B Mobilization A 1 DAY C Layout B 1 DAY D Excavation B 3 DAYS E Grading Areas C,D 3 DAYS F Utility Excavation C,D 3 DAYS G Concrete Pouring C,D 2 DAYS H Wall Footing E,F,G 2 DAYS I CHB Layout H 10 DAYS J Column H 5 DAYS K Beam J 5 DAYS L Wall Construction I,K 6 DAYS M Roofing Installation I,K 5 DAYS N Ceiling Works M 6 DAYS O Tile Works M 8 DAYS P Painting L 20 DAYS Q Windows & Doors N,O,P 4 DAYS R Fixtures Q 3 DAYS