Professional Documents
Culture Documents
Cost 8,000 Equipment Cost 8,000 × RM 5.42 1 Equipment Cost RM 43,360 Purchase Cost RM 43,360 × Purchase Cost RM 130,513.60
Cost 8,000 Equipment Cost 8,000 × RM 5.42 1 Equipment Cost RM 43,360 Purchase Cost RM 43,360 × Purchase Cost RM 130,513.60
1 Equipment cost
All equipment that are involved for production of Methanol are considered to be further
analysed as equipment costing is one of the most crucial investment needed to b calculated.
Thus, the evaluation for profit and payback rate can be performed in the future. The
calculation of equipment cost is based on R.K. Sinott, 2005 and A.M. Gerrard, 2007.
a) Pump
Assume the power of centrifugal pump used is 5 kW, as there are no exact estimations done
for pump. Price of centrifugal pump can be obtained by referring to curve cost of large
centrifugal pump [ CITATION Ger07 \l 17417 ].
Cost =£ 8,000
RM 5.42
Equipment Cost =£ 8,000 ×
£1
b) Heat Exchanger
The cost for heat exchanger will be obtained by using the Heat Transfer Surface
Area of each Heat Exchanger unit. Cost curves as shown in Figure 1 will be used in cost
determination. Cost of each unit will be determined based materials used as shown in
Figure 3 [ CITATION Sin051 \l 17417 ].
E-101
By referring to Figure 1, the cost of E-101 in year of 2004 is $300,000. This value is
obtained by referring to fourth curve as material used for both shell and tube is stainless
steel. The cost of equipment obtained is $300,000, which is equivalent to RM 1,239,000. By
using cost of inflation index of year 2004 and 2020, the cost of heat exchanger in 2020 is RM
3,300,345.13. The inflation index is as shown in Figure 2.
RM 4.13
$ 300,000× =RM 1,239,000
$1
301
Price=RM 1,239,000 ×
113
Price=RM 3,300,345.13
Figure 1: Shell and Tube Heat Exchanger cost in 2004[ CITATION Sin051 \l 17417 ].
Figure 3: Consideration Factors in Shell and Tube Heat Exchanger[ CITATION Sin051 \l 17417 ].
¿ RM 3,085,822.70
E-102
RM 4.13
$ 120,000× =RM 495,600
$1
301
Price=RM 495,600×
113
Price=RM 1,320,138.05
¿ RM 1,122,117.35
E-106
RM 4.13
$ 100,000× =RM 413,000
$1
301
Price=RM 413,000×
113
Price=RM 1,100,115.04
¿ RM 935,097.79
c) Compressor, C-101
kJ
Q=194025.339
min
kJ 0.01667 kW
Q=194025.339 ×
min 1 kJ /min
Q=3234.4024 kW
The cost for compressor, C-101, can be determined by referring to Figure
7.19[ CITATION Ger07 \l 17417 ]. The cost obtained for the equipment is £1,900,000, which
equivalent to RM 10,298,000. This price was then employed with cost inflation index as
obtained equipment cost is based on January 2000.
RM 5.42
Equipment Cost =£ 1,900,000×
£1
d) Reformer
For calculating the cost of reformer, Figure 7.4 from A.M. Gerrard are seen to be unsuitable
to be used to estimate price of reformer. The curve required reformer’s diameter be used but
diameter of 4.12 m located out of curve provided. Hence, Equation 1 will be used to
calculate cost based on value from Figure provided below, where volume of reformer tank
will be used as reference.
Ce=CSn
Ce=CSn
Ce=£ 40,685.27
RM 5.42
£ 40,685.27 × =RM 220,514.16
£1
Cost Index 2020
Price=Price 2004 ×
Cost Index 2004
301
Price=RM 220,514.16 ×
113
Price=RM 587,387.28
e) Reactor
For calculating the cost of reactor, Figure 7.4 from A.M. Gerrard are seen to be unsuitable to
be used to estimate price of reactor. The curve required reactor’s diameter be used but
diameter of 4.95m located out of curve provided. Hence, Equation 1 will be used to calculate
cost based on value from Figure provided below, where volume of reactor tank will be used
as reference.
Ce=CSn
Ce=CSn
Ce=£ 47,102.46
RM 5.42
£ 47,102.46 × =RM 255,295.33
£1
301
Price=RM 255,295.33 ×
113
Price=RM 680,034.46
f) Condenser
E-103
RM 4.13
$ 38,000× =RM 156,940
$1
301
Price=RM 156,940 ×
113
Price=RM 418,043.72
¿ RM 390,870.88
E-104
RM 4.13
$ 150,000× =RM 619,500
$1
Cost Index 2020
Price=Price 2004 ×
Cost Index 2004
301
Price=RM 619,500 ×
113
Price=RM 1,650,172.57
¿ RM 1,542,911.35
g) Distillation Column
Determining the cost of distillation column will require two parts of calculation, which is the
vessel cost and column cost. Vessel cost will be determined by using length or height of
vessel (7.0 m) and diameter of vessel (3.07 m). The value for vessel cost can be determined
by referring to curve below using fourth curve as diameter is 3.0 m.
Cost =£ 20,000
RM 5.42
Equipment Cost =£ 20,000×
£1
301
Price=RM 108,400 ×
113
Price=RM 288,746.90
¿ RM 635,243.18
As for column cost, Figure 7.12 from A.M. Gerrard (2007) will be referred as sieve tray will
be used for distillation column. Cost of £20,000 was obtained at diameter of 3.0 m, and will
be multiplied with 1.35 for stainless steel and 0.6 power law for plates exceeding 10.
Cost =£ 20,000
RM 5.42
Equipment Cost =£ 131,534.77×
£1
301
Price=RM 712,918.48 ×
100
Price=RM 2,145,884.63
h) Storage Tanks
There are three storage tanks, important for the plant, which is the methane tank, inlet water
tank and methanol storage tanks after production. The assumptions for the storage tank
calculation is the storage is a cone roof type and are each 1000 m3 each tank. Figure below
shows the purchase cost for tanks, alongside the cost constant and index for that particular
type of equipment [ CITATION Sin051 \l 17417 ].
Calculation will be done by using the equation below. By referring to the Figure above, the
value of C is $2300, S is 1000 m3 and n is 0.55, and purchased cost (Ce) will be obtained.
Ce=CSn
Ce=£ 62,535.70
RM 5.42
£ 62,535.70 × =RM 338,943.49
£1
301
Price=RM 338,943.49 ×
113
Price=RM 902,849.47
The price obtained for storage tank is RM 902,849.47 each. However, the price should be
multiplied by 2 as the material used for storage tank is stainless steel.
Price=RM 902,849.47× 2
Price=RM 1,805,698.94
8.1.2 Purchase Cost Estimation (PCE)
PPC=PCE (1+ f 1+ f 2 + f 3+ f 4 + f 5 + f 6 +f 7+ f 8 + f 9 )
Process Type
Item
Fluid
Major Equipment, total purchase cost PCE
F1 : Equipment Erection 0.4
F2 : Piping 0.70
F3 : Instrumentation 0.20
F4 : Electrical 0.10
F5 : Buildings, process Not Applicable
F6 : Utilities Not Applicable
F7 : Storages Included in PCE
F8 : Site Development Not Applicable
F9 : Ancillary Buildings Not Applicable
RM 48,583,555.24 (1+0.4+ 0.7+0.2+0.1 ¿
Total Physical Plant Cost (PPC)
=RM 116,600,532.60
FCI=PPC (1+ f 10 +f 11 +f 12 )
Process Type
Item
Fluid
Physical Plant Cost PPC
F10 : Design and Engineering 0.30
F11 : Contractor’s Fee 0.05
F12 : Contingency 0.10
RM 116,600,532.60 (1+0.30+0.05+0.10)
Fixed Capital Cost (FCI)
=RM 169,070,772.30
8.1.5 Working Capital
Working Capital, also known as Working Capital Investment, is 15% out of Fixed
Capital Cost (FCI).
15
Working Capital= × RM 169,070,772.30
100
Total investment is the sum of value of Fixed Capital cost and Working Capital. The purpose
of estimating this value is to assess the profitability for the production of Methanol.
a) Raw Materials
The raw materials that will be used for the plant is Methane and water. Calculation of
catalyst used (ZnO) in Reformer, RF-101 will also be included.
Methane, CH4
RM 0.25
Methane=
kg
Water, H2O
Values
>227m3 RM 0.84/m3
mol g 1 kg
Water used=21851.742 × 18.015 ×
min mol 1000 g
kg 60 min 24 hr 30 days
Water used=393.659 × × ×
min 1 hr 1day 1 month
kg 1m 3
Water used=17,006,068.8 ×
month 1000 kg
m3
Water used=17,006.0688
month
Industrial Water Rates Water Used (m3) Rate Calculated
RM 0.92
3 3
×227 m 3
0-227 m = RM 0.92/m 0-227 m 3
=RM 208.84
RM 0.84
×16779.0688 m3
>227m3 = RM 0.84/m3 227-17,006.0688 m 3
=RM 14,094.42
Total Rate per month RM 14,303.26
RM 14,303.26 12 months
Rate per year= ×
month 1 year
Catalyst, ZnO
RM 238.301
Final Price of Catalyst = × 24,510.3309 kg
0.5 kg
RM 11,681,672.73
Final Price of Catalyst =
10 years
b) Utilities
Miscellaneous Cost
Miscellaneous = 10% of maintenance cost
10
× RM 8,453,538.61=RM 845,353.86
100
8.2.2 Fixed Cost
RM 68 k
Manning Estimates (RM68k per ×150
b) Operating labour year . person
year per person X 150 employees)
= RM 10,200,000.00
20
× RM 10,200,000
c) Supervision 20% of Operating Labour (b) 100
= RM 2,040,000.00
50
× RM 10,200,000
d) Plant Overheads 50% of Operating Labour (b) 100
= RM 5,100,000.00
15
× RM 169,070,772.24
e) Capital Charges 15% of Fixed Capital Cost 100
= RM 25,360,615.84
1
× RM 169,070,772.24
f) Insurances 1% of Fixed Capital Cost 100
= RM 1,690,707.72
2
× RM 169,070,772.24
g) Rates 2% of Fixed Capital Cost 100
= RM 3,381,415.44
1
× RM 169,070,772.24
h) Royalties 1% of Fixed Capital Cost 100
= RM 1,690,707.72
30
× RM 85,823,523.82
i) Sales Expenses 30% of Direct Production Cost 100
RM 25,747,057.15
20
j) General × RM 85,823,523.82
20% of Direct Production Cost 100
Overheads
RM 17,164,704.76
25
k) Research and × RM 85,823,523.82
25% of Direct Production Cost 100
Development
RM 21,455,880.95
Utilities RM 6,009,300.00
Maintenance RM 8,453,538.61
Supervision RM 2,040,000.00
Rates RM 3,381,415.44
Insurance RM 1,690,707.72
Design Cost
Year 1: RM 17,498,824.93
9% of Total Investment
Construction Cost
Year 2 : RM 77,772,555.23
40% of Total Investment
Construction Cost + Working Capital
Year 3 : RM 99,160,007.92
51% of Total Investment
Table 3.1: Explanations of project cash-flow diagram ([ CITATION Sin051 \l 17417 ].
Point Explanation / Details
A-B Point represent the investment required to design the plant.
Timeline showing the heavy flow of capital to start building the plant and
B-C
providing funds for start-up phase.
The curve can be seen to rises at this point, as product was produced,
and income will be obtained from sales. At this timeline, the cumulative
C-D
net cash flow can be seen to remain negative until investments were paid-
off (Point D), while net cash flow is positive.
This timeline is called as ‘payback time’, which represents the time to
A-D reach ‘break-even point’. Curve shows that, it took four years to start
gaining return and paying off investments.
This point is known as ‘break-even point’. It can be used to quantify the
D percentage of plant capacity at which the income of the plant equals to the
production cost.
Regions shows positive numbers for cumulative cash flow, indicating a
D-E
return from the investment.
Due to the increment in operating costs and falling sale in terms of volume
E-F
and price, cash flow tends to fall off, and slope of curves will change.
Point indicate the final cumulative net cash flow by the end of the project
F
life.
CASH IN
Current Methanol Price = $210/MT [Asia Pacific price, Valid till 30th Nov 2020]
Current Methanol Price = RM 1.28/kg
Sales Price = RM 1.50/kg
For the first three years, no sales income counted as plant is in phase of start-up. Due to
reducing the payback time, sales price will be increased to RM 2.50/kg for year 4, and RM
3.10/kg for year 5. The price used will back to RM 2.50/kg for the proceeding years.
Year 4 and Year 6 onwards = RM 2.50/kg x 175,000,000 kg/year = RM 437,500,000
Year 5 = RM 3.10/kg x 175,000,000 kg/year = RM 542,500,000
Year 9 (less production due to major maintenance) = RM 2.50/kg X 125,000,000
kg/year =RM 312,500,000
Total Investment = RM 194,431,388.07
Interest is 10% of Total Investment and will stay the same throughout the years.
10
× RM 194,431,388.07=RM 19,443,138.81
100
CASH OUT
Investment :
Year 1 = RM 17,498,824.93
Year 2 = RM 77,772,555.23
Year 3 = RM 99,160,007.92
Raw Materials :
Methane = RM 19,712,078.23
Water = RM 171,639.12
Catalyst = RM 1,168,167.27
Total Raw Materials = RM 21,051,884.62
Fixed Cost = Sub Total B = RM 57,916,985.34
Variable Cost = Sub Total A = RM 27,906,538.48
Year 1 2 3 4 5 6 7 8 9
CASH IN (RM)
Sale Income - - - 4.38E+08 5.43E+08 4.38E+08 4.38E+08 4.38E+08 3.13E+08
Interest (10%
of Total 1.94E+07 1.94E+07 1.94E+07 1.94E+07 1.94E+07 1.94E+07 1.94E+07 1.94E+07 1.94E+07
Investment)
Total IN 1.94E+07 1.94E+07 1.94E+07 4.57E+08 5.62E+08 4.57E+08 4.57E+08 4.57E+08 3.32E+08
CASH OUT (RM)
Investment 1.75E+07 7.78E+07 9.92E+07 - - - - - -
Raw Materials 2.11E+07 2.11E+07 2.11E+07 2.11E+07 2.11E+07 2.11E+07 2.11E+07 2.11E+07 2.11E+07
Fixed Cost 5.79E+07 5.79E+07 5.79E+07 5.79E+07 5.79E+07 5.79E+07 5.79E+07 5.79E+07 5.79E+07
Variable Cost 2.79E+07 2.79E+07 2.79E+07 2.79E+07 2.79E+07 2.79E+07 2.79E+07 2.79E+07 2.79E+07
Total OUT 1.24E+08 1.85E+08 2.06E+08 1.07E+08 1.07E+08 1.07E+08 1.07E+08 1.07E+08 1.07E+08
Net Cash
-1.05E+08 -1.65E+08 -1.87E+08 3.50E+08 4.55E+08 3.50E+08 3.50E+08 3.50E+08 2.25E+08
Flow
Cumulative
-1.05E+08 -2.70E+08 -4.57E+08 -1.07E+08 3.48E+08 6.98E+08 1.05E+09 1.40E+09 1.62E+09
Cash
8.3.2 Net Present Worth (NPW)
The net cash flow in each year of the project was brought upon its “present worth” at the
start of the project by discounting the value at some chosen compound interest rate.
Where;
10 %
r= =0.1
100 %
RM 3.48× 108
NPW 5= 5
(1+ 0.1)
The value of NPW is much smaller compared to NFW, and reflect that time value of
money and the earnings pattern over project life [ CITATION Sin051 \l 17417 ]. If the money
were invested, the figures obtained will be roughly equivalent to the current interest rate that
could be earned from the project.
8.3.3 Payback Period
Payback period, defined as the time required to pay off the initial investment form
income, after the start of the project. This is an important criteria in judging the
improvements of the projects on operating plants. Typical payback time is 2 to 5 years,
depending on the projects [ CITATION Sin051 \l 17417 ].
8.3.4 Return of Investment (ROI/ROR)
Rate of Return (ROR), defined as the ratio of annual profit to investment. It is a simple index
to show the performance of the invested money. The calculation to base the ROR is based
on the average income over life of project and the original investment invested [ CITATION
Sin051 \l 17417 ].
F−C
ROR= ×100 %
C ×G
Where;
ROR=50.50 %