1. GENERAL
The supplier should confirm availability of the required infrastructure and manpower in
technical bid as given in this specification.
a INFRASTRUCTURE FACILITIES
2
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
b. TESTING FACILITIES :
(a) Digital oscilloscope Dual channel Min.100 MHZ Band width with following
advance features would be preferred. .
Advanced signal processing
TDR measurement
Eye pattern analyzer
Cross talk and ringing analysis
The development shall require at least two engineering graduate (electronics) who
would be responsible for execution of the order . Experience in multilayer PCB
manufacturing using latest state of art technology components like SMT ,
digital electronics components, ASICS & microcontrollers and software application
on .NET platform, Database Management System like ORACLE would be
preferred. Technical persons responsible for the execution of the contract should
be competent enough to substitute / suggest suitable alternatives for the
components which are getting obsolete / not available in the market .
3
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
A. SCOPE OF WORK:
The Scope of this specification is divided into development of a common hardware and
software platform which can be scaled up and down to realize two different monitoring
systems architectures to meet different technical requirements.
The common hardware platform shall be developed as per following architecture which
shall be modular in nature to scale up or scale down the system based on the technical
requirement.
4
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
Two separate SMPS provision to be kept for a. Section-1 only and b. Section-1 and
Section-2 combined.
The project scope is for development of Gerber, PCB, complete card assembly,
firmware, software, testing and integration of the developed system with BHEL existing
server. Bidder to Design & develop PCB manufacturing documents / PCB Gerber files &
test jig and take approval on the same from BHEL before arranging the PCBs and
testing of the card .
The major implementation features of the Distribution monitoring system shall be:
1. Development, Supply, customization, installation, deployment and maintenance of
necessary hardware, software and communication equipment at distribution
transformer site to facilitate monitoring of Distribution Transformer for the purpose
of centralized DT monitoring, data logging and data analysis.
2. Integrating the proposed DTMS system with BHEL Bhopal server.
3. DTMS Software should be scalable in nature, DTMS Software and associated
equipment’s should be capable of handling at-least 2000 connections, without any
additional infrastructure and cost implication.
4. DTMS system should have complete interoperability for accommodating all types
of FRTU/MFM and communication H/W and vice-versa should also be there for
any future up gradation of hardware / software.
5. The proposed solution must efficiently enable all required interfaces and
integration, including integration with the existing software infrastructure of BHEL
server.
6. The supplier shall be responsible for providing all material, equipment and
services specified or otherwise, which are required to fulfill the intent of ensuring
5
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
operability, maintainability and the reliability of the complete work covered under
this specification.
i. SYSTEM ARCHIETECTURE:
6
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
Smart Energy Monitoring unit with cellular modem will be installed at each distribution
transformer site. DTMU will monitor all transformer parameters and transmit the same to
Server at the control center.
Smart Energy Monitoring Unit with cellular modem will be installed at each distribution
transformer site. It should have following functions:
1. Monitor electrical parameters (instantaneous and energy) from distribution
transformer.
2. Monitor harmonics (voltage and current) & Total Demand Distortion (TDD)
3. Monitor transformer parameters for limit conditions (alarm conditions):
a. Over load
b. Load unbalance
c. High harmonics etc. (up-to total sixteen set points can be set)
d. Low transformer oil level
e. High transformer oil temperature
f. Phase failure detection
4. Monitor transformer oil level via digital input.
5. Monitor transformer oil temperature via analog input.
6. Send all parameters to control centre periodically as well as report by exception.
7. Send instant messages to control centre on alarm events mentioned above).
8. Communicate with control centre via cellular modem (3G/4G).
9. Multiple set point minimum 12, so that required alarm set point can be configured
and transmitted to control centre.\
10. The scope also includes supply of following compatible sensors with cabling and
installation to transformer unit:
7
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
a. Current sensor
b. Voltage monitoring arrangement
c. Oil level sensor
d. Temperature sensor
DT Monitoring unit should have following unique features which are essentials for this
project.
a. All the required electrical parameters are available on display and communication.
b. PT input up to 690VAC (Line to line)
c. CT input 1A or 5A
d. PT Burden < 0.15VA. CT Burden: For 5A CT Sec. <0.1 VA, for 1A CT Sec.
<0.02VA
e. CT primary and PT ratio are site configurable.
f. All type of wiring is configurable at site.
g. Four quadrant measurement.
h. All parameters updated on cycle to cycle basis and sampling rate 128 sample per
cycle.
i. Accuracy class 0.2S as per IEC-62053-22:2003.
j. Input frequency: 45-65 Hz.
k. Individual Harmonics for voltage and current till 39th harmonic.
l. Internal RTC.
m. Energy display of nine digits.
n. Data log memory >= 135KB.
o. Front panel LED for calibration check and communication status.
p. Communication protocol: MODBUS RTU, ASCII, DNP 3.0., IEC 104 Required
communication protocol is selectable at site.
q. User defined registers. Minimum 100 user defined registers should be available in
the device.
r. Standard IoT’s of IEC 104 for configuration mapping with SCADA FEP (Front End
Protocol) server.
s. All the parameters should be available as direct reading 32 bit registers.
t. Power Supply: (Self powered)
u. Ambient operating temperature: -10 to 60ºC.
v. Ambient operating humidity: 0 to 95% non-condensing.
w. Standard DIN Rail mounted.
x. Input/output Signals:
a. 4 Digital inputs and 2 digital relay outputs for digital signal monitoring.
b. 3 Analog inputs
y. Cellular Modem with antenna along with SIM card and monthly usage charges for
entire project duration i.e. 24 Months
z. The system shall be mounted on wall or pole, outdoor ABS/Polycarbonate plastic
cabinet.
aa. Required MCB
8
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
Software implementation in control room server should provide following unique features:
9
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
o. Send alarm messages via e-mails to pre-defined users in case on events.
p. Send reports to pre-defined user at set intervals.
q. Results in saving capital equipment by early detection of expected faults.
r. Based on alarm messages received from remote DT sites.
s. Detect location of transformer faults.
t. Detect energy loss based on energy through DT and actual energy billed.
a. The successful bidder shall be responsible for installation and configuration of software, hardware and other
equipment supplied to the satisfaction of the owner.
b. Post Go-Live, the software vendor shall provide support to fix any bug related to implementation. The entire
system would be considered as successfully installed when the software will run with actual live data at site
without any bugs (Bug is lacunae in the system that prevents/ delays an operation or performs a function
within the system at suboptimal level/ at performance level lesser than that specified in this specification or
provides incorrect operational data or provides incorrect results in any data format in the reports generated by
the users).
c. Demonstration of all the features of latest version of software; Acceptance testing of the system thus
implemented to the owner’s satisfaction.
10
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
NOTE:
1. The redundancy logic for all the channels and processor shall be finalized after taking BHEL’s approval.
2. Any other Accessories, ethernet cable etc not mentioned here but required for complete implementation
of the unit shall be under supplier’s scope.
11
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
ITEM no. 3 INDOOR REMOTRANS UNIT:
Server Details:
Processor: i7
RAM: 8GB minimum
Hard-disk: 1TB
Operating System: Windows 10
Port: 2 no. HDMI port, 2 no. USB3.0, ETHERNET
Software: MSOFFICE latest version
12
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
COMPLETE SYSTEM ARCHEITECTURE:
13
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
NOTE: Stage-2 shall be implemented on the BHEL central servers made available to the supplier.
Software implementation in control room server should provide following unique features:
14
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
The application software of the system shall be based on an interactive platform for easy
implementation and understanding and shall be finalized after placement of order and
supplier is responsible to fully implement and prove the same.
The application software shall also have option for self-test of the system.
Application preferably to be developed in JAVA/.NET Database to be developed
preferably on ORACLE 11G
Supplier to ensure Penetration testing to be conducted by CERT-IN empaneled agency
on the application
b) Application source code and its programming software for server application.
v. Test jigs/tools
15
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
Complete test jigs/tools for complete system to be developed and supply along
with clear test instructions for comprehensive testing on test.
CAUTION:
1. Before applying coating, the PCB’s should be tested in all respect.
2. All contacts for connectors and test points & fiber optic ports must be
protected thoroughly by providing suitable cover on it. This cover only be
opened after the coating is dried up.
16
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
3. Standard EMI/EMC protective norms must be followed during the entire
process.
The complete electronics rack should be complied with following type tests and certificate
for the same to be provided by the supplier.
While executing the PO, supplier shall submit to BHEL and take approval for the
following documents for each of the modules mentioned in the enquiry.
1. Test Certificate
2. Burn-in test report
3. Warranty certificate
4. Card Schematics
5. BOM
6. User Manuals
7. System Administrator Manuals
8. Technical Manuals
9. Installation Guides
10. Business Process Guides
11. Program Flow Descriptions
12. Sample Reports
13. Screen Formats
14. Toolkit Guides
15. Troubleshooting Guides
16. Frequently Asked Question (FAQ) Guides
4. WARRANTY.
System along with all the components mounted thereon shall be guaranteed for 24
months from the date of supply or 18 months from date of commissioning whichever is
earlier.
18
CONTROL EQUIPMENT ENGINEERING DIVISION
BHARAT HEAVY ELECTRICALS LIMITED, BHOPAL
All the individual cards and complete rack to be numbered as per following convention:
Following document duly filled must be submitted by the bidder party as annexure to
their technical bid (to be kept in separate sealed envelope) . Otherwise bid will be
technically rejected.
A. Infrastructure details
20