Professional Documents
Culture Documents
Lifting Plan Agc
Lifting Plan Agc
Lifting Plan Agc
TABLE OF CONTENTS
1. PURPOSE
2. SCOPE
3. DEFENATIONS
4. RESPONSIBILITIES
6. PROCEDURE
7. WEATHER CONDITION
No Yes
Lifting More Than 75 Ton
No
No
Operating overY or near other Yes
building, sensitive,No difficult or
restricted areas
No
Yes
Lifting of Machinery without
known lifting points
No
Yes
Lifting more than 75% of rated
load chart
No
Yes
Irregular Shape/difficult to
estimate weight and centre of
gravity
No
Yes
Routine Lift
Crane TC 750
Capacity 75 Ton
Jib Length 45m + 16m
Working Radius 360 degree
Safe working Load < 75 Ton
Weight of The Crane 46 Ton
To ensure that lifting operations are managed to a suitable standard and are safe and appropriate for the
task being undertaken the load must not be more than 75% of the rated lifting capacity.
Only an approved crane operator and rigger shall be employed to doing lifting operations.
6.3. Preparation of Lifting Operation
Below are listed some items which have to be checked and considered before starting a lifting
operation using a mobile crane (all-terrain/crawler):
Ground condition (levelling, soil compaction, need for steel plates under outriggers, etc.) (stability
of the crane if mobile crane is used)
Presence of proximity hazards (Overhead obstacles/power lines, underground services, excavations,
recently excavated ground, adjacent lifting operations, site facilities & obstructions.
Size and weight of the load
Availability of access means (Ladders, Mobile Elevated Work Platform, etc.)
Communication means
Weather conditions
Availability of suitable lifting gears (capacity, length, type…) and cranes (capacity…)
Availability of personnel (crane operator, site supervisor, rigger, banksman…)
Access to and egress from the work area.
Area available for siting the equipment.
Environmental conditions including weather and permissible limits, wind/gust speed
Working under suspended loads must not be allowed
Access and emergency escape routes for the Operator and load handlers
Number of personnel required for task
Visibility of the load at all times by the Lifting Operator or by signaler
Toolbox Talk must be conducted before lifting activity and Lifting Supervisor should inform everyone
involving to the lifting activity about how the operation will be done, which precautions will be
taken and the risks of the activity
Exclusion zone must be set up depending on the lifting study and the warning signs must be placed
Crane should set up on the location with the configuration as defined in the lifting study
Third-party certified riggers can do the rigging
All lifting accessories must be third party certified
Only designated rigger can give signal to the crane operator
After rigging of the test weight beam designated rigger control the exclusion zone that no one in
the exclusion who will not involve in lifting activity (like trailer driver), rigging of the lifting
accessories are proper
Designated rigger will give signal to the crane operator to start lifting
The load shall be lifted above from the ground level under control of the rigger
When the structure reaches to the desired height crane will swing and boom down/up to the
installation location as mentioned in the lifting study
When the load is stabilised by the tag lines
Then the load will be placed on the ground.
After placing the structure, crane will release the load and structure will be designed
7. Weather Condition
Wind speed and climatic conditions (cranes are provided with anemometer);
Visibility must be such that all persons involved in the lifting operations can see each other.
Loads with surface exceeding 6m2 must not be lifted if wind speed is above 13.6 knots – 25 km/h - 7m/s –
15.6 mph and must stop if the wind force exceeds 19.4 knots – 36km/h – 22 mph.