AOH Activity Planning (Autosaved) - 1
AOH Activity Planning (Autosaved) - 1
AOH Activity Planning (Autosaved) - 1
Generator CTs terminal box tightness check and cleaning 4 27-Dec-19 30-Dec-19 NA
11KV Unit Board (Section A & B) & it's feeders Testing. 7 4-Jan-20 10-Jan-20 NA
415V Unit PCC Sec - A & its transformers 2 28-Dec-19 29-Dec-19 Available
415V Unit PCC Sec - B & its transformers 2 31-Dec-19 1-Jan-20 Available
TDBFP LOP power souce & panel segregation work 8 2-Jan-20 9-Jan-20 Cable PR to be done Panel PR
done
UT (Unit Transformer)
GTU Panel Inspection, Cleaning & Terminal Tightness check 2 31-Dec-19 1-Jan-20 NA
Pre Activities
FUSE CRTRG;PN:XRNM-
MEL391216060168 41 External manpower agency Prateek
12/160;HGH VLTG;HRC
FUSE CRTRG;PN:XRNM-
MEL391216060169 39 External manpower agency Prateek
12/80;HGH VLTG;HRC
FUSE CRTRG;PN:XRNM1-
MEL391216060526 18 External manpower agency Prateek
12/63;HRC,12KV,63A
FUSE CRTRG;PN:XRNM-
MEL391216060164 12/100;HGH VLTG;HRC 13 external testing agency Prateek
Prateek
Prateek
Prateek
In the scope of UPS supplier
Prateek
Prateek
Nilanjan
Ritesh
external manpower agecny Ashish
Prateek
Prateek
Prateek
Prateek
Prateek
Prateek
Prateek
Prateek
Prateek
Prateek
External testing agency / Motor
Prateek
service vendor
Prateek
Prateek
Prateek
Prateek
Prateek
Prateek
Prateek
Prateek
Prateek
Prateek
Varinder
Varinder
Varinder
Rahul
Gorakhnath
Naveen Gupta
Naveen Gupta
Muthu
Remarks
Scaffoldling required
Scaffolding required
Completed
CW-A,BFP,Mill A,C,E,CEP-A,ID-A,PA-A,FD-
A,Unit tarfo-A,ESP trafo -A,TDEB-A,OCCW-
A,BA Sluury A,Lighting trafo-A
CW-B,Mill B,D,F,CEP-B,ID-B,PA-B,FD-B,Unit
tarfo-B,ESP trafo -B,TDEB-B,OCCW-B,BA
Sluury B,Lighting trafo-B
CW-A,BFP,Mill A,C,E,CEP-A,ID-A,PA-A,FD-
A,Unit tarfo-A,ESP trafo -A,TDEB-A,OCCW-
A,BA Sluury A,Lighting trafo-A
CW-B,Mill B,D,F,CEP-B,ID-B,PA-B,FD-B,Unit
tarfo-B,ESP trafo -B,TDEB-B,OCCW-B,BA
Sluury B,Lighting trafo-B
Not planned
Not planned
2
2
2
2
3
2
1
2
1
1
1
4
4
2
2
4
4
2
2
2
12
12
1
1
4
HT Motor Bearing Inspection, Cleaning, Regreasing (as applicable) and
Terminal tightness check
S.No. Equipments Remark
1 IDF A
2 IDF B
3 FDF A
4 FDF B
5 PAF A
6 PAF B
7 Mill A -Complete overhauling
8 Mill B
9 Mill C
10 Mill D
11 Mill E
12 Mill F
13 TDBFP Booster Pump motor A
14 TDBFP Booster Pump motor B
15 OCCW Pump kotor -A
16 OCCW Pump kotor -B
17 CW pump-A
18 CW pump-A
19 CEP-3A
20 CEP-3A
21 MDBFP
Bushing replacement-Oil
drainge,Filtration,testing,oil
6 Transformer Bushing top up no
7 UPS erection vendor UPS installation Yes
Laxhmi Associates
Precision
As per PO
As per PO
Not to be done
In house
On hold 0.95
0.6
2.45
Deputation Deputation Utilization from
Sl. No. Summary for Manpower in AOH Req. Nos. from Steag from Steag current setup at Difference Remarks
Hazira Vizac Steag TSPL
HMEL TEAM
HMEL TEAM
HMEL TEAM
Proposed Scheduled
Duration date
Contnous
during AOH 26th Decmber
2 Days 30th December During AOH + Synchronisation
2 Days 16th Jan
3 days 12th jan
10 days 28th December
Contnous
during AOH 26th Decmber
Contnous
during AOH 10th december
Contnous
during AOH 10th december
3 days 28th December