WI-NG-6460-002-022 Work Instruction-NER Rev00
WI-NG-6460-002-022 Work Instruction-NER Rev00
Concurred By:
-----
Approved By:
1.0 INTRODUCTION
Proper commissioning and testing of new NER is an important issue to prove that
NER has been properly shipped and correctly erected and installed. This work
instruction highlights the necessary steps related to proper commissioning of NER in
HV and EHV substations.
All NERs must be tested in the factory before delivery to the site and must be tested
by commissioning contractor at site after installation for processing to begin in the on-
site Commissioning and testing phase. Commissioning tests at site is done to prove
that:
Index Number:
WI-NG-6460-002-022
Neutral Earthing Resistor Commissioning Page Number:
2 of 5
2.0 RESPONSIBLITIES
- Any one working in testing location during commission stage must follow the safety
requirements as per SEC rules and CSD employees are responsible for applying
safety rules in all places which they working in.
- Project site engineer is responsible for committing the contractor to prepare testing
and commissioning places to be done in proper climate conditions as per Company
policies, procedures and accepted temperatures the relays, devices and test
equipment can be tested or operated within it.
- All CSD staff are responsible for testing activities according to approved
specification and design
- CSD engineer/technician shall not start any test for NER until providing the following
and the Testing Contractor engineer is responsible for all providing:
- Its responsibility of the CSD Engineer/Technician to check and witness all activities
required for NERs following all of this work instruction.
- CSD Engineer/Technician is responsible for recording status of any test for NERs in
its check list and test form as per the following work instruction.
Index Number:
WI-NG-6460-002-022
Neutral Earthing Resistor Commissioning Page Number:
3 of 5
Reference/
Item Description
Criteria Limit
1. Visual inspection for any insulator broken.
Check nameplate and data. 57-TMSS-01,
2.
4.3.5
Check the value of resistance and current ratings against the
3.
specifications.
Check that the earthing with solderless connectors and suitable for 57-TMSS-01,
termination of copper conductor of size 240 mm2 for 40 kA and below. 4.3.1
4. Check the grounding resistance of the enclosure earth terminal and
resistor earth terminal. Confirm the continuity and tightness of the Bolt &
Nut.
Check the resistor rated for 5 Seconds unless specified in data 57-TMSS-01,
5.
schedule. 4.3.4
6. Test associated NCT & power cable.
Main circuits Resistance measurement test at ambient temperature. The 57-TMSS-01,
7. resistor provided in the NER panel/box shall be measured (after 5.2
disconnecting the leads) and it should match with the name plate.
8. Perform Insulation resistance test at 5kV DC >1000 MΩ
9. Cleaning of all internal as well as external to NER before energization.
Check that the enclosure earth terminal and resistor earth terminal are
10.
separate to allow the possibility of disconnection during testing.
Index Number:
WI-NG-6460-002-022
Neutral Earthing Resistor Commissioning Page Number:
4 of 5
4.0 REFERENCES
Index Number /
Title
Reference Number
PR-NG-6460-002 Project Commissioning Procedure
57-TMSS-01 TMSS for Resistor
Index Number:
WI-NG-6460-002-022
Neutral Earthing Resistor Commissioning Page Number:
5 of 5
This document shall comply in accordance with the existing Company’s Rules and Regulations.
Any modifications therein found not conformance with the document shall be declared invalid.
For clarification and verification on this document, contact the following: