Professional Documents
Culture Documents
NORD G TBM VS DRILL & BLAST
NORD G TBM VS DRILL & BLAST
net/publication/264942493
CITATIONS READS
6 4,989
2 authors:
Some of the authors of this publication are also working on these related projects:
Hard Rock Tunnel Boring: Performance Predictions and Cutter Life Assessments View project
All content following this page was uploaded by Javier Macias on 26 April 2017.
ABSTRACT: The right choice of the excavation method is essential in hard rock underground projects. The
Drill and Blast (D&B) and Hard Rock Tunnel Boring Method (TBM) are widely and successfully used. Selecting
the most appropriate excavation method is not simple as it is depending of several parameters and particular
conditions. The purpose of this paper is to make a review of the parameters involved in the selection of proper
excavation method. The applicability and level of convenience of each excavation method in function of every
parameter defined will be briefly discussed. A final resume of the excavation method comparison is presented
and proposed to be general guidelines at the early stages in hard rock tunnelling.
823
With both methods the cross section area available time equipment, time consumption in assembling and
to excavate are similar, e.g. TBM method can be used start-up (Lislerud, 1988).
from 2–3 meters diameter and up to approx. 15 m For a new TBM, the delivery time is 6–12 months
according to Hansen (2008). Nowadays, tunnel boring (Holen, 1998) or 10–12 months (Stewart et al., 2006;
method can even be used in smaller excavation areas Hansen, 2008). For a new drill-jumbo 5–6 months
using micro tunnelling. In hard rock conditions it may (Stewart et al., 2006).
be successful from 900 mm. (Nicholas, 2006). The erection time of a TBM and backup, small and
TBMs are more competitive for tunnels with small medium hard rock TBMs, takes usually 3–6 weeks
cross sections (Nord et al., 1988, 2006; Gütter et al., depending local conditions and machinery available
2011). There are limitations in the both methods for (Holen, 1998). Erection times are highly variable
very small diameters (Nord. et al., 1988). worldwide and should be considered with caution.
Regarding to the general layout, e.g. curve radius, It is also important to consider that TBM method
slope…, the TBM method has more limitations needs a more comprehensive study in the design phase
(Holen, 1998; Stewart et al., 2006). However, the D&B with widely geological pre-investigation.
method has almost no limitations (Holen, 1998; Jodl,
2011; Stewart et al., 2006).
The length of the tunnel is a key parameter from 2.5 Health, safety and working
the technical and economical point of view. The TBM environment
method is more competitive for long tunnels while
D&B method is for short tunnels (Nord, 1988; Holen, There are almost no worldwide historical data supports
1998; Ehrbar, 2008; Jodl, 2011). in the literature to say that one method is safer than
It would be risky to define lengths since every the other (Holen, 1998, Tarkoy, 1995), but it is widely
project has its particular characteristics. It is largely accepted that less numbers of accidents occur with the
accepted in the literature that in 3 km length there is a TBM method.
tipping point. By used of the tunnel boring excavation method
In a large number of projects the excavation of serious accident risk from storing or handling explo-
niches, branch tunnels, cavern and/or extended cross sives are avoided (Hansen, 2008, Holen, 1998) and
sections excavation are required. Since normally drill the safety is higher in the face and work area (Tarkoy,
and blast is the technique applied, it creates interfer- 1991). In practically all types of TBM the rock support
ences in the boring operation resulting in machine is installed from protected areas.
downtimes (Holen, 1998). Extra cost in drilling equip-
ment and workers with special drill and blast skills has
to be considered. 2.6 Advance rate
From the authors opinion it should be considered
that in the TBM method, the initial part of the tunnel The advance rate has a high impact in the total
is normally performed by D&B technique. construction time and excavation cost.
In normal conditions, it is accepted for many
researchers that the advance rate in the TBM method is
much higher than with drill and Blast method (Kaiser,
2.3 Final purpose considerations 1994, Tarkoy, 1995, Holen, 1998, Stewart et al., 2006,
The excavation geometry and the final quality required Nord, 2006, Hansen, 2008, Ehrbar, 2008).
are considerations to consider for the final use of the The excavation rate, in normal conditions, with
underground project. TBM method is estimated 4–6 times faster than with
In water tunnels, the head loss due to wall fric- D&B method (Tarkoy, 1995), 1.5–5 (Holen, 1998) or
tion between unlined TBM tunnels and drill and nearly to 1–3 times according to Stewart et al. (2006).
blast is substantial. Cross section reductions between The author’s opinion is that would be risky to define a
33% (Hansen, 2008) and 40% (Holen, 1998) can ratio due to conditions variability worldwide.
be achieved. In road tunnels, the circular excavation However with the D&B method it is easier to
profile is not optimal. advance in crushed zones due to the high versatility
Since in the D&B method “any” shape is possible, of the method (Lislerud, 1988).
it is more adapted to any final purpose of the project The influence of rock in TBM excavation makes
(Ehrbar, 2008). the advance rate estimation much more difficult and
The final operation facilities of the tunnels, as water uncertain (Nord et al., 2006).
and frost protection, can be simplified and optimized,
since systems can be mounted on an even and exact
profile using the TBM method (Hansen, 2008). 2.7 Flexibility
Flexibility in an excavation method is related to the
ability of adapting it to changes in the layout profile
2.4 Start-up time
and in the rock mass conditions.
The start-up time in the TBM project is much longer The TBM method is less or even not flexible than the
than in the D&B method. This is due to longer delivery D&B method. Changes of the TBM diameter is almost
824
limited depending on the machine design, and align- 2.11 Costs
ment during the construction stage (Hansen, 2008;
Construction time and cost detailed studies must be
Stewart et al., 2006).
made at the earliest project stages and have to be
The Drill and Blast method advance easier in
updated periodically Ehrbar (2008).
crushed zones (Lislerud, 1988). This easier advance
In TBM method, capital cost or initial investment
involves a low safety and ground stability risk.
are higher while marginal cost for the excavation
D&B method is the best excavation method for
phase are less (Holen H., 1998).This means important
underground projects with highly variable rock con-
finance and negative cash flows at the beginning of the
ditions or variable shapes (Ehrbar, 2008).
project which is a disadvantage for the TBM method.
In addition, the excavation cost for TBM method has
large variability (Holen, 1998),
2.8 Risk However, life time costs, operation and mainte-
Tunnelling, included D&B and TBM method, is nance, for TBM excavation may be significantly less
exposed to greater risks especially because the ground than for a D&B tunnels (Hansen A.M., 2008).
to excavate and its behavior knowledge is limited The most extraordinary cost saving that can be done
(Thomas et al., 2007). with TBM excavation is the possibility of eliminating
TBM method has higher advance risk (Stewart et al., temporary excavation structures such as access adits
2006). The TBM risk takes particular significance in according Tarkoy (1995).
the case of long and deep hard rock tunnels (Barton, As already mentioned, TBM method reduces the
2000). rock support. The amount of rock support and concrete
TBM method requires a more complete and detailed lining are more predictable in the TBM method for
geological investigation, mapping and testing during normal conditions (Hansen, 2008). This means lower
the planning stage. More time and cost in the design rock support costs and more predictable rock support
phase is necessary to evaluate the project viability and lining costs.
(Hansen, 2008; Bruland, 2010). Anyway, tunnel cost estimation in the TBM method
Highly variable rock conditions favor the choice of is much more difficult and uncertain (Nord et al.,
the blasting method (Ehrbar, 2008). 2006).
825
as TBM requires more electric power than drill and 3 CONCLUSIVE REMARKS
blast (Hansen, 2008).
In projects with difficult access, complicated orog- A summary in table form of the parameters involved
raphy or urban areas, D&B method is especially in the excavation method choice discussed earlier are
appropriated (Ehrbar, 2008). TBM method is more shown in the following.
suitable for projects with a good accessibility.
Table 3. Comparison between D&B and TBM method
2.15 Contractual considerations in the choice of related to health, safety and working environment.
the excavation method
D&B Method TBM Method
High risks are involved in underground construction.
Uncertainties in the rock conditions and behavior, Safety Lower Higher
unforeseen conditions, dependency of the excavation Storage Terrorism and Avoided
method and the high construction risk are associated explosives accident risk
Handling Serious accident Avoided
with this type of construction. Therefore is very impor-
explosives rick
tant a specific and differently contracting practices Rock support No protected area Protected area
(Ehrbar H., 2008). installation
The choice of the excavation method should be Working Temporary worse Improved
responsibility of the contractor, always based on the environment Toxic gases Dust
owner’s comprehensive design, except in special cases Principal safety Handling and Cutter changes
with project restrictions (Ehrbar H., 2008). risk storage explosives
The level of initial investigation should be adapted Loading and
to the excavation method requirements. hauling
The total investment and delivery time for new
machines emphasizes the need for reliable prognoses
of rock conditions (Barton, 2000). Table 4. Comparison between D&B and TBM method
related to advance rates.
Table 1. Comparison between D&B and TBM method D&B Method TBM Method
related to the project design considerations.
Higher
D&B Method TBM Method Lower (1.5–6 times)
Lower std. dev. Higher std. dev.
Geometry “Any” shape∗ Circular (24 %)∗ (45 %)∗∗
Almost same range∗∗ Better prediction Uncertain prediction
2 2
3 m –180 m Advance rate Low potential High potential
TBM micro tunnelling: 0.9–3 m2 Rock mass Lower Much higher
Cross Section Not competitive influence
Area small Competitive small
General layout Almost Restrictions ∗ ∗∗
, , Case stories (Stewart et al. (2006).
no restrictions
Tunnel Length Shorter Longer
Optimal 3 km (5 km–25 km) Table 5. Comparison between D&B and TBM method
Start-up Time Shorter Much longer related to flexibility.
5–6 months 6–12 months
(new machine) (new machine) D&B Method TBM Method
Niches and Less problematic More problematic
Branch Tunnels Profile Highly Not flexibility
Layout, rock support. . . High Very low
∗
“any shape” excavation means within reasonable contour Advance in crushed Easier Very difficult
tunnel. zones
∗∗
Commonly cross section areas used. Profile variability High Fairly limited
in construction
826
Table 7. Comparison between D&B and TBM method Table 11. Comparison between D&B and TBM method
related to ground stability. related to the environmental disturbance.
827
REFERENCES Jodl, H.G. & Resch, D. 2011. NATM and TBM – comparison
with regard to construction operation. Geomechanics and
Barton, N. 2002. TBM tunnelling in jointed and faulted rock. Tunnelling, vol. 4, August, 2011, No 4, 337–345.
A.A. Balkema, Rotterdam. ISBN 90 5809 341 7 Lieb, R.H. & Ehrbar, H. 2011. Gothard Base Tunnel. Risk
Barton, N. 2012. Reducing risk in long deep tunnels by Management of the World’s Longest Railway Tunnel:
using TBM and Drill and Blast methods in the same Lessons learnt. W T C (ITA/AITES) Helsinki, Finland
project-the hybrid solution. Journal of Rock mechanics (2011).
and Geotechnical Engineering. 2012, 4 (2): 115–126. Lislerud, A. 1988. Hard Rock Tunnel Boring: Prognosis and
Barton, N. 2013. Hybrid TBM and Drill-and-Blast from the Costs. Tunnelling and Underground Space technology,
start. Tunnelling Journal, December 2012/January 2013. 1988, Vol.3 No.1, pp 9–17.
Bauer, F.; Hödl, K.J,; Lemmerer, J.; Obermeier, O. & Zwit- Maidl, B.; Schmid, L.; Ritz, W. & Herrenknecht, M. 2008.
tnig, G. 2011. Widening of the Westbahn line to four Hard Rock Tunnel Boring machines. Ernst & Sohn.
tracks: Experience in the selection of the tunnelling Moritz, B.; Wagner, H.; Mussger, K.; Handke, D. & Harer
method. Geomechanics and Tunnelling, August, 2011, G 2011. Criteria for the selection of tunnelling method
No 4, 285–294. through the example of the Koralm Tunnel. Geomechanics
Blindheim, O. T.; Johansen, E. D. & Hegrenæs, A. 1998. and Tunnelling, vol. 4, August, 2011, No 4, 305–316.
Bored Road Tunnels in hard rock. Publication NO.11, Myrvang, A.; Blindheim, O.T. & Johansen, E. D. 1998.
Norwegian Tunnelling Society. Rock stress problems in bored tunnels. Publication NO.11,
Bruland, A. 1998. Hard Rock Tunnel Boring. PhD The- Norwegian Tunnelling Society.
sis.The Norwegian University of Science and Technology Nicholas, P. 2006. Micro tunnelling – Methods and Devel-
(NTNU). Trondheim, Norway. opment. International Conference and Exhibition on
Bruland, A. 2010. Pre-investigations and prediction for TBM Tunnelling and Trenchless Technology, Malaysia (2006).
tunnels-the NTNU model. Seminar: TBM Applications, Nord, G. & Stille, H. 1988. Bore and Blast Techniques
2010. Norwegian Tunnelling Society, Bergen, Norway. in Different Types of rock: Sweden’s Experience. Tun-
Hansen, A.M. 2008. TBM vs D&B – Pros and Cons, AMH nelling and Underground Space technology, 1988, Vol.3,
Consult AS. Personal communication. pp 45–50
Kaiser, P.K. & McCreath, D.R. 1994. Rock Mechanics Con- Nord, G. 2006. TBM versus Drill and Blast, the choice of
siderations for Drilled or Bored Excavations in Hard Rock. tunnelling method. International Conference and Exhibi-
Tunnelling and Underground Space technology, 1994, tion on Tunnelling and Trenchless Technology, Subang,
Vol.9 No.4, pp 425–437. Selangor, Malaysia.
Ehrbar, H. 2008. Gothard Base Tunnel, Switzerland. Expe- Spiegl, M.; Sander, P.; Pellar, A.; Maidl, U.; Herdina, J. &
riences with different tunnelling methods. 2 Congresso Feistmantl, K. 2011. The conclusions of risk analysis as
Brasileiro de Tuneis e Estructuras Subterraneas. a basis for deciding between variants through the exam-
Ehrbar, H.; Beeler, P.; Neuenschwander, M. & Bianchi, M. ple of Contract H8. Geomechanics and Tunnelling, vol. 4,
2008. Tough decisions for mega-projects. A methodol- August, 2011, No 4, 295–304.
ogy for decision making on time-relevant measures at Stewart, P.; Ramezanzadeh, A. & Knights, P. 2006. Bench-
the Gothard Base Tunnel. WTC (ITA/AITES) Vancouver, mark Drill and Blast and Mechanical Excavation Advance
Canada (2010). Rates for Underground Hard-Rock Mine Development.
Ehrbar, H.; Sala, A. & Wick, R. 2012. Drives in the Gothard Australian Mining Technology Conference: 41–63.
Base Tunnel – A review. Findings and lessons learned from Tarkoy, P.J. 1995. Comparing TBMs with drill+blast excava-
the client’s viewpoint. Swiss Tunnel Congress (2012). tion. Tunnels & tunnelling. October, 1995.
Eskesen, S. D.; Tenborg, P.; Kampmann, J. & Veicherts, T.H. Tarkoy, P. & Byram, J.E. 1991. The advantages of tunnel bor-
2004. Guidelines for tunnelling risk management: Inter- ing: a qualitative/quantitative comparison of D&B and
national Tunnelling Association, Working Group No. 2 TBM excavation. Hong Kong Engineering, 1991.
(ITA/AITES). Tunnelling and Underground Space tech- Thuro, K. & Plinninger, R.J. 2003. Hard Rock tunnel bor-
nology, 2004, Vol.19 pp 217–237. ing, cutting, drilling and blasting: rock parameters for
Gütter, W.; Jäger, M.; Rudigier, G. & Weber, W. 2011. excavability. ISRM2003-Technology roadmap for rock
TBM versus NATM from the contractor’s point of view. mechanics, South African Institute of Mining and Met-
Geomechanics and Tunnelling, August, 2011, vol. 4, allurgy.
327–336. Thomas A.H. et al. 2007. Risk Management of the construc-
Holen, H. 1998. TBM vs Drill & Blast Tunnelling. Publica- tion of tunnels using Tunnel Boring Machines (TBMs).
tion NO.11, Norwegian Tunnelling Society. Underground Space – the 4th Dimension of Metropolises.
828