRASHED
Step #1 Step #2 Step #3
Option # Activities Cost ($) Option # Activities Cost ($) Option # Activities
1 1 3,000 1 2 5,000 1 2
2 2 5,000 2 6 15,000 2 6
3 6 15,000 3 7 11,000 3 7
4 7 11,000 4 11 4,000 4 12
5 11 4,000 5 12 8,000 5
6 12 8,000 6 6
7 7 7

Step #5 Step #6 Step #7


Option # Activities Cost ($) Option # Activities Cost ($) Option # Activities
1 6 15,000 1 6 15,000 1 5,6
2 7 11,000 2 2 8,6
3 3 3 10,6
4 4 4
5 5 5
6 6 6
7 7 7

Step #9 Step #8 Step #8


Option # Activities Cost ($) Option # Activities Cost ($) Option # Activities
1 5,6 65,000 1 1
2 2 2
3 3 3
4 4 4
5 5 5
6 6 6
7 7 7
Step #3 Step #4
Cost ($) Option # Activities Cost ($)
5,000 1 6 15,000
15,000 2 7 11,000
11,000 3 12 8,000
8,000 4
5
6
7

Step #7 Step #8
Cost ($) Option # Activities Cost ($)
65,000 1 5,6 65,000
29,000 2 8,6 29,000
22,000 3
4
5
6
7

Step #8 Step #8
Cost ($) Option # Activities Cost ($)
1
2
3
4
5
6
7