Observations & Comments Sheet (OCS) : Qatar Olympic Committee
Observations & Comments Sheet (OCS) : Qatar Olympic Committee
Observations & Comments Sheet (OCS) : Qatar Olympic Committee
Super-Structure & Facade Works for Multipurpose Hall at Al Lusail Sports Club - Package 2
Contract No.: EPD/C/154/2012 - Project Number: 2782B
ASTAD / KEO Review Comments
Observations & Comments Sheet (OCS)
OCS Ref. No.: 2782B-CCC-PR-05AC-0019-OCS OCS Rev. : A Project Stage: Construction
Engineer in Charge: Samer Daqaq - ADE/C54 OCS Date: Wednesday, May 14, 2014 Discipline: Mechanical
Doc or Dwg Title, Ref.No and Rev.: 2782B-CCC-PR-05AC-0019-001 Rev. A_ testing & Commissioning Procedure for CO Monitoring and Alarm System
The document(s) reviewed under this OCS, were issued "For Review and Approval" under the Contractor's Transmittal Ref.: 2782B-TS-CCC-KEO-13152 dated 04/05/2014 and are hereby returned to the issuer with the following return code
and actions request:
A = No comments & proceed B=Reviewed with Minor comments / Resubmit for Final Approval
Assessment Code: B C= Reviewed with Major Comments / Resubmit for Review D= Not Approved / Rejected
Identification of
Reviewer Ref. Reference Number Returned Sign-Off
S/N Indicator comment's source: Observations / Comments of Doc. or Dwg. Code Comments (if any) (Open/Closed) (Open/Closed)
(title /page /clause)
Clause 4.2: Personnel Title to be changed to Personnel involved and responsibilities. 2782B-CCC-PR-05AC-
2 KEO-EL-HW
involved Responsibilities shall be furnished for all personnel’s involved. 0019 Rev. A B Open
Testing shall include continuity and insulation resistance tests for all
Clause 5.2: Pre cables prior to installation of system devices, results shall be
2782B-CCC-PR-05AC-
5 KEO-EL-HW commissioning
Procedures
recorded in pre commissioning check list. The pre commissioning
check list shall be revised to include continuity and insulation 0019 Rev. A B Open
Identification of
Reviewer Ref. Reference Number Returned Sign-Off
S/N Indicator comment's source: Observations / Comments of Doc. or Dwg. Code Comments (if any) (Open/Closed) (Open/Closed)
(title /page /clause)
Safety:
Proposed procedure is lacking safety rules/precautions required to 2782B-CCC-PR-05AC-
6 KEO-EL-HW General
be implemented thru T&C of subject system. Contractor to furnish 0019 Rev. A B Open
safety precautions required to be considered during testing.
KEO-Mech/ Submit ITP plans and flow chart to simulate the task of work/testing 2782B-CCC-PR-05AC-
8
SE/Kaj
Method of statements
for each agent as showing per referenced names in item 4.3. 0019 Rev. A B Open
item 5.4 shall be modified to read " the CO level inside the car parks
KEO-Mech/ 2782B-CCC-PR-05AC-
9 SE/Kaj Clause 5.4 will be programmed as per local authority regulations such as QCDA
and as Specified standards"and not as consultant requirments.
0019 Rev. A B Open
KEO-Mech/ item 5.4 &5.5 shall be reviewed against the approved Cause and 2782B-CCC-PR-05AC-
10 SE/Kaj Clause 5.4&5.5 Effect Matrix. 0019 Rev. A B Open