PERT/CPM

ACTIVITY DESCRIPTION PREDECESSORS ESTIMATED TIME

A Site Clearing 1 DAY


B Mobilization A 1 DAY
C Layout B 1 DAY
D Excavation B 3 DAYS
E Grading Areas C,D 3 DAYS
F Utility Excavation C,D 3 DAYS
G Concrete Pouring C,D 2 DAYS
H Wall Footing E,F,G 2 DAYS
I CHB Layout H 10 DAYS
J Column H 5 DAYS
K Beam J 5 DAYS
L Wall Construction I,K 6 DAYS
M Roofing Installation I,K 5 DAYS
N Ceiling Works M 6 DAYS
O Tile Works M 8 DAYS
P Painting L 20 DAYS
Q Windows & Doors N,O,P 4 DAYS
R Fixtures Q 3 DAYS