Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/264942493

D&B versus TBM: Review of the parameters for a right choice of


the excavation method

Conference Paper · May 2014

CITATIONS READS

6 4,989

2 authors:

Javier Macias Amund Bruland


JMConsulting-Rock Engineering AS Norwegian University of Science and Technology
39 PUBLICATIONS   187 CITATIONS    72 PUBLICATIONS   1,234 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Prediction model for drill and blast tunnelling View project

Hard Rock Tunnel Boring: Performance Predictions and Cutter Life Assessments View project

All content following this page was uploaded by Javier Macias on 26 April 2017.

The user has requested enhancement of the downloaded file.


Rock Engineering and Rock Mechanics: Structures in and on
Rock Masses – Alejano, Perucho, Olalla & Jiménez (Eds)
© 2014 Taylor & Francis Group, London, 978-1-138-00149-7

D&B versus TBM: Review of the parameters for a right choice


of the excavation method

F.J. Macias & A. Bruland


Department of Civil and Transport Engineering, Norwegian University
of Science and Technology (NTNU), Trondheim, Norway

ABSTRACT: The right choice of the excavation method is essential in hard rock underground projects. The
Drill and Blast (D&B) and Hard Rock Tunnel Boring Method (TBM) are widely and successfully used. Selecting
the most appropriate excavation method is not simple as it is depending of several parameters and particular
conditions. The purpose of this paper is to make a review of the parameters involved in the selection of proper
excavation method. The applicability and level of convenience of each excavation method in function of every
parameter defined will be briefly discussed. A final resume of the excavation method comparison is presented
and proposed to be general guidelines at the early stages in hard rock tunnelling.

1 INTRODUCTION been divided into groups according to the parameters


involved in the excavation method choice.
Underground construction industry has been experi- A final summary in table forms is achieved. It has
encing a strong development with enormous techno- been attempted to quantify the parameters based on
logical improvement. In hard rock projects, drill and literature when possible.
blast excavation method (D&B) and tunnel boring The summary of the comparison is proposed to be
machine method (TBM) are widely used with success. general guidelines in the selection of the excavation
In hard rock tunnelling the selection of the exca- method for tunnels in rock at the early stages.
vation method is not a simple issue. It may result in
catastrophic situations as experience has shown.
The choice is more complex than a simple eco-
nomic issue and rarely clear from the early stages of 2 PARAMETERS FOR THE EXCAVATION
the projects. It is necessary to have an entire overview METHOD CHOICE
of the parameters involved in the excavation method
choice. 2.1 Introduction
Many parameters are involved with different role The parameters involved on the excavation method
in every project case; project characteristics and pur- choice are grouped according to the main topics. A
pose, environmental aspects or even social issues are briefly discussion is carried out following.
involved. Every project is unique and a comprehensive
and detailed study should be carried out.
The excavation methods are not mutually exclusive.
2.2 Project design considerations
Hybrid solutions should be considered taking advan-
tage of them whenever circumstances allow (Barton, The geometry of the excavation in the TBM method
2013). is limited to a circular shape while the drill and
In the present paper, through a wide literature blast method allows almost “any” excavation geome-
review, the main parameters involved in the selec- try. With “any” excavation is meant within reasonable
tion of the excavation method are briefly discussed. contour tunnel.
The extension of the discussion is limited due to the The cross section area is defined from the early
space available on the paper. A further research is stages of design and it can hardly be changed.
considered. This great versatility of the shapes suppose an
The existing literature related to the excavation advantage of the drill and blast method in projects with
method choice in hard rock tunnelling is normally a variety in the cross section shapes whileTBM method
based on particular cases studied and many “sub- is more appropriate for projects with constant shapes
jective” statements are done. The discussion has (Ehrbar, 2008).

823
With both methods the cross section area available time equipment, time consumption in assembling and
to excavate are similar, e.g. TBM method can be used start-up (Lislerud, 1988).
from 2–3 meters diameter and up to approx. 15 m For a new TBM, the delivery time is 6–12 months
according to Hansen (2008). Nowadays, tunnel boring (Holen, 1998) or 10–12 months (Stewart et al., 2006;
method can even be used in smaller excavation areas Hansen, 2008). For a new drill-jumbo 5–6 months
using micro tunnelling. In hard rock conditions it may (Stewart et al., 2006).
be successful from 900 mm. (Nicholas, 2006). The erection time of a TBM and backup, small and
TBMs are more competitive for tunnels with small medium hard rock TBMs, takes usually 3–6 weeks
cross sections (Nord et al., 1988, 2006; Gütter et al., depending local conditions and machinery available
2011). There are limitations in the both methods for (Holen, 1998). Erection times are highly variable
very small diameters (Nord. et al., 1988). worldwide and should be considered with caution.
Regarding to the general layout, e.g. curve radius, It is also important to consider that TBM method
slope…, the TBM method has more limitations needs a more comprehensive study in the design phase
(Holen, 1998; Stewart et al., 2006). However, the D&B with widely geological pre-investigation.
method has almost no limitations (Holen, 1998; Jodl,
2011; Stewart et al., 2006).
The length of the tunnel is a key parameter from 2.5 Health, safety and working
the technical and economical point of view. The TBM environment
method is more competitive for long tunnels while
D&B method is for short tunnels (Nord, 1988; Holen, There are almost no worldwide historical data supports
1998; Ehrbar, 2008; Jodl, 2011). in the literature to say that one method is safer than
It would be risky to define lengths since every the other (Holen, 1998, Tarkoy, 1995), but it is widely
project has its particular characteristics. It is largely accepted that less numbers of accidents occur with the
accepted in the literature that in 3 km length there is a TBM method.
tipping point. By used of the tunnel boring excavation method
In a large number of projects the excavation of serious accident risk from storing or handling explo-
niches, branch tunnels, cavern and/or extended cross sives are avoided (Hansen, 2008, Holen, 1998) and
sections excavation are required. Since normally drill the safety is higher in the face and work area (Tarkoy,
and blast is the technique applied, it creates interfer- 1991). In practically all types of TBM the rock support
ences in the boring operation resulting in machine is installed from protected areas.
downtimes (Holen, 1998). Extra cost in drilling equip-
ment and workers with special drill and blast skills has
to be considered. 2.6 Advance rate
From the authors opinion it should be considered
that in the TBM method, the initial part of the tunnel The advance rate has a high impact in the total
is normally performed by D&B technique. construction time and excavation cost.
In normal conditions, it is accepted for many
researchers that the advance rate in the TBM method is
much higher than with drill and Blast method (Kaiser,
2.3 Final purpose considerations 1994, Tarkoy, 1995, Holen, 1998, Stewart et al., 2006,
The excavation geometry and the final quality required Nord, 2006, Hansen, 2008, Ehrbar, 2008).
are considerations to consider for the final use of the The excavation rate, in normal conditions, with
underground project. TBM method is estimated 4–6 times faster than with
In water tunnels, the head loss due to wall fric- D&B method (Tarkoy, 1995), 1.5–5 (Holen, 1998) or
tion between unlined TBM tunnels and drill and nearly to 1–3 times according to Stewart et al. (2006).
blast is substantial. Cross section reductions between The author’s opinion is that would be risky to define a
33% (Hansen, 2008) and 40% (Holen, 1998) can ratio due to conditions variability worldwide.
be achieved. In road tunnels, the circular excavation However with the D&B method it is easier to
profile is not optimal. advance in crushed zones due to the high versatility
Since in the D&B method “any” shape is possible, of the method (Lislerud, 1988).
it is more adapted to any final purpose of the project The influence of rock in TBM excavation makes
(Ehrbar, 2008). the advance rate estimation much more difficult and
The final operation facilities of the tunnels, as water uncertain (Nord et al., 2006).
and frost protection, can be simplified and optimized,
since systems can be mounted on an even and exact
profile using the TBM method (Hansen, 2008). 2.7 Flexibility
Flexibility in an excavation method is related to the
ability of adapting it to changes in the layout profile
2.4 Start-up time
and in the rock mass conditions.
The start-up time in the TBM project is much longer The TBM method is less or even not flexible than the
than in the D&B method. This is due to longer delivery D&B method. Changes of the TBM diameter is almost

824
limited depending on the machine design, and align- 2.11 Costs
ment during the construction stage (Hansen, 2008;
Construction time and cost detailed studies must be
Stewart et al., 2006).
made at the earliest project stages and have to be
The Drill and Blast method advance easier in
updated periodically Ehrbar (2008).
crushed zones (Lislerud, 1988). This easier advance
In TBM method, capital cost or initial investment
involves a low safety and ground stability risk.
are higher while marginal cost for the excavation
D&B method is the best excavation method for
phase are less (Holen H., 1998).This means important
underground projects with highly variable rock con-
finance and negative cash flows at the beginning of the
ditions or variable shapes (Ehrbar, 2008).
project which is a disadvantage for the TBM method.
In addition, the excavation cost for TBM method has
large variability (Holen, 1998),
2.8 Risk However, life time costs, operation and mainte-
Tunnelling, included D&B and TBM method, is nance, for TBM excavation may be significantly less
exposed to greater risks especially because the ground than for a D&B tunnels (Hansen A.M., 2008).
to excavate and its behavior knowledge is limited The most extraordinary cost saving that can be done
(Thomas et al., 2007). with TBM excavation is the possibility of eliminating
TBM method has higher advance risk (Stewart et al., temporary excavation structures such as access adits
2006). The TBM risk takes particular significance in according Tarkoy (1995).
the case of long and deep hard rock tunnels (Barton, As already mentioned, TBM method reduces the
2000). rock support. The amount of rock support and concrete
TBM method requires a more complete and detailed lining are more predictable in the TBM method for
geological investigation, mapping and testing during normal conditions (Hansen, 2008). This means lower
the planning stage. More time and cost in the design rock support costs and more predictable rock support
phase is necessary to evaluate the project viability and lining costs.
(Hansen, 2008; Bruland, 2010). Anyway, tunnel cost estimation in the TBM method
Highly variable rock conditions favor the choice of is much more difficult and uncertain (Nord et al.,
the blasting method (Ehrbar, 2008). 2006).

2.12 Overbreak and tunnel profile quality


2.9 Ground stability
Most of the authors agree that tunnel boring exca-
Circular excavation is the most favorable shape from vation produces less geological overbreak compared
the point of view of ground stability; therefore the to drill and blast (Nord G., 2006; Stewart P. et al.,
TBM method has more rock stability under normal 2006). The overbreak with TBM method is near elim-
conditions (Hansen, 2008). ination (Tarkoy P.J., 1995). With D&B method should
In case of water inflow under high pressure, D&B be predicted not less than 10% overbreak.
method is more suitable (Ehrbar, 2008), due to the high When the geology is not favorable, the overbreak
flexibility in the application of auxiliary constructions is very difficult to control, but always is much lower
methods and rock support applications. with TBM.
In case of high rock stress conditions the TBM
method may result in important delays.
However, the excavation with TBM method causes 2.13 Environmental disturbance
less damage in the rock mass around the excava- Using the TBM method, less environmental distur-
tion. The rock support required, compared with D&B bances, noisy and vibrations, are caused in the sur-
method, is significantly reduced in the same geologi- rounding areas (Holen H., 1998; Hansen A.M., 2008).
cal conditions (Tarkoy, 1991, Holen, 1998, Nord, 2006, TBM method will be easier acceptable from an envi-
Hansen, 2008). ronmental point of view due a lower construction time
D&B method alloy a great variability and excava- and adits with roads and porwerlines may be omitted
tion sequences depending the rock conditions (Ehrbar, (Holen H., 1998).
2008) while in the TBM method is fixed.

2.14 Temporally access and implantation layout


2.10 Operation and construction crew TBM method has a higher potential when it is neces-
For operation and crew, the TBM method is more sary to avoid or have no possibilities to make additional
advantageous than D&B method. adits or being able to start a heading from the opposite
The tunnel boring operation is a continuous (non- end of the tunnel (Hansen, 2008). One example of this
cyclical) operation, so is a repetitive process; crew is the AMR project (India) where with only two adits
perform repetitive activities with limited competences it will perform more than 40 km of tunnel by TBM
and skills which facilities training and learning is con- method.
tinually reinforced (Tarkoy P.J., 1995), which means However, TBM method has increased requirements
less human factor. for mobilization and demanding infrastructure as well

825
as TBM requires more electric power than drill and 3 CONCLUSIVE REMARKS
blast (Hansen, 2008).
In projects with difficult access, complicated orog- A summary in table form of the parameters involved
raphy or urban areas, D&B method is especially in the excavation method choice discussed earlier are
appropriated (Ehrbar, 2008). TBM method is more shown in the following.
suitable for projects with a good accessibility.
Table 3. Comparison between D&B and TBM method
2.15 Contractual considerations in the choice of related to health, safety and working environment.
the excavation method
D&B Method TBM Method
High risks are involved in underground construction.
Uncertainties in the rock conditions and behavior, Safety Lower Higher
unforeseen conditions, dependency of the excavation Storage Terrorism and Avoided
method and the high construction risk are associated explosives accident risk
Handling Serious accident Avoided
with this type of construction. Therefore is very impor-
explosives rick
tant a specific and differently contracting practices Rock support No protected area Protected area
(Ehrbar H., 2008). installation
The choice of the excavation method should be Working Temporary worse Improved
responsibility of the contractor, always based on the environment Toxic gases Dust
owner’s comprehensive design, except in special cases Principal safety Handling and Cutter changes
with project restrictions (Ehrbar H., 2008). risk storage explosives
The level of initial investigation should be adapted Loading and
to the excavation method requirements. hauling
The total investment and delivery time for new
machines emphasizes the need for reliable prognoses
of rock conditions (Barton, 2000). Table 4. Comparison between D&B and TBM method
related to advance rates.

Table 1. Comparison between D&B and TBM method D&B Method TBM Method
related to the project design considerations.
Higher
D&B Method TBM Method Lower (1.5–6 times)
Lower std. dev. Higher std. dev.
Geometry “Any” shape∗ Circular (24 %)∗ (45 %)∗∗
Almost same range∗∗ Better prediction Uncertain prediction
2 2
3 m –180 m Advance rate Low potential High potential
TBM micro tunnelling: 0.9–3 m2 Rock mass Lower Much higher
Cross Section Not competitive influence
Area small Competitive small
General layout Almost Restrictions ∗ ∗∗
, , Case stories (Stewart et al. (2006).
no restrictions
Tunnel Length Shorter Longer
Optimal 3 km (5 km–25 km) Table 5. Comparison between D&B and TBM method
Start-up Time Shorter Much longer related to flexibility.
5–6 months 6–12 months
(new machine) (new machine) D&B Method TBM Method
Niches and Less problematic More problematic
Branch Tunnels Profile Highly Not flexibility
Layout, rock support. . . High Very low

“any shape” excavation means within reasonable contour Advance in crushed Easier Very difficult
tunnel. zones
∗∗
Commonly cross section areas used. Profile variability High Fairly limited
in construction

Table 2. Comparison between D&B and TBM method


related to final purpose considerations.
Table 6. Comparison between D&B and TBM method
D&B Method TBM Method related to risk.

Purpose by Any purpose Variably suitable D&B Method TBM Method


geometry Road Water
Purpose by Lower Higher Geological risk Lower Higher
quality Rock mass conditions Any Optimal midrange

826
Table 7. Comparison between D&B and TBM method Table 11. Comparison between D&B and TBM method
related to ground stability. related to the environmental disturbance.

D&B Method TBM Method D&B Method TBM Method

Ground stability Lower Higher Noise and vibrations Higher Significantly


Water inflow Higher Lower 50–75% lower
induced reduction Environmental impact More difficult Easier
Water pressure Lower Higher acceptable acceptable
influence Blasting fumes Continuously Not
Rock stress Lower delay risk Higher delay risk Avoid Contamination Not possible Reduction
conditions potential
Rock support Increased Reduced 30–90%
required Less predictable More predictable
Excavation variations Great variability No variability
Auxiliary support Much easier More difficult
Table 12. Comparison between D&B and TBM method
Faster Slower
related to the adits and implantation layout.

D&B Method TBM Method


Table 8. Comparison between D&B and TBM method
related to operation and construction crew. Temporally access Necessary Omitting or
reducing
D&B Method TBM Method Portal space Little Ample
Electrical power Lower Higher
Operation Cyclical Continuous Difficult access Especially Not appropriate or
(repetitive) appropriate not allowed
Manpower Almost same manpower
per volume excavated
Exc./support Interfere Not interfere
operation 4 CONCLUSIONS
Equipment Inappropriate Appropriate
for mucking non continuous continuous
Construction All skills required Less skills required There is not too much research about the selection of
crew More difficult Easier training the excavation method, D&B versus TBM, based on
training field data. Many “subjective” statements are done.
Most of the authors agree that the main advan-
tages of the D&B method are high flexibility of the
method, almost no restrictions in the general layout,
Table 9. Comparison between D&B and TBM method great adaptability to unexpected situations or lower
related to construction costs. start-up and initial investments.
In the TBM method case, most of the authors agree
D&B Method TBM Method
in the most suitability for longer tunnels, has high
Design cost Lower Higher potential in advance rate, high potential reducing of
Initial investment Lower Higher the rock support and overbreak with a concrete lin-
Adits impact: High Limited ing more predictable, the possibility of omitting and
investment and cost reducing temporally access or less skills and easier
Marginal rate More increased Less increased training of the crew. As well as most of them have a
Construction costs Not vary Highly variable wide acceptance that the disadvantages of the TBM
very much method are a high geological risk, high cost design
Life time cost Higher Significantly and initial investments or long start-ups.
lower
The choice is more complex than a simple economic
issue and rarely the selection is clear from the early
stages of the projects. Depending on the particular cir-
Table 10. Comparison between D&B and TBM method cumstances of a project, the parameters that in a case
related to overbreak and tunnel profile. are not even considered may be decisive in the choice
for others.
D&B Method TBM Method Hybrid solutions, considering the excavation meth-
ods advantages, D&B & TBM, should be considered
Overbreak Higher 15–25 cm. Much lower whenever circumstances allow.
<10 cm. A further work it will consist in the application of
Tunnel profile Difficult Nearly total
the risk matrix method considering all the parame-
quality
Filling concrete High extra cost Limited extra cost ters described in the present paper. Application of the
Concrete lining Less predictable More predictable matrix can be utilised in the decision of the excavation
method in future tunnelling projects.

827
REFERENCES Jodl, H.G. & Resch, D. 2011. NATM and TBM – comparison
with regard to construction operation. Geomechanics and
Barton, N. 2002. TBM tunnelling in jointed and faulted rock. Tunnelling, vol. 4, August, 2011, No 4, 337–345.
A.A. Balkema, Rotterdam. ISBN 90 5809 341 7 Lieb, R.H. & Ehrbar, H. 2011. Gothard Base Tunnel. Risk
Barton, N. 2012. Reducing risk in long deep tunnels by Management of the World’s Longest Railway Tunnel:
using TBM and Drill and Blast methods in the same Lessons learnt. W T C (ITA/AITES) Helsinki, Finland
project-the hybrid solution. Journal of Rock mechanics (2011).
and Geotechnical Engineering. 2012, 4 (2): 115–126. Lislerud, A. 1988. Hard Rock Tunnel Boring: Prognosis and
Barton, N. 2013. Hybrid TBM and Drill-and-Blast from the Costs. Tunnelling and Underground Space technology,
start. Tunnelling Journal, December 2012/January 2013. 1988, Vol.3 No.1, pp 9–17.
Bauer, F.; Hödl, K.J,; Lemmerer, J.; Obermeier, O. & Zwit- Maidl, B.; Schmid, L.; Ritz, W. & Herrenknecht, M. 2008.
tnig, G. 2011. Widening of the Westbahn line to four Hard Rock Tunnel Boring machines. Ernst & Sohn.
tracks: Experience in the selection of the tunnelling Moritz, B.; Wagner, H.; Mussger, K.; Handke, D. & Harer
method. Geomechanics and Tunnelling, August, 2011, G 2011. Criteria for the selection of tunnelling method
No 4, 285–294. through the example of the Koralm Tunnel. Geomechanics
Blindheim, O. T.; Johansen, E. D. & Hegrenæs, A. 1998. and Tunnelling, vol. 4, August, 2011, No 4, 305–316.
Bored Road Tunnels in hard rock. Publication NO.11, Myrvang, A.; Blindheim, O.T. & Johansen, E. D. 1998.
Norwegian Tunnelling Society. Rock stress problems in bored tunnels. Publication NO.11,
Bruland, A. 1998. Hard Rock Tunnel Boring. PhD The- Norwegian Tunnelling Society.
sis.The Norwegian University of Science and Technology Nicholas, P. 2006. Micro tunnelling – Methods and Devel-
(NTNU). Trondheim, Norway. opment. International Conference and Exhibition on
Bruland, A. 2010. Pre-investigations and prediction for TBM Tunnelling and Trenchless Technology, Malaysia (2006).
tunnels-the NTNU model. Seminar: TBM Applications, Nord, G. & Stille, H. 1988. Bore and Blast Techniques
2010. Norwegian Tunnelling Society, Bergen, Norway. in Different Types of rock: Sweden’s Experience. Tun-
Hansen, A.M. 2008. TBM vs D&B – Pros and Cons, AMH nelling and Underground Space technology, 1988, Vol.3,
Consult AS. Personal communication. pp 45–50
Kaiser, P.K. & McCreath, D.R. 1994. Rock Mechanics Con- Nord, G. 2006. TBM versus Drill and Blast, the choice of
siderations for Drilled or Bored Excavations in Hard Rock. tunnelling method. International Conference and Exhibi-
Tunnelling and Underground Space technology, 1994, tion on Tunnelling and Trenchless Technology, Subang,
Vol.9 No.4, pp 425–437. Selangor, Malaysia.
Ehrbar, H. 2008. Gothard Base Tunnel, Switzerland. Expe- Spiegl, M.; Sander, P.; Pellar, A.; Maidl, U.; Herdina, J. &
riences with different tunnelling methods. 2 Congresso Feistmantl, K. 2011. The conclusions of risk analysis as
Brasileiro de Tuneis e Estructuras Subterraneas. a basis for deciding between variants through the exam-
Ehrbar, H.; Beeler, P.; Neuenschwander, M. & Bianchi, M. ple of Contract H8. Geomechanics and Tunnelling, vol. 4,
2008. Tough decisions for mega-projects. A methodol- August, 2011, No 4, 295–304.
ogy for decision making on time-relevant measures at Stewart, P.; Ramezanzadeh, A. & Knights, P. 2006. Bench-
the Gothard Base Tunnel. WTC (ITA/AITES) Vancouver, mark Drill and Blast and Mechanical Excavation Advance
Canada (2010). Rates for Underground Hard-Rock Mine Development.
Ehrbar, H.; Sala, A. & Wick, R. 2012. Drives in the Gothard Australian Mining Technology Conference: 41–63.
Base Tunnel – A review. Findings and lessons learned from Tarkoy, P.J. 1995. Comparing TBMs with drill+blast excava-
the client’s viewpoint. Swiss Tunnel Congress (2012). tion. Tunnels & tunnelling. October, 1995.
Eskesen, S. D.; Tenborg, P.; Kampmann, J. & Veicherts, T.H. Tarkoy, P. & Byram, J.E. 1991. The advantages of tunnel bor-
2004. Guidelines for tunnelling risk management: Inter- ing: a qualitative/quantitative comparison of D&B and
national Tunnelling Association, Working Group No. 2 TBM excavation. Hong Kong Engineering, 1991.
(ITA/AITES). Tunnelling and Underground Space tech- Thuro, K. & Plinninger, R.J. 2003. Hard Rock tunnel bor-
nology, 2004, Vol.19 pp 217–237. ing, cutting, drilling and blasting: rock parameters for
Gütter, W.; Jäger, M.; Rudigier, G. & Weber, W. 2011. excavability. ISRM2003-Technology roadmap for rock
TBM versus NATM from the contractor’s point of view. mechanics, South African Institute of Mining and Met-
Geomechanics and Tunnelling, August, 2011, vol. 4, allurgy.
327–336. Thomas A.H. et al. 2007. Risk Management of the construc-
Holen, H. 1998. TBM vs Drill & Blast Tunnelling. Publica- tion of tunnels using Tunnel Boring Machines (TBMs).
tion NO.11, Norwegian Tunnelling Society. Underground Space – the 4th Dimension of Metropolises.

828

View publication stats

You might also like