Professional Documents
Culture Documents
Operations Primer - 2017: A Brief Introduction To The Basics of Operations Management
Operations Primer - 2017: A Brief Introduction To The Basics of Operations Management
• Introduction
• Important Terminologies
• Theory of Constraints
• Supply Chain Management
• Inventory Management
• Project Management
• Quality Management System
• Service Operations
• Assignments
The objective of the Operations Management is ‘to produce goods and services of Right Quality and Quantity at the Right time and Right
manufacturing cost’:
Right Quality : The quality of product is established based upon the customers need. The right quality is not necessarily being the best
quality. It is determined by the cost of the product and the technical characteristics as suited to the specific requirements.
Right Quantity : The manufacturing organization should produce the products in right number. If they are produced in excess of demand,
the capital will block up in the form of inventory and if the quantity is produced in short of demand, leads to shortage of products.
Right Time : Timeliness of delivery is one of the important parameter to judge the effectiveness of production department. So, the
production department has to make the optimal utilization of input resources to achieve its objective.
Right Cost : Manufacturing costs are established before the product is actually manufactured. Hence, all attempts should be made to
produce the products at pre-established cost, so as to reduce the variation between actual and the standard (pre-established) cost.
Let us consider the following situation to better under the terminologies related to process analysis.
Situation: A hospital with a waiting room for patients, treatment room, and a room for cured patients
Cycle time: The average successive time between completions of successive units. Reciprocal of Cycle Time is Throughput.
In the above example, cycle time is the average time for a patient in treatment room to get treated and join the ‘cured patients' group. In other words, if for every 10
minutes one patient gets treated and joins ‘cured patients’ group then cycle time is said to be 10 minutes. Throughput is 0.1 unit per minute or 6 units per hour.
Utilization: Is the ratio of the time that a resource is actually activated relative to the time that it is available for use
Example – If the doctor works for 8hrs. a day but uses the stethoscope for only 2 hrs. then the stethoscope utilization is = (2/8) = 0.25 = 25
Setup Time: Time required to prepare an instrument/pre-requisites to carry out an operation.
Example: If the doctor takes 5 minutes. to setup the instruments in his room to operate a patient. It is considered as the setup time
Operation Time: Sum of the setup time and run time for a batch of parts
Example: Here, the setup time(5 minutes.)+ time to treat a patient or run time (10 min.) = 15 minutes is the operation time.
Waiting Time: Time spent waiting to be taken up for operation
Example: Time spent by the patients in the waiting room before consulting the doctor.
Throughput Time: It is the average time for a unit to move through the system. Sum of operation time and waiting time. Example: It is the total time a patient
spends in the hospital (waiting time + setup time + operating time), If waiting time is 3 min => Throughput time = 3 min +5 min + 10min = 18min. (>Cycle Time)
Lead time: The total time it takes a customer to receive an order (includes time to process the order, throughput time and delivery time)
Inventory:
• Inventory is an idle stock of physical goods that contain economic value, and are held in various forms by an organization in its custody awaiting
packing, processing, transformation, use or sale in a future point of time.
Examples : Manufactured cars in warehouse waiting to be sold, Software Engineer who is waiting for allocation of work, etc.
Inventory = Cycle Stock + Safety Stock:
Cycle Stock – Average inventory resulting due to production or purchases to satisfy day to day operations. Average demand, Ordering Cost & Holding
Costs of material in context are determinants of Cycle Stock.
Safety Stock – Amount of inventory that has to be kept, to safeguard against uncertainties so as to be able to fulfill the customer demands. Uncertainty
in Lead time and Uncertainty in Demand are determinants of Safety Stock.
Costs Associated with Inventory:
• Ordering Costs – Includes all fixed costs i.e. components that do not vary with the size of the order. For example, admin cost & transportation costs.
• Holding Costs – Costs pertaining to Working Capital held up with inventory, Storage and Handling, Deterioration, Obsolescence, Shrinkage etc.,
• Stock-out Costs – Costs due to running out of stock. Lost sales Cost when company looses potential sales. Backorder Cost additional costs (admin,
transportation, expediting, etc.,) when customer is willing to wait for his/her order to be fulfilled.
Framework for Decision Making:
How Much To Order? Objective is to optimize the ordering quantity, while minimizing the combination of Ordering Cost, Holding Cost & Stock-out
cost. For example, if an item has high holding cost and low ordering/stock out costs, it makes sense to order in less quantity with more no. of orders.
When To Order? Objective is to minimize the total costs, while considering the uncertainty in lead time. For example, if you order too early, holding
costs might increase or if you order too late stock-out (uncertainty in lead time) costs will increase. If stock-out costs are significantly more than holding
costs, it would be wise to order a little earlier and vice versa.
What is a Project? An assignment which is temporary with a defined beginning and end in time, and is unique in nature with a specific set
of activities to accomplish a singular goal.
Examples : Development of software for an improved business process, the construction of a building or bridge, the relief effort after a natural
disaster, the expansion of sales into a new geographic market
What is Project Management? It is the application of knowledge, skills, tools, and techniques to project activities to meet the project
requirements.
Life Cycle of a Project:
Initiating – At this stage, scope of the project is perfectly defined with the help of many discussions and clarifications from the client. For
Planning - With help of Work Breakdown Structure (WBS), Project Schedule Plan for all the activities & sub-activities is prepared which
will be the reference for executing the project. The duration of activities, sub-activities and their interdependence will determine the critical
path for completion of project, which is detrimental for the duration of project.
Executing - All requisite resources (Human Resources, Plant & Machinery etc.) are deployed and the work is carried out w.r.t Project Schedule
Plan.
Monitoring and Controlling – At regular intervals current work is compared with the Project Schedule Plan, and necessary actions are taken
wherever there are backlogs with the formulation and implementation of Catch-Up Plan.
Closing - In this stage, it is necessary to ensure everything has been completed as per scope and all payments are made and also transfer of
ownership has taken place. Meticulous documentation plays a major role for smooth project closure formalities.
Important Terminologies:
• Quality Assurance (QA) – A way of preventing mistakes or defects in manufactured products with necessary measures in the system.
• Quality Control (QC) – A process by which entities review the quality of all factors involved in production.
Lean Six Sigma: (Equivalent to Lean Philosophy & Six Sigma Philosophy)
• Lean is achieved by removing “Waste,” which is an activity not required to complete a process i.e Non-Value Adding Activity.
• Six Sigma is named after a statistical concept where a process produces not more than 3.4 defects per million opportunities (DPMO).
• Six Sigma can therefore be also thought of as a goal, where processes not only encounter less defects, but do so consistently (low variability).
Framework/Sequence of activities to carry out for achieving Lean Six Sigma level of Quality in a process – DMAIC
Define : Define the problem and what is required to satisfy your customer. Measure : Map the current process to collect data.
Analyze : Investigate and identify what causes the problem. Improve : Implement a fix that will solve the problem.
Control : Sustain the improved results.
Simply put, Lean Six Sigma helps you identify the cause of a problem and implement a fix based on facts, rather than assumptions.
Service Operations:
• The objective of Service Operations is to make sure that services are delivered effectively
and efficiently. This includes fulfilling user requests, resolving service failures, fixing
problems, as well as carrying out routine operational tasks.
• With advancements in competitive landscape across industries, as a strategy to retain and
acquire customers through customer satisfaction, service operations is playing a vital role.
• In recent years, this is evident in the improvement of customer care services provided by
firms of ecommerce, telecom operators, banks & financial institutions, etc.
Waiting Line Management:
• Deals with reducing the waiting time for a customer & reducing queue length in a system. Framework for Understanding:
• Important Parameters: (Refer the block diagram ‘Queuing System’) Objective – To optimize the Queue length while
• Arrival Rate of People – Number of people that are entering into the system minimizing the investment in the system.
• Service Rate of Server – Number of people that can be served by each server Constraints:
• Number of Phases – Number of sequential Queuing Systems 1. Increasing the number of servers will increase the
• Number of Servers & Number of Channels service rate of whole system thus reducing the
• The aim of the management is to work on the right combination of above parameters while queue length, but increases the cost of salary that
understanding the tradeoff w.r.t cost i.e Cost Benefit Analysis of all possible combinations. has to be paid to new servers.
Application Areas: 2. Increasing the quality of servers by training, will
• Banks have customers in line to get service of teller, cars queue up for re-filling, aero-planes improve the service rate and reduce the queue, but
waiting in sky for landing, customer waiting to get connected to customer care executive etc. increases training costs.
1. Understand the SIPOC framework from the following link (http://bit.ly/2o7RDXz). And develop the SIPOC
model for the processes at,
• Retail Shop nearby your home.
• Barber Shop nearby your home.
Talk to both Retail Shop owner & Barber Shop owner and understand the processes in the framework of Suppliers,
Inputs, Processes, Outputs & Customers. You need to mention the names & mobile numbers of both the owners’
in your assignment submission. (Mandatory)
2. Read the book ‘The Goal’ by Eliyahu M. Goldratt and send a write-up of maximum 500 words explaining the
crux of the topic discussed in the book. (Optional)
Ø Few Pointers :
• Send your submissions in pdf file to our club ID – clubkaizen@iimidr.ac.in
• Naming Convention of the file should be Assignment_No._Name_Mobile No._CAT ID
• For example, if your name is Abhinay Singh and you’re sending Assignment 1; Naming Convention is
‘Assignment_1_Abhinay_Singh_9898989898_500084’
• Deadline – 25th June 2017, 11:59 PM.
• Winners will be announced in our Facebook Page (Web address is in the next slide)
Prepared by Club Kaizen in association with Placement Preparation Committee
Thank You!
Club Kaizen is Looking Forward to Meet You At IIM, Indore!!