Professional Documents
Culture Documents
Text Section 4
Text Section 4
Date 1-31-13
SECTION 4
4.0 Electrical
4.1 General
A. A manual check of all electrical interlocks to the satisfaction of a Chrysler Group LLC Launch
Technician
B. A machine and/or automated line must run, in the weld mode, with parts and in the presence of a
Chrysler Group LLC Launch Technician.
4.1.6
4.1.7
4.1.7.3
4.1.10
4.1.14
4.1.19.1
Page 2 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.1.21
4.2 Design
Page 3 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
A. Sheet numbers are to run in sequence starting with sheet #1 (1,2,3, etc......). Sheets added after
initial packages are approved must maintain the same flow as the initial design. Alpha numbered
sheets are allowed to be used, with the approval of a Chrysler Group LLC AME Controls Design
Coordinator. For example sheets added to the magnetic's will be placed at the end of the
magnetic circuits and utilize the next available line numbering.
B. Detail numbers are to run in sequence starting with detail #1 (1,2,3, etc......).
4.2.6
A. Hydraulic timing chart showing the peak hydraulic volume demands in G.P.M.
B. Pneumatic timing chart showing the peak pneumatic volume demands in CFM per plant drop.
C. Electrical timing chart showing the peak electrical demands in KVA per plant drop.
D. Water demand chart showing the peak water volume in G.P.M. per plant drop.
Files comprising the Controls Design must be named using the following guideline:
A. AutoCAD
12345001.DWG ---------------------- WD12345’s Sheet 1
C. Programmable Controllers
The FIS controller name plus the programming software’s extension.
12345ROOF1.xxx
Page 4 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
[12345][ROOF1] . [xxx] ------- Programming software’s extension.
| | ----------------------- FIS Controller name.
| ----------------------------------- WD number for this design.
4.2.9
Control Wiring
AC
o 480VAC (above the DP main disconnect) Black/Orange Tracer
o 480VAC (below the DP main disconnect) Black
o 120VAC Red
o 0VAC Common White
o 120VAC Interlock Orange
o 0VAC Interlock Common White/Orange Tracer
DC
o 24VDC Blue
o 0VDC Common White/Blue Tracers
o 24VDC Interlock Orange/Blue Tracer
o 0VDC Interlock Common White/Orange Tracer
Page 5 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
Ground Green
4.2.11
4.2.12
4.2.13
XXXYYZZ
Upon completion of each design, the supplier must provide Approval drawings and a copy of all
applicable calculation files for each WD to the assigned Chrysler Group LLC AME Controls
Design Coordinator from Assembly Manufacturing Engineering (AME) Controls Design in Auburn
Hills. This documentation must be clearly identified with "APPROVAL PRINT". Fourteen (14)
days must be scheduled for the Chrysler Group LLC AME Controls Design Coordinator
approval process.
Completed designs (hardwire, logic, peripherals, etc.) must be resubmitted within fourteen (14)
days after approval corrections or revisions have been returned to the Supplier (“Approved As
Marked” - 80% Complete). This documentation must be clearly identified with "APPROVED FOR
BUILD" (90% Complete).
Page 7 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
When the WD’s contain (FIS/AVI/PFS/PFCS) ITM content Hardware or connectivity, the supplier must
provide one (1) set of (PDF format only) Approval drawings for each WD to the assigned ITM Launch
Coordinator from Information Technologies Management (ITM) in Auburn Hills. The documentation must
be clearly identified with “APPROVAL PRINT”, in the exact format and content, for hardware and
software, as defined above for the Chrysler Group LLC AME Controls Design Coordinator. Fourteen 14
days must be scheduled for the ITM Launch Coordinator approval process.
1. The documentation outlined in this section must be delivered to the designated representative
of the Plant Manufacturing Engineering Department. The Chrysler Group LLC AME Controls
Design Coordinator will provide the name of this contact. The shipping document must be
adequately detailed to show that all of the deliverables per design have been included. The
shipper must be signed by the designated plant representative. The supplier must package and
deliver this documentation and provide a copy of the signed shipper to the Chrysler Group LLC
AME Controls Design Coordinator.
a. (1) 11" x 17" copy of each WD Drawing Set (for production floor)
b. (1) electronic copy of program files for every PLC (for office) (PDF format only).
c. (1) electronic copy of program files for every Programmable Device (i.e. HMIs, EDS, etc…and
all applicable network configuration files) (for office).
d. (1) electronic copy of all applicable Calculations.
e. (1) electronic copy of all applicable “Build” validation reports.
2. The documentation outlined in this section applies to ASME ONLY and must be delivered at
the installation site. The shipping document must be adequately detailed to show that all of the
deliverables per the design have been included. The shipper must be signed by the ASME
Launch Technician. The supplier must package and deliver the documentation and provide a
copy of the signed shipper to the Chrysler Group LLC AME Controls Design Coordinator.
a. (1) 11" x 17" copy of each WD Drawing Set (for Launch Technician).
b. (1) electronic copy of program files for every PLC
c. (1) electronic copy of program files for every Programmable Device (i.e. HMIs, EDS, etc… and
all applicable network configuration files).
d. (1) electronic copy of program files for every robot (for office)
e. (1) electronic copy of all applicable Calculations
f. (1) electronic copy of all applicable “Build” validation reports.
g. (1) hard copy of all applicable “Build” validation reports.
3. The documentation outlined in this section must be delivered to the Chrysler Group LLC AME
Controls Design Coordinator in Auburn Hills. The shipping document must be adequately
detailed to show that all deliverables per the design have been included. The supplier must
Page 8 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
package and deliver this documentation and provide the shipper for the Chrysler Group LLC AME
Controls Design Coordinator signature. The supplier must provide a copy of the shipper for the
Chrysler Group LLC AME Controls Design Coordinator.
The following documentation is required after plant launch. All items listed are to be delivered to the
designated recipients no later than sixty (60) days following "Official" Launch date. All CAD files and
prints are to be current and must have been updated to include ALL changes occurring through launch.
All documentation must be clearly identified with "AS LAUNCHED".
1. The documentation outlined in this section must be delivered to the designated representative of the
Plant Manufacturing Engineering Department for signature. The Chrysler Group LLC AME Controls
Design Coordinator will provide the name of this contact. The shipping document must be adequately
detailed to show that all of the deliverables per design have been included. The shipper must be signed
by the designated plant representative. The supplier must package and deliver this documentation and
provide a copy of the signed shipper to the Chrysler Group LLC AME Controls Design Coordinator.
a. (1) 11" x 17" copy of each WD Drawing Set (for production floor)
b. (1) electronic copy of all AutoCAD files for all WD’s (for office)
c. (1) electronic copy of program files for every PLC (for office)
d. (1) electronic copy of program files for every Programmable Device (i.e. HMI's, EDS, Ethernet Switch
configuration, etc… and all applicable network configuration files) (for office)
e. (1) electronic copy of all applicable Calculations
f. (1) electronic copy of all applicable “In Plant” validation reports
2. The documentation outlined in this section must be delivered to the Chrysler Group LLC AME Controls
Design Coordinator in Auburn Hills. The shipping document must be adequately detailed to show that all
of the deliverables per design have been included. The supplier must package and deliver this
documentation and provide the shipper for the Chrysler Group LLC AME Controls Design Coordinator
signature. The supplier must provide a copy of the shipper for the Chrysler Group LLC AME Controls
Design Coordinator.
Page 9 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
D. General Notes:
1. All documentation for Plant Floor and Technicians is required per machine/tool, not per WD design.
Where more than one tool is built to a common WD design, complete documentation is required for EACH
tool.
3. All electronic documentation must be placed on a CD or DVD media. CD or DVD must be formatted to
be readable on any standard CD or DVD drive. Each CD or DVD must be provided in its own protective
case.
4. Consult Chrysler Group LLC AME Controls Design Coordinator for filename, disk organization, and
labeling requirements.
5. PLC Programs must be completely documented and annotated using project-specified Software.
6. All disks/data/software delivered to Chrysler Group LLC must be virus-free. It is the OEM's
responsibility to implement and police stringent procedures to assure this requirement.
Note: Supplier must provide all over current protective devices through final buy-off at the plant.
4.2.21
Page 10 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.2.23
4.2.27
4.2.28
4.2.29
4.2.31
4.3 Identification
All cables must have approved tags affixed at each end of the cable. These tags must carry the complete
cable identification. Mating receptacles must likewise be identified with the same information. i.e. "WD
12345 - Cable #1", "WD 12345 - Receptacle #1" All cable connections must be shown on WD drawings
and identified with cable and pin numbers. To simplify design, a cable name may be abbreviated within
its' own WD drawing package by omitting the WD number.
4.3.1.1 Receptacles
All receptacles must have conductors identified with the cable number and pin number. This tag will be in
addition to the tag with the wire number.
A. Permanent identification utilizing either an approved engraved tag, mechanically attached to the
front of the enclosure or a Chrysler Group LLC approved oil and weld flash resistant polyester
label Polyester labels must meet the following requirements: Face stock: 2 mil white polyester.
Adhesive: 5 mil acrylic adhesive. Adhesion: min 2.5lbs/inch width on painted metal substrate.
Operating temperature: up to 350 F. Application temp: +45 F. Recommended label supplier:
Whitlam Label Company, Inc. 24800 Sherwood Ave. Center Line, MI 48015-1059 Ph: 586-
757-5100.
Page 12 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
B. Each tag must indicate the device PLC address and Description, function and direction of motion.
Characters must be a minimum 5/32" in height.
C. Tag must be readily visible from the service side of the line and must not be mounted on the
device it identifies or obscure the manufacturer’s label.
Note: For an example of approved tag format contact a Chrysler Group LLC AME Controls Design
Coordinator (reference WD_TAGS)
Example: Drawing
Identification
Note: For an example of approved tag format contact a Chrysler Group LLC AME Controls Design
Coordinator (reference WD_TAGS)
Note: For an example of approved tag format contact a Chrysler Group LLC AME Controls Design
Coordinator (reference WD_TAGS)
Page 13 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.3.6 WD Drawings
The WD drawings must identify all limit switches, proximity switches and solenoids with the address
number and function name. Example:
Example:
A. The EXTD (extended) is based on the position of the driven member and not the position
of the cylinder rod.
B. The RETD (retracted) is based on the position of the driven member and not the position
of the cylinder rod.
C. The color of, and the location of, the position indicator on the HMI is based on whether
the driven member is at the WORK (amber) or Home (green) position.
Note: Nomenclature for horizontal or vertical motions not covered by 4.3.7 or 4.3.8 must be approved by
a Chrysler Group LLC AME Controls Design Coordinator.
4.3.9 Pendants
Pendants must be identified with the WD number and the description as shown on the WD drawings.
Page 14 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.3.12 Wire and Electro-Mechanical Devices
Wires and electro-mechanical devices in systems which are connected to a programmable logic controller
must be designated per the I/O address.
Page 15 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.4 Construction/Installation
4.4.5.1
Page 16 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
(Note: When KANBAN is functional within the receiving plant, in conjunction with PFCS, ONLY the stack
light shall be omitted and identified as a cost savings / credit to Chrysler.)
Page 17 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.4.16 Multi-Conductor Cable - Guidelines
Multi-Conductor cables shall:
Page 18 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.4.19 Crimp Feral
When stranded wire is used and the terminals / lugs are manufactured without pressure plates, crimp
feral(s) shall be installed prior to final wire termination to maintain connection integrity and the ability to
achieve proper torque requirements per the terminal / lug manufacture. When the terminals / lugs are
equipped with pressure plates, crimp feral(s) can be omitted.
Pedestal Sealers
The material handling robot shall be able to purge from the home or "wait to drop" position. The purge
bucket shall be mechanically contained to prevent movement and resides no more than 48" below the
sealer nozzle. The pedestal sealer shall not be positioned more than 7’ from the floor. Nozzles positioned
higher than 7’ from the floor or purge buckets located further than 48" from the nozzle require approval
from the AME process manager.
4.4.23 End of Travel Limit Switch for Bridge, Rail, Trolley and Carrier Switch Actuation Method
The placement of the End of Travel (EOT) limit switch and limit switch actuation cam, or trip dog, for the
process equipment supporting the product build is critical for the safety of the operator, the quality of the
product and prevents damage to the equipment and facility. As the equipment trolley and carrier is
moving with the product, within the design job station, the mechanical actuation cam or trip dog shall be
secured to the trolley in a fashion that will reliably trip the limit switch actuator independent of carrier
movement or carrier swing. The preferred location of the actuator cam, or trip dog, is mounted on the
trolley of the carrier. The preferred location of the EOT limit switch is mounted on the inside of the rail to
protect the limit and avoid Nycoil hose or other facility installation devices that will interfere with the limit
switch function. The supplier will show due diligence of the design and demonstrate the repeatability of
the process under normal and abnormal carrier conditions.
Page 19 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
Photo 4.4.23.a
Photo 4.4.23.b
Page 20 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
Photo 4.4.23.c
4.5.2
4.5.3
4.5.7
Page 21 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
relays and motor overload relays must include auxiliary contacts. A contact from each of these relays
must be wired to PLC inputs for monitoring.
4.5.11
4.5.13
4.5.14
A. All position, sequence, and event indicator lights on operator stations must be driven from PLC
outputs. Separate ladder logic rungs must be used to control these lights.
B. Diagnostic logic in the PLC must blink the position or event indicator light of the next event,
action, or sequence programmed, until the event, action, or sequence is complete. The light must
be held on until the device is no longer sensed by the detection switch (limit switch etc..), event,
action, or sequence begins.
C. The completion of the previous event, action or sequence must be used to blink the next event,
action, or sequence indicator light.
D. When the machine has completed the closing cycle, the indicator lights for all event, actions, or
sequences must be held on. As the opening cycle begins, the indicator light for the next event,
action or sequence must begin to blink. When the machine has completed the opening cycle the
functions listed in "B" through "D" must be repeated for the next cycle.
A. Wherever style sensitive parts are being introduced into a system. Comparison of shift register
and style sensors.
B. Wherever tooling must be shifted to accommodate a unique style before the part can be married
to the tooling. Comparison of style sensors, shift register, and tool position sensors.
C. Wherever Build System (VMS, AVI, or Manually input, etc.) data is downloaded to the tooling
PLC. Comparison of style sensor, Build System, and shift register data.
Page 23 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.6.9 Production Simulation Mode / Dry Cycle Mode (Formerly 20-Hour Run)
The supplier must provide a Production Simulation Mode / Dry Cycle Mode. This mode must simulate all
interlocks, part present sensors, etc., as required, in order to make use of the Production Logic for
Production Simulation. The intent is to have only one program, not a Production Simulation Program and
a Production Program, thus insuring that the Production Logic contains all of the corrections that occurred
during the Production Simulation/Dry Cycle. The Production Simulation Mode / Dry Cycle Mode logic will
remain in the system following launch. This feature is only active while in automatic mode. This
maintained pushbutton light is located on the system maintenance screen and can be enabled via a login
and password (see Secured Feature Login section within this document).
Features must include preventing a station from cycling if any production material is detected or
required external conditions are not met. This mode is utilized to simulate production. Equipment motion
is generated without the associated processes expulsing sealant, adhesive, or handling product. This
mode is useful for verifying process flow, robot dressing, cycle-time validation, and interference zones.
Dry cycle zones shall be groups of processes, exact areas to be defined during process verification, and
documented accordingly. To activate this mode, no part present can be detected within the zone (run-out
mode can be utilized to achieve this state). To deactivate this mode, it is required that all style registers
are clear within the zone (run-out mode can be utilized to achieve this state).
1. This mode cannot be enabled (and will drop automatic mode) if any product is detected within the
system (exceptions: any parts in enabled "hold-back" areas such as rack buffers and cross-
transfers).
2. If a part present switch is detected, the line shall stop and annunciate a "PART PRESENT
DETECTED IN DRY CYCLE MODE" diagnostic message shall be activated and displayed on the
HMI. Manual intervention will be required to clear this fault.
3. Robots will go to buffer racks and material rack stands. These must be empty or in bypass in
order to enable the mode.
4. The interaction with AVI must be deactivated in this mode (block build logic enabled).
5. Horizontal conveyors shall cycle with the unloading process.
6. While this mode is enabled, an indicator "DRY CYCLE MODE ENABLED" shall be displayed in
the left hand upper corner on all HMI screens (see example below).
7. The dry cycle mode logic shall not be removed from the code and available for usage at all times.
For detailed specifications, HMI screens and button functionality contact an Chrysler Group LLC Controls
Design Coordinator.
Two methods of dry cycle are available for palletized transfer processes:
"Dry Cycle Without Pallets" will cycle the processes without the presence of a pallet. Process flow
shall always be forward.
"Dry Cycle With Pallets" shall process pallet(s) to the end of the dry cycle zone. Once the zone is
blocked downstream, the process shall reverse the pallet(s) to the zone beginning and restart the
process. The pallet quantity must be identified in the pallet selection prior to selecting this option.
Page 24 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
These features are only active while in automatic mode. This maintained pushbutton light is located on
the system maintenance screen and can be enabled via a login and password.
4.7 Enclosures
Note: Where calculations indicate that enclosure conditions require the use of active cooling (air
conditioning) the panel lighting transformer must be sized to support the additional load. Individually
protected branch circuits, must be provided as required.
Page 25 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.7.7 I/O Rack Mounting
Each I/O rack must be installed in accordance to the manufacturers recommendation in a suitable
enclosure (NEMA-12 minimum).
A. Permanent identification utilizing an approved tag, mechanically attached to the front of the
enclosure.
B. Each tag must indicate the tool number/unit number, WD number, station and/or operation
number, description as noted in the wiring diagram (WD), and rack/chassis numbers (if
applicable).
Note: For an example of approved tag format contact a Chrysler Group LLC AME Controls Design
Coordinator (reference WD_TAGS).
D.A. Be UL listed and installed in accordance to the latest release of the National Electrical
Code.
Page 26 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.7.13
- Stamping Exclusion
Lexan window 1/4" thick in the door of the I/O enclosure to allow observation of I/O racks and
power supply is NOT required in the door of the I/O enclosure used in Stamping Plants.
Note: Where calculations indicate that enclosure conditions require the use of active cooling (air
conditioning) the panel lighting transformer must be sized to support the additional load. Individually
protected, branch circuit must be provided as required.
4.7.21
Page 27 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
Provide 480 volt power distribution boxes, sized to Article 312 (Table 312.6(B)) of the latest release of the
National Electrical Code for Top Entry ONLY, for all weld control panels with line connectors sized to
accept plant feeder cables. Plant feeder cables are to be sized for the thermal equivalent ampacity of the
weld control panel using a 50% duty cycle in the calculation multiplied by the number of load side
connections.
Each power distribution box must have load side connectors sized to support properly sized cables from
the distribution box to the weld controller. A maximum of three (3) AC or four (4) DC weld control panels
per power distribution box will be allowed.
4.7.27
Page 28 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
operation of the Power Distribution Panel disconnect. For operation description and panel drawings
contact a Chrysler Group LLC Controls Design Coordinator.
4.8
4.9
4.10
4.11.5
Page 29 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.11.6
4.11.10
4.11.11
4.11.13
Page 30 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
Programming support equipment must be provided for every system, (an authorized Chrysler Group LLC
representative will define the total quantity requirement for an entire program).
All programmable equipment, supplied by the equipment supplier, shall have the ability of being
connected to and backed up from a Programming Work Station (PWS).
Part numbers, insert drawings and software versions will be as specified for the program, contact the
assigned Chrysler Group LLC AME Controls Design Coordinator for information.
A Zone is defined as a physical and logical delineation of control scope. It may be identified by perimeter
barrier devices and / or presence sensing safety devices, placed such that no personal and or automation
can enter / exit without being sensed, in conjunction with other physical and logical process
requirements. Multiple zones can reside within a WD.
A System is defined as the start and finish of a defined process (i.e. S01 Elevator Lowered to S12
Elevator Raised). Multiple WD’s can reside within a system.
The assigned Chrysler Group LLC Control Design Coordinator and Launch Technician shall be
responsible for defining the various Zone(s) of Control, with the OEM, during Wiring Diagram assignment
activities. The resultant of these activities shall be outlined in detail within the Controls Process Review
document(s).
When the zone is enabled, all incoming product sources (material racks, conveyors, buffer racks,
etc.) shall be inhibited from bringing in new parts once the requirements are fulfilled for all existing
products within the zone (for instances where part mating is required).
This mode will utilize "hold-back" areas unless they are enabled.
When enabled, each station in the system that has a part will complete one full cycle (achieves
cycle complete).
If only one part is in a zone, that part will only cycle once and will not continue cycling through
each station. The purpose of this mode is to cycle each part completely, not each station.
The control for single cycle will be at the HMIs within the zone. Cycle hold PBs will not activate
nor deactivate single cycle, but will take priority over single cycle.
Single cycle will not exist for overhead systems or cross transfers.
Clamp and hold shall not apply to idle stations, cross transfers or any pallet return lines.
Clamp and hold shall inhibit all robots, with the exception of material handling robots, from
receiving a new style.
Clamp and hold shall hold all material handling docking robots at the docked position.
Page 32 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
Robotic Material Handling
This mode is utilized to verify the robot material handling device(s) interaction with the product. Every
material handling robot shall have a robot clamp and hold feature. This button initiates robot clamp and
hold. This maintained pushbutton light resides on the robot status HMI screen.
Page 33 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
status screen, the specific robot must be identified via the "Robot Selection" prior to initiating this feature.
These indicators are available for each robot and reside on the robot status and system maintenance HMI
screens.
[Flashing] When at least one auto zone is able to achieve automatic mode
[Solid] When all auto zones achieve automatic mode
[Not Flashing nor Solid] Auto zones are unable to achieve automatic mode
Page 35 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
The re-pick option is available for the following processes:
Horizontal conveyors
Fixtures
Hand-off nests
Qualifying stands
Shuttles
Transfer pallets/carriers
CMM carts/turn tables
Remove The Product/Style
The technician can physically remove the product (deactivating the part present switches) and then
manually clear the style from the shift register edit screen.
Each single cycle zone can be deactivated individually, releasing product to the process.
If all single cycle zones for that affected quality hold area are off, this mode shall be deactivated.
Cycle hold will complete all current motions, then hold, allowing entry into the cell.
Examples of activities that will be affected by cycle hold are, but not limited to:
• Robot program calls will be inhibited if not yet initiated.
• Robots will not continue from pounce.
• Material handling robots will not go to pick-up, exit pick-up, go to drop-off and exit drop-off.
• Weld processes shall complete.
• Sealer/adhesive apply applications shall complete.
• Versa products will complete current motion.
• Tooling will complete current sequence (whether sequence in or sequence out), then stop.
Cycle hold will not affect each motion independently.
The control for cycle hold will come from the existing PBLTs on the pendant boxes and from the
HMI PB on the overview screen.
Cycle hold will take precedence to single cycle and inhibit the system when able.
Cycle hold will exist for overhead systems and cross transfers.
Versa product motion of the first two upstream stations and the first downstream station of the
adjacent auto zones must be held and/or completed prior to cycle being held. This is requested
so potential motion will not be interrupted.
Page 36 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.13.15 Secured Feature Login / Logout
Several features within this document require secured access. To validate feature activation by an
approved representative, it is possible to disable features until authorization is permitted. Specific login
names and passwords can grant different access to features. The secured area login prompt is activated
by selecting the "Log In" go to button.
Every screen that requires secured access shall have a "Log In" go to button. When selected, an
onscreen keyboard will be displayed for user input. Additionally, a five minute login active timer shall be
enabled. Every screen that requires secured access shall have a "Log Out" go to button. The user group
is displayed in the indicator above the button. When selected, or if the login active timer is done, the
secured feature selection device6s shall be disabled.
Accept
This option can be utilized to exit the "pick override inspection" position and to re-establish the main
process. Once selected, the material handling devices will extend and the robot shall move to the "go to
drop" position. This feature can only be activated while the machine is in automatic mode and the robot is
at the "pick override inspection" position. This momentary pushbutton light resides on the robot status
HMI screen. Additionally, the specific robot must be identified via the "Robot Selection" prior to initiating
this feature
Reject
This option can be selected at anytime once the robot has acquired a part. This option is also utilized to
exit the "pick override inspection" position and cancel the "Abort Drop" feature. When this mode is
enabled, the robot will move to a pre-determined drop position where the suspect product will be
disposed of (floor, hook, etc.). Additionally, the robot shift register data will be automatically cleared, the
robot will verify all end effector part presents are off and return to the home position. In cases where the
reject was selected while an abort drop is active on the second drop, special automatic means may be
necessary to dispose of the first part that was dropped off. This feature can only be activated while the
machine is in automatic mode. This momentary pushbutton light resides on the robot status HMI screen.
Additionally, the specific robot must be identified via the "Robot Selection" prior to initiating this feature
Page 37 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.13.17 Abort Drop-Off
This feature is utilized in instances where the receiving process has an active part present or clamp fault
and product removal is advantageous to the recovery process. This feature can only be activated while
the machine is in automatic mode. This momentary pushbutton light resides on the robot status HMI
screen. Additionally, the specific robot must be identified via the "Robot selection" prior to initiating this
feature.
When this feature is enabled:
Receiving Processes Without Clamps
The robot shall move to the "wait to drop" position with the product.
Receiving Processes With Clamps
If the receiving process part presents are not activated, the robot shall move to the "wait to drop"
position with the product.
If the receiving process clamps fault while extending, the process clamps shall retract, the robot
material handling devices shall extend and then the robot shall move to the "wait to drop" position
with the product.
Receiving Processes Gravity Drop (Qualifying Stand)
The robot shall re-acquire the product and move to the "wait to drop" position. For stations that have weld
robots at the pounce position, the robots will be commanded to return home from pounce.
Double drop operations (abort second drop off)
This procedure is required for material handling applications that drop off multiple components. If the
robot is having difficulty with the second part drop off and abort drop was selected, the robot shall move
to the "wait for drop 2" position.
Abort Drop – Deactivation
When the abort drop is active and the robot has returned to the "wait to drop" position, the technician can
select one of the following methods to cancel the feature.
Selecting Reject
This option can be selected at anytime once the robot has acquired a part. This option is also utilized to
exit the "pick override inspection" position and cancel the "Abort Drop" feature. When this mode is
enabled, the robot will move to a pre-determined drop position where the suspect product will be
disposed of (floor, hook, etc.). Additionally, the robot shift register data will be automatically cleared, the
robot will verify all end effector part presents are off and return to the home position. In cases where the
reject was selected while an abort drop is active on the second drop, special automatic means may be
necessary to dispose of the first part that was dropped off. This feature can only be activated while the
machine is in automatic mode. This momentary pushbutton light resides on the robot status HMI screen.
Additionally, the specific robot must be identified via the "Robot Selection" prior to initiating this feature
Selecting Re-Drop
This feature is utilized to re-establish the drop process. When selected, it shall cancel the "Abort Drop"
feature and initiate the "go to drop" program. This feature can only be activated while the machine is in
automatic mode. This momentary pushbutton resides on the robot status HMI screen. Additionally, the
specific robot must be identified via the "Robot Selection" prior to initiating this feature
Page 38 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
4.14 Early Equipment Management (EEM)
All gage faces shall have markings to indicate the proper operating set point and range. Gage
indication should be clearly visible verification of proper operating settings without having to read
the numbers on the gage face scale. Additionally, alternative means that allow for accurate
operating pressure to be displayed on an HMI, or acceptable display, the gage shall be omitted
from the designs.
All systems’ operating pressure range(s) are clearly identified on the sight gage glass. Each sight
glass shall include a color coded, semi-transparent label applied to outer surface of the gage
glass indicating correct, min/max (green) and incorrect, min/max (red) operating pressuresAll
digital displays are accompanied with labels mounted adjacent to the digital read out, indicating
correct and incorrect operating ranges.
All rotation and flow direction decals are installed where applicable.
All flow meters are installed where applicable.
All hydraulic system filters shall have an indicator to show when the filter element requires
replacement. Indicators should be visible from outside the cell. If possible, the equipment should
be designed for filter replacement while the equipment is running.
All systems have the ability to monitor and adjust key process parameters from outside the cell
(e.g. press tonnage, weld gun current, etc.) while the equipment continues to run.
All equipment operating controls are clearly marked with the function of operation and are
permanently tagged and identified.
Thermal - or other PdM indicators (where practical) are incorporated into equipment design (e.g.:
temperature sensitive labels on all critical components, tonnage monitoring, secondary current
modeling, vibration monitoring).
All equipment requiring air filters include a filter map and all openings shall be labeled with "air in
– do not restrict" and "air out – do not restrict" at the appropriate location, filter type including
NPM#, size, frequency of filter cleaning/change required, and a location to document date of last
filter change. All exhaust ports shall include air flow indicators or streamers to validate air flow
and all filters locations shall be easily accessible. External filters shall be installed on all external
motors.
Exploded assembly diagrams are provided and that they list all parts and detailed part numbers
on the equipment (not just recommended spare parts). Part numbers shall be stamped and
clearly identifiable on all parts. A "Bill of Material" with Chrysler NPM part numbers where
possible shall also be included.
Page 39 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx
Spare parts lists include NPM codes compiled and readily available in accordance with the TMS
procedure. All recommended spare parts shall be locally available within North America.
All equipment is designed for quick program and machine cycle recovery.
All work instructions for start-up, shut down and fault recovery shall be documented and shipped
with the equipment. Include visual diagrams attached to the equipment. These work instructions
shall be part of the Training Deliverables.
All warning lights are properly labeled and in clear view of operator/operator station.
All shutoffs and controls are mounted outside the work cell in an easily accessible and
ergonomically compliant manner (e.g. solenoids, shutoff valves, motor controls, etc.).
All Automation can be easily put into manual mode of operation.
All Shutoffs block and discharge stored energy, have an internal bleed system. Lockouts shall
isolate material within the piping system.
Alarms are present (sound, lights, messages, pagers, etc.) for monitoring unsafe/dangerous
conditions, faults, running outside of process limits, equipment conditions, or other plant-
designated conditions.
Shutoffs and controls are "easy on and easy off", wherever possible, to enable "weekend" energy
savings.
Centralized access or display for diagnostic information (e.g. weld controllers).
Maintenance time-saving devices are used on the equipment where applicable (example: quick
disconnects, easily removable guards).
When using a hinged guard that is protecting from hazardous motion, it shall be electrically
interlocked and include captive fasteners.
All automatic operations be provided with guarding in accordance with SMI-145. All hinged,
sliding, or lift off guards that enclose hazardous motion and require routine (daily) access to the
industrial machinery shall be electrically interlocked. Automatic operations shall not operate
unless the interlocked guard is closed.
REVISION HISTORY
Revision
Date Number* NAME Description (include pages affected)
1-2-2013 13.01 M. Wesley 4.4.23 End of Travel Limit Switch for Bridge, Rail, Trolley and
Carrier Switch Actuation Method
Page 40 of 40
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 4 Electrical 1-31-2013.docx