I. SUPPLY OF
9 pc/s " TOYO/LEC" Butt hinge 4.5" x 4" x 3.4mm @ 180.00 = 1,620.00
with 2 Ball Bearing (2BB ) Painted
3 set/s "THASE " #5510 F-36-ND-689 Fire Exit Device @ 5,200.00 = 15,600.00
Horizontal Rim Without Cylinder Key, UL Listed Aluminum Color Finish
3 set/s "TOYO/POSSE" A073 Door Closer Surface Mounted @ 2,200.00 = 6,600.00
UL Listed Silver Color 23,820.00
************ = 81,575.00
*Additional preliminaries or requirements under the "New Normal" plus 12% VAT….. 9,789.00
Safety Protocol are NOT INCLUDED IN THIS OFFER. TOTAL…………..P 91,364.00
*Should this be required ( Rapid Test, SwabTest/RT-PCR vvvvvvvvvvvvvv
full health certificate,and all other medical certificates, quarantine)
a separate cost shall be charged accordingly.
NOTES:
- Supply only.
- Above price subject to change anytime without prior notice.
- All steel parts are epoxy prime painted. Paint finish by others.
- All hardware samples and door accessories samples and all required hinges for the steel doors shall be issued
by the client/buyer prior to door fabrication.
- Unloading of items shall be on street level only; vertical haulage shall be for the account of the client/buyer.
- PLEASE REFER TO OTHER TERMS WRITTEN AND CONTAINED AT THE REVERSE SIDE OF THIS PAGE.
Terms of Payment
- Door/s : 50% upon signing of this contract, 50% before delivery.
- Hardware : 50% upon signing of this contract, Full payment before delivery.
Place of Delivery : Jobsite.
Date of Delivery : To be confirmed.
Name:_____________________ By:_________________
Designation:________________ Ms. Jully Lim .