Please find the Quotation for the 66KV H FRAME MAINTENANCE WORKS :
TOTAL 3,345,000.00
MATERIALS
1 DISC INSULATOR - 66KV NOS. 20.00 6,200.00 124,000.00
2 H FRAME PAINTING MATERIAL - SILVER COAT ONLY NOS. 48.00 5,000.00 240,000.00
3 STRAY SET NOS. 76.00 7,500.00 570,000.00
4 BARREL CONNECTOR NOS. 50.00 4,800.00 240,000.00
5 EARTHING ROD AND BFC COMPOUND NOS. 15.00 10,000.00 1,00,000.00
TOTAL 1,274,000.00
NOTE : MATERIAL QUANTITY IS APPROXIMATELY, IT MAY VARY AT THE TIME OF WORKS. FINAL BILLING WILL BE DONE ON AT ACTUAL BASIS.