home / study / business / operations management / operations management questions and answers / three recent college graduates have forme…

Question: Three recent college graduates have formed a partnership an… Post a question
Answers from our experts for your tough
homework questions
(16 bookmarks)

Three recent college graduates have formed a partnership and have opened an advertising rm. Their rst Enter question
project consists of activities listed in the following table.
a) Draw the precedence diagram.
b) What is the probability that the project can be completed in 24 days or less? In 21 days or less?
c) Suppose it is now the end of the seventh day and that activities A and B have been completed while Continue to post
activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6 and 7. Activities 20 questions remaining
C and H are ready to begin. Determine the probability of nishing the project by day 24 and the probability
of nishing by day 21.

Activity Immediate Time in Days


Predecessor Snap a photo from your
Optimistic Most Likely Pessimistic phone to post a question
We'll send you a one-time downloa
link
A - 5 6 7

B - 8 8 11 888-888-8888 Text me
C A 6 8 11 By providing your phone number, you agree to receive a one-
automated text message with a link to get the app. Standard
messaging rates may apply.
D - 9 12 15

E C 5 6 9
My Textbook Solutions
F D 5 6 7

G F 2 3 7

H B 4 4 5

I H 5 7 8 Operations... Introductio... Corporate..

12th Edition 10th Edition 4th Edition

View comments (1) View all solutions




Expert Answer

Bella Jackson answered this


Was this answer helpful? 14 4
150 answers

https://www.chegg.com/homework-help/questions-and-answers/three-recent-college-graduates-formed-partnership-opened-advertising-firm-first-proje… 1/5
1/31/2021 Three Recent College Graduates Have Formed A Partn... | Chegg.com

 
NEW!
Textbook Solutions Expert Q&A Study Pack Practice 

https://www.chegg.com/homework-help/questions-and-answers/three-recent-college-graduates-formed-partnership-opened-advertising-firm-first-proje… 2/5
1/31/2021 Three Recent College Graduates Have Formed A Partn... | Chegg.com

 
NEW!
Textbook Solutions Expert Q&A Study Pack Practice 

https://www.chegg.com/homework-help/questions-and-answers/three-recent-college-graduates-formed-partnership-opened-advertising-firm-first-proje… 3/5
1/31/2021 Three Recent College Graduates Have Formed A Partn... | Chegg.com

 
NEW!
Textbook Solutions Expert Q&A Study Pack Practice 

View comments (4)




Practice with similar questions

Q: 7. Three recent college graduates have formed a partnership and have opened an advertising rm. Their rst project
consists of activities listed in the following table. a . Draw the precedence diagram. b. What is the probability that the
project can be completed in 24 days or less? In 21 days or less? C. Suppose it is now the end of the seventh day and
that activities A and B have...

A: See answer

Q: 7. Three recent college graduates have formed a partnership and have opened an advertising rm. Their rst project
consists of activities listed in the following table. a. Draw the precedence diagram. b. What is the probability that the
project can be completed in 24 days or less? In 21 days or less? c. Suppose it is now the end of the seventh day and
that activities A and B have...

https://www.chegg.com/homework-help/questions-and-answers/three-recent-college-graduates-formed-partnership-opened-advertising-firm-first-proje… 4/5
1/31/2021 Three Recent College Graduates Have Formed A Partn... | Chegg.com

A: See answer


 Textbook Solutions Expert Q&A Study Pack Practice
NEW!


Show more 

Questions viewed by other students

Q: Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising rm. Their
rst project consists of activities listed in the following table. Use Table B. TIME IN DAYS Activity Immediate
Predecessor Optimistic Most Likely Pessimistic A — 5  6         7      ...

A: See answer

Q: The project described in the following table has just begun. It is scheduled to be completed in 11 weeks. Use Table B1
and Table B2. Activity Estimated Time (weeks) Standard Deviation (wks.) 1-2 4 0.70 2-4 6 0.90 1-3 3 0.62 3-4 9 1.90 a. If
you were the manager of this project, would you be concerned? (Round your intermediate calculations to 2 decimal...

A: See answer 100% (5 ratings)

Show more 

COMPANY

LEGAL & POLICIES

CHEGG PRODUCTS AND SERVICES

CHEGG NETWORK

CUSTOMER SERVICE

© 2003-2021 Chegg Inc. All rights reserved.

https://www.chegg.com/homework-help/questions-and-answers/three-recent-college-graduates-formed-partnership-opened-advertising-firm-first-proje… 5/5

You might also like