Professional Documents
Culture Documents
Topic 2.2.1 Additional Notes
Topic 2.2.1 Additional Notes
Example 1
A company is producing and selling 3,000 units of Product A on a monthly basis. Below are the
information related to this product.
Unit Cost $
Direct Material (1kg*$6 per kg) 6.00
Direct Labour (2hours*$4 per hour) 8.00
Direct Expenses 2.00
REQUIRED
a) Determine the overhead cost to be absorded by a unit of Product A.
b) Calculate the total cost per unit of Product A.
Unit costs
Prime cost $6 + $8 + $2 = $16
Overhead Analysis
To determine the overhead per unit for finished goods,
Absorption costing:
A method that absorbs overhead costs into the TOTAL PRODUCTION COST for each cost
unit produced.
Considers all production costs, both fixed and variable.
Cohort 1803MA
Compiled by: Cheryl. TYX
• Collection of Overheads
Step 1
• Primary Distribution
• Allocation
Step 3 • Apportionment
• Secondary Distribution
Step 4 • Reapportionment
• Final distribution
• Absorption
Step 5 • Overheads Absorption Rate (OAR)
Cohort 1803MA
Compiled by: Cheryl. TYX
STEP 2
Cost Centres:
A production or service location whose costs may be attributed to costs units.
A department where costs are accumulated
Production department:
Where the products are manufactured
Service department:
Department that supports the other departments
Example: technical support, marketing
STEP 3
Allocation:
The process of charging costs that derived from a cost centre directly to the particular cost
centre.
Eg: direct costs allocated to relevant cost centre
Apportionment:
Many expenses of the business such as rent and rates are shared by a number of different cost
centres.
These joint expenses must be apportioned between cost centres on some suitable basis.
The process of charging overhead costs to a cost centre on a rational basis.
STEP 5
The total of each department is then absorbed into a cost unit using Overheads Absorption
Rate (OAR).
Cohort 1803MA
Compiled by: Cheryl. TYX
The Absorption of Overheads
The idea here with calculating an overhead absorption rate (OAR) is that we are using
𝑩𝒖𝒅𝒈𝒆𝒕𝒆𝒅 𝑶𝒗𝒆𝒓𝒉𝒆𝒂𝒅
= OAR
𝑩𝒖𝒅𝒈𝒆𝒕𝒆𝒅 𝑩𝒂𝒔𝒆
1. Use direct labour hours = Labour intensive and there is little machinery used/ machine
costs are low.
2. Use the machine hour = Production methods are capital intensive or machinery costs are
relatively high.
3. Other suitable bases can also be direct labour cost rate, direct material cost rate, unit
produced rate and etc.
The actual overheads incurred will only be known or determined at the end of the
period.
However, evaluation of cost units (circulation of cost/unit) is an on-going process throughout the
period.
Predetermined overhead absorption rates are required in advance of the period using
estimated or budgeted figures for overhead and for the number of units of the
absorption base.
Reason:
1. The total expected cost of production must be identified in advance
2. To enable selling prices to be calculated
3. Ensure that expected overhead costs are fully recovered.
4. Actual figures are not available
Cohort 1803MA
Compiled by: Cheryl. TYX
During the period:
Cost per unit:
$
Direct materials cost X
Direct labour cost X
Direct expense X
Prime Cost X
Step 1:
Budgeted Overhead
Budgeted Base
= OAR
Step 2:
OAR
x Actual Base
Overhead Absorbed
Step 3:
Overhead Absorbed
- Overhead Incurred (Actual)
Over/ (Under) Absorbed
Cohort 1803MA
Compiled by: Cheryl. TYX
Overhead absorption rate:
Based on predictions of future levels of activity and budgeted levels of overhead
expenditure
Cohort 1803MA
Compiled by: Cheryl. TYX