Professional Documents
Culture Documents
FSR 2020-10 CobrePanama SAG2 Elec
FSR 2020-10 CobrePanama SAG2 Elec
REPO RT
FSR_2020-10_CobrePanama_SAG2_Elec N.A.
CUSTOMER DESIGNATION
n.a.
PREPARED
CONFIDENTIAL - We reserve all rights in this document and the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright © 2020 ABB Switzerland Ltd. All rights reserved.
G EAR LE S S M I L L D R I V E
FIELD SERVICE REPORT (ELECTRICAL)
Contents
1. Customer and site information................................................................................................ 4
1.1. Service basic information ......................................................................................................... 4
1.2. List of distribution (ABB & customer) .................................................................................... 4
5. Cycloconverter ......................................................................................................................... 34
5.1. Table of overall activities and tests...................................................................................... 34
5.2. Visual inspection ....................................................................................................................... 35
5.3. Check cycloconverter drive control panel +F02 ................................................................. 38
5.3.1. Check control cables of panel +F02 .................................................................... 38
5.3.2. Check cabinet cooling fans of +F02.................................................................... 38
5.3.3. Check earth fault protection relay (stator) ....................................................... 39
5.3.4. Check Stator Ground Fault Protection Device VME 420 ................................ 40
5.3.5. Check safety relay function ...................................................................................41
5.3.6. Time synchronization............................................................................................. 42
5.4. Cycloconverter power part (+CA, +CB, +CC) ...................................................................... 43
5.4.1. Check power cable connections, tightness & torque ..................................... 43
5.4.2. Check tightness of control cable connections and
measurement circuits ............................................................................................ 44
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
8. Ringmotor..................................................................................................................................57
8.1. Table of overall activities and tests...................................................................................... 57
8.2. Visual inspection ....................................................................................................................... 57
8.3. Ringmotor cooling and overpressure fans ......................................................................... 58
8.4. Rotor brush gear and mill slipring connections ................................................................ 58
9. Off load disconnector switches (OLDS for Stator & Rotor) ................................................ 59
9.1. Table of overall activities and checks for Stator OLDS .................................................... 59
9.2. Table of overall activities and checks for Rotor OLDS ..................................................... 59
9.3. Visual inspections of Stator & Rotor OLDS (during shutdown)..................................... 60
9.4. Check motor start point connection .....................................................................................61
9.5. Check resistance between input - output ............................................................................61
9.6. Check power cable connection ...............................................................................................61
10.E-House..................................................................................................................................... 62
10.1. Table of overall activities and tests...................................................................................... 62
10.2. Visual inspection & general checks ....................................................................................... 64
10.3. Seismic Detection ..................................................................................................................... 65
10.4. MCC (by client) .......................................................................................................................... 65
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
2. Service information
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
2.11. Tools
Item pc. Instrument / type / brand calibrated comment
(yes/no)
1 Multimeter yes
2 Megger MIT525 5kV Insulating Resistance Test- yes
er
3 Low resistance ohmmeter digital Megger - yes
DLRO 10X
4 Set of Hand Tools
5
2.12. Abbreviations
+A1 Left ring motor I/O panel ControlIT PLC programming platform
+A3 Right ring motor I/O panel Cyclo Cycloconverter
+AC01… Air conditioners no. 1 – n DCS Distributed Control System
+CA Cycloconverter power part (U) DM ABB Drive MonitorTM
+CB Cycloconverter power part (V) DRI Drive
+CC Cycloconverter power part (W) DTM Device Type Manager
+CCT Cyclo Control Terminal eth Ethernet (port)
+F01 Excitation control panel FW Firewall
+F02 Cycloconverter control panel FW Firmware
+F03 Auxiliary control panel (Auxiliary PLC) GMD Gearless Mill Drive
+F04 Network panel HMI Human Machine Interface
+F05…nn Motor Control Center panel HVAC Heating, Ventilation, Air Condition-
ing
+F14 Firefighting system panel I/O Input/Output
+F15 Cyclo cooling unit panel LAN Local Area Network
+F16 Stator transformer protection panel MCB Miniature Circuit Breaker
+F17 Lighting panel MCC Motor Control Center
+MLCP Mill Local Control Panel MVB Medium Voltage Breaker
+RIO1 General remote I/O panel no. 1 NLS National Language Support
+RIO2 General remote I/O panel no. 2 OLDS Off Load Disconnect Switch
+UPS Uninterruptible Power Supply OPC Open Platform Communications
IT
800xA ABB's System 800xA Industrial platform PLC Programmable Logic Controller
BMI Refers to as Minerals Solution library Simulink Drive control program. platform
CBM ABB Control Builder M VLAN Virtual LAN
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Service Date
Description by /done Remarks
period dd.mm.yyyy
Event analysis before shutdown (4.3) always ABB ☒ 23-10-2020
Parameter settings -snapshot (4.4) always ABB ☒ 23-10-2020
Air gap supervision (4.5) always ABB ☒ 23-10-2020
Drive control signals, before shutdown (4.6.1) always ABB ☒ 23-10-2020
Cyclo synchronization voltage (4.7) always ABB ☒ 23-10-2020
Comments:
Service Date
Description by /done Remarks
period dd.mm.yyyy
Air gap supervision (4.5) always ABB ☒ 31-10-2020
Normal / Max speed operation (4.6) always ABB ☒ 31-10-2020
Drive control signals, after shutdown (4.6.2) always ABB ☒ 31-10-2020
Cyclo synchronization voltage (4.7) always ABB ☒ 31-10-2020
Mill start behavior (4.8) always ABB ☒ 31-10-2020
Trending of data via HMI (4.9) always ABB ☒ 31-10-2020
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
15
10 8 8 8 8
7
6 6
5
5 4
3
2 2 2 2 2
1 1 1 1 1 1 1 1
0
WaterTempSecOut_FaultH2
ExternalHWFaultLINCA3
StallProtection
CriticalInterlock
LineUnderfrequency
LineOverfrequency
ExternalHWFault_CombiIO
ExcitationOvercurrent
RotorCBIsTripping
MotorOvervoltArrester_PhaseW
OvercurrentLINCC1
EmergencyStopPressed
DCFTripped
Motor_DifferentialFaultV
LineUndervoltage
DoorsAreOpen
LineOvervoltage
ExcitationEarthFault
ThyristorFault
EmergencyStopPendant
ExcitationLineUndervoltage
MotorUnbalancedCurrent
OvercurrentLINCA1
EarthFault_Stator
OvercurrentLINCA3
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
800
600
400 332
267
165
200
78
34 26 14 13 11 8 4 3 3 3 3 1 1
0
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Date: 07.07.2019.
Service Date
Description by /done Remarks
period dd.mm.yyyy
Check air gap supervision and record trends 6/12/36m ABB ☒ 31-10-2020
Compare electrical measurements of the air 36 month ABB ☐ Not applicable for 12
gap signals with mech. measurements with months service
feeler gauge (4.5.1)
(Mechanical measurement performed by MSV)
Check conditioner box: note type & serial num- on request ABB ☐ Not applicable for 12
ber installed in ringmotor terminal box. months service
(if ringmotor terminal boxes are accessible)
Check condition of the extension cables, con- on request ABB ☐ Not applicable for 12
nector & connector cable between sensor and months service
extension cable inside the ringmotor.
Type of extension cables installed inside the on request ABB ☐ Not applicable for 12
ringmotor. months service
Check proper shielding of the extension cables on request ABB ☐ Not applicable for 12
inside terminal box months service
It is recommended that the airgap measuring system gets upgraded in order to improve the
Comments:
quality of the measured signal.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Check air gap supervision and record trends with transient recorder of all signals, before the shut-
down.
Result: No offset problem was detected between sensors in same position.
Air gap 1, 2 and 3 located at 6 o’clock (bottom, view from feed side)
Air gap 4, 5 and 6 located at 9 o’clock (left, view from feed side)
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Air gap 7, 8 and 9 located at 12 o’clock (top, view from feed side)
Airgap 10, 11 and 12 located at 3 o’clock (right, view from feed side) :
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Check air gap supervision and record trends with transient recorder of all signals after the shutdown.
Result: No offset problem was detected between sensors in same position.
Air gap 1, 2 and 3 located at 6 o’clock (bottom, view from feed side)
Air gap 4, 5 and 6 located at 9 o’clock (left, view from feed side)
Air gap 7, 8 and 9 located at 12 o’clock (top, view from feed side)
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Airgap 10, 11 and 12 located at 3 o’clock (right, view from feed side)
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Airgap 4 alarm: During start of the mill Airgap 4 alarm appeared. It was online checked. All the 3 air-
gap sensor in the same position (No 4, 5, 6) measurement permanent low airgap close to the alarm
limit for 20 seconds long. The measurement was real, not electrical failure.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Service Date
Description by /done Remarks
period dd.mm.yyyy
Ringmotor winding temperatures always ABB ☒ 31-10-2020
Ringmotor Cooling system always ABB ☒ 31-10-2020
Cyclo cooling system always ABB ☒ 31-10-2020
Air gap supervision always ABB ☒ 31-10-2020
Motor power always ABB ☒ 31-10-2020
Motor speed always ABB ☒ 31-10-2020
Motor voltage always ABB ☒ 31-10-2020
Motor current always ABB ☒ 31-10-2020
The cycloconverter cooling system slightly release the pressure. It can be maintained by
Comments: pumping regularly to keep pressure value within the tolerance. In long term recommended
to improve cooling unit to keep pressure.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result: Cycloconverter cooling unit air pressure slightly decreasing, pressure is maintained 2 times
per month
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
5. Cycloconverter
5.1. Table of overall activities and tests
Service Date
Description by /done Remarks
period dd.mm.yyyy
Preparation and LOTO always ABB ☒ 24-10-2020
Harddrive cleanup (CCT panel), make back-ups always ABB ☒ 31-10-2020
Visual inspection cabinets +CA, CB, CC, +F02 (5.2) always ABB ☒ 24-10-2020
Check cooling water hoses power part (check always ABB ☒
24-10-2020
connections & leakage)
Door switches (function test) (5.2) always ABB ☒ 24-10-2020
Control cables in +F02 (check tightening) (5.3.1) always ABB ☒ 24-10-2020
Cabinet cooling fans in +F02 (5.3.2) always ABB ☒ 24-10-2020
Earth fault protection relay (stator) +F02 (5.3.3) always ABB ☒ 24-10-2020
E-Stop loop & safety relays +F02 (funct.test) always ABB ☒
24-10-2020 Field E-stop 3 is dirty
(5.3.5)
Time synchronization (CCT, PEC, 800xA) (5.3.6) always ABB ☒ 24-10-2020
Check Power Part resistance at input-output (u- always ABB ☒
24-10-2020
ohm meter) (5.4.6)
Comments:
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Check the condition of the equipment and note down the results below (dust, water leakage,
damage, signs of overheating, cooling tubes, capacitor leakage, cable trays, cabling, doors,
etc.)
a) Visual checks of power part bus bar isolators, dust, water leakage, cooling water circuit,
capacitor leakage (snubber circuit, base load capacitor, etc.
c) Check cooling water hoses power part (check connections & leakage)
Result / comments:
a) Visual checks: No visual damage noticed neither in the control panels nor in
the power part main components. Dust was very moderate, it
was cleaned.
b) Signs of over- No sigh for overheating
heating:
c) Cooling water The cooling water hoses were all found in good condition.
hoses:
d) Door switches: At the Back doors some of the Door switches are bypassed, it is
a safety issue. New “long arm” door switches were installed for
the front door, they are functioning properly.
e) other
Result: No visual damage noticed in the control panels neither in the power part main
components.
Some of the Back door’s door switch supervisions are bypassed.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result: No visual damage noticed in the control panels neither in the power part main
components.
Some of the Back door’s door switch supervisions are bypassed.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result / comments:
Very few dust, cleanness is well maintained.
Check fan and filter condition of cabinet or rack cooling fans in +F02
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Check function of the protection relay, and the correct alarm & trip information on the HMI
and CCT.
Check and note the actual settings of the protection relay in the table below (e.g. Bender
relay):
Result / comments:
The trip function from the stator insulation protection relay is temporary disabled in the
PEC software via parameter setting. The analog output is recorded by the PEC controller
and it is available in HMI.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Check function of the protection relay, and the correct alarm & trip information on the HMI
and CCT.
Result / comments:
This function is not tested in a 12 month service, but the settings are recorded in the table
below, they are correct and according the standard.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result / comments
The E-stop buttons from the different panels and locations were tested. The relevant mes-
sage and E-stop relay reacted as expected. Field E-stop no. 3 is very dirty, the first time
that was tested the contact did not acted after pushing as they are very dirty.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Check the time synchronization between the AC800PEC Controller, MLCP/CCT panels and
the system 800xA.
Result / comments
The AC800 PEC controller is synchronized to 10.42.104.21 IP address. The MLCP/CCT panel
are synchronised to 10.42.100.21.
Panel times, and message event times are matching with the actual time.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Apply the different torques for power cable connections according below table (specification
of screws: ST-NR A2-70)
Result / comments:
The torque was checked with torque wrench on all power cables in
the Cycloconverter power part, excitation converter panel, and Off load disconnect-
or switches input side. Some cables were needed to re-apply torque to reach the 40 Nm.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result / comments:
2 loose connection was found, the wire-end-sleeve needed to be replaced to improve con-
nection.
Check proper and tight cable/wire connections of the CTs secondary side and its earthing.
Result / comments:
No loose connection was found.
Result / comments:
No loose connection was found. Voltage signals were found in good
shape therefore no need to perform the low voltage test
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
5.4.5. Check Power Part resistance on input and output of cyclo (µ-ohm meter)
(required for 6/12 & 36month service)
For the Resistance measurement you should use µ-ohm meter, with minimum 1-10A current
injection.
Result / comments:
The measured values were found within the limit.
Cyclo Resistance:
input
Busbars R1-S1 S1-T1 T1-R1 R2-S2 S2-T2 T2-R2 R3-S3 S3-T3 T3-R3
Panel 3.7 mΩ 3.9mΩ 3.8mΩ 3.4mΩ 3.5mΩ 3.5mΩ 3.7mΩ 3.6mΩ 3.7mΩ
+CA
Panel 4.0mΩ 4.0mΩ 3.9mΩ 3.9mΩ 3.9mΩ 3.9mΩ 3.7mΩ 3.6mΩ 3.6mΩ
+CB
Panel 3.7mΩ 3.7mΩ 3.7mΩ 3.7mΩ 3.8mΩ 3.7mΩ 3.5mΩ 3.5mΩ 3.5mΩ
+CC
Check correct pressure (acc. OMM) with the feeler gauge of cyclo tool set.
Result / comments:
The thyristor stack pressure was found lower than usual, it was re-tightened.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result / comments:
Visual inspection:
Cooling signal monitoring: Performed via HMI, see chapter 4.9 above. All the
instrumentation inside the cooling unit give coher-
ent information.
Check conductivity trend: The conductivity is stable and oscillate according to
the water temperature. Deionizer bottle was not
require to be replaced.
Check function of leakage sensors: It was tested, the error message came up as ex-
pected.
Check and adjust water level, flow, air pres- Water needed to be refilled, air pressure was
sure: pumped. Pressure needs to be pumped 2 times per
month. No visible sign for leakage. Flows are cor-
rect.
Clean mechanical filters: Was cleaned.
Check cooling pump LCS & E-stop function: Was tested, and working properly
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Water level:
Heat exchanger:
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Comments:
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result / comments
No abnormal finding took place in the +F01 panel.
5.6.4. Check fuses, door switch and cooling fans, power cables
(required for 6/12 & 36month service)
Result / comments:
Fuses: The input fuses and converter fuses were
checked and measured.
Door switch: The panel door switches were functioning
properly.
Cooling fans: The panel and converter fans were tested
and worked as expected.
Power cable connections, tightness & re- The torque level was adjusted on the power
torque (only for 12/36m): cables.The torque value was 40Nm.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
DCS800 Resistance:
AC busbars U1-V1 V1-W1 W1-U1
Resistance: 28.4 mΩ 28.3 mΩ 28.4 mΩ
DC busbars plus - mi-
nus
Resistance 320 mΩ
Result / comments:
No unbalance in resistance value was found the AC side. 1A was injected.
Check and note the actual settings of the protection relay (Bender relay):
Result / comments
It is recommended to adjust the value of the leakage capacitance to 10µF and check
whether the resistance calculation gets even more stable and reliable.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result / comments:
Setting: 0.52A, as per circuit diagram. The test has been performed and the trip message
came as expected.
5.6.9. Check Rotor over voltage arrester by forcing high voltage from Megger
Disconnect one side of the Rotor over voltage arrester (crow bar) from DC circuit and inject
“high voltage” from megger till the BOD will trigger and activate the arrester. Test arrester in
both directions.
Result / comments:
The overvoltage arrester modules were tested by injecting voltage using the insulation
Resistance tester (Megger). The voltage injected was 1600V. Both rotor overvoltage pro-
tection thyristors were triggered.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
6. Cycloconverter Transformers
Result / comments:
Not performed due to the reduced manpower availability and time constraint for the ser-
vice execution.
Result / comments: Not performed due to the reduced manpower availability and time
constraint for the service execution.
Winding temperature:
Buchholz relay:
Overpressure relief valve:
Oil level supervision:
Etc.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result / comments:
Not applicable for 12 months service
Test transformer protection relay function (every 36month):
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
7. Excitation Transformer
Result / comments:
Not performed due to the reduced manpower availability and time constraint for the ser-
vice execution.
Result / comments: Not performed due to the reduced manpower availability and time
constraint for the service execution.
Winding temperature:
Buchholz relay:
Overpressure relief valve:
Oil level supervision:
Etc.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
8. Ringmotor
Result / comments:
A1-A6 junction boxes were visually checked. A2 and A4 electrical connection was checked
as well.
Ringmotor cooling system water and air temperature values were around the alarm lev-
els while the mill was running.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result / comments:
Not performed due to the reduced manpower availability and time constraint for the ser-
vice execution.
This service task should be performed by the MSV (mechanical supervisor) if available.
Result / comments: Not performed due to the reduced manpower availability and time
constraint for the service execution.
Brush gear cables connection:
Rotor grounding cable connection:
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
Result / comments: Not performed due to the reduced manpower availability and time
constraint for the service execution.
Stator OLDS: xxx
Stator OLDS:
Rotor OLDS:
Result / comments:
Stator OLDS: Contact resistance values are optimal.
Rotor OLDS: Contact resistance values are optimal.
Measured with 1A.
Result / comments:
Stator OLDS: Only front (input) side were checked, 40Nm was verified with torque wrench.
Rotor OLDS: 40Nm was verified with torque wrench.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
10. E-House
10.1. Table of overall activities and tests
Service Date
Description by /done Remarks
period dd.mm.yyyy
Preparation and LOTO always ABB ☒ 24-10-2020
Visual check (grounding, dust, always ABB ☒
damage, floor entries sealed,
24-10-2020
cable Isolation covers still in
place) (10.2)
Check emergency exit of E- always ABB ☒
24-10-2020
House (10.2)
Seismic sensor:
Check functionality and set- 36m ABB ☐
Not applicable for 12 months
tings of seismic protection
service
(10.3)
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
If the plant is equipped with a seismic detection system delivered by ABB, it needs to be
checked and verified.
Result / comments:
Not scope of 12 month service
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE
11. Appendix
No. Description Reference Pages Remarks
Number
12. Revisions
Rev. Page (P) Description Date Dept./Init.
Chapt. (C)
- All pages First issue 28.11.2020 GM/ PI-OE4
13. Disclaimer
The contents of this document should in no event be considered as any acknowledgement of
any liability or obligation (without prejudice). ABB reserves all rights and remedies. This doc-
ument and associated information are privileged and confidential and may not be used or
referred to in any legal or arbitration proceedings. The contents of this document should not
be considered as exclusive or comprehensive. This document contains the opinion of the
author, based on the information currently available to him. It does not represent the opinion
of the company nor necessarily the final opinion of the author.
This work, including all parts thereof, is protected by copyright. Any use of it beyond the nar-
row restrictions of the copyright law without prior approval of ABB Switzerland Ltd. is pro-
hibited and subject to punishment under the applicable law. The above pertains to (in partic-
ular) reproduction, translation, microfilming, and electronic data processing.
PROJECT NAME PROJECT ID / REPORT NO: DOCUMENT ID. REV. LANG. PAGE