Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 18

s

Project Name: R12-T07B11-BDOM Contract


( Temporary Utilities – SWRO Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

METHOD OF

STATEMENT

FOR

FORMWORK
s

Project Name: R12-T07B11-BDOM Contract


( Temporary Utilities – SWRO Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

Prepared Checked Approved


Rev. Date Purpose of Issue
By By By

0 12-09-2020 Issued for Approval Karim Abhinav Ammar


Hisham Jai Smaili
1 28-10-2020 Issued for Approval Karim Abhinav Ammar
Hisham Jai Smaili

Contents

1. Project Introduction:...........................................................................................................................3
2. Project Scope:......................................................................................................................................3
3. MOS Purpose:......................................................................................................................................3
4. MOS Scope:.........................................................................................................................................3
5. Definition :...........................................................................................................................................3
6. Responsibilities:...................................................................................................................................4
7. Resources:...........................................................................................................................................4
1. Equipment and Tools.......................................................................................................................4
2. Manpower.......................................................................................................................................5
3. Work Procedure:.............................................................................................................................5
8. Health & Safety Management Plan:.................................................................................................6
9. Work Schedule:................................................................................................................................7
10. Job Safe Practice Analysis :..........................................................................................................7
s

Project Name: R12-T07B11-BDOM Contract


( Temporary Utilities – SWRO Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

1. Project Introduction:

The Red Sea development is a mega project along the Red Sea in the West of the Kingdom of Saudi Arabia
(The Red Sea Project). The strategic objective of the Project is to transform Umluj and Al Wajh regions into a
unique luxury tourist destination with a focus on the ecology and wellness for local and international visitors.

Metito Saudi limited has been awarded by the Red Sea development company to design, manufacture, supply,
construction, erection, testing and commission of 12,500 m3/d SWRO desalination plant comprising

of Seawater Intake, Media Filter, Seawater Reverse Osmosis and Brine disposal.

Metito Saudi Limited will maintain overall responsibility for the logistic plan throughout the construction and
erection phase of the plant.

2. Project Scope:

Project Scope of work is based on EPC contract to execute desalination plant of capacity 12,500 M3/day that
shall be executed in two phases likewise 1st phase - 3,000 M 3/d and 2nd phase - 12,500 M3/d.

Metito Scope of work included detailed civil construction & erection, engineering, manufacture, inspection,
supply installation, testing & commissioning, start up and performance test and will be responsible for design
& execution of electromechanical scope of work to deliver final product water output of 12,500 M 3/d.

3. MOS Purpose:

The purpose of this document is to lay down the systematic procedures for the various activities required for
FORM WORKS to ensure that all works are carried out in accordance with the approved shop drawings and
contract specification. Works shall be carried out in compliance with the drawings, project specifications,
and materials without injuries.

4. MOS Scope:

This Work Method Statement refer to various work procedures contained within project control documents ,
which explains and cover the installation of formwork.

5. Definition :

 PC Project Coordinator
 CM Construction Manager
 MS Method Statement
s

Project Name: R12-T07B11-BDOM Contract


( Temporary Utilities – SWRO Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

 FM Checklist / Form
 RA Risk Assessment
 ITR Inspection & Testing Request
 QCP Quality Control Procedure
 ITL Independent Testing Laboratory
 QA / QC Quality Assurance / Quality Control
 HSE Health & Safety Engineer
 BS British Standard
 ASTM American Society for Testing and Materials
 PTW Permit to Work

6. Responsibilities:

 Project Manager is responsible for overall project execution, quality and safety. Adopt a leading role
with respect to Contractor’s quality and safety procedures. The PM is responsible for the overall
implementation of this method statement. The Project Manager shall ensure that the key personnel
are well aware of the specifications and method statement.
 Safety Engineer shall be responsible for safe working environment & conditions. Coordinate with
Site Engineer to identify potential hazards before works and advice methods of safe working from
new developments.
 Surveyor shall be responsible for setting out for levels, layout, and lines & establish top levels.
Ensuring setting out books are properly maintained and filed when completed. To coordinate with
the CONSULTANT surveyor in determining coordinates, levels, and limits.
 QA/QC Engineer shall be responsible for ensuring that execution of works are complying with
approved method statement; specifications, approved shop drawings.
 Site Engineer shall ensure that all works are carried out according to approved shop drawings. He
shall direct the surveyor for the setting out lines & levels in concurrence from the Construction
Manager/Senior Civil Engineer.
 MEP Coordinator / Engineer shall be responsible for proper execution of MEP works involved
before, during and after the works.

7. Resources:

1. Equipment and Tools

The following equipment will be required for the execution of the Excavation works, whereby the number of
equipment required will be determined upon progress and upon schedule requirements:
s

Project Name: R12-T07B11-BDOM Contract


( Temporary Utilities – SWRO Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

5.1 Nail gun


5.2 Trowel
5.3 Mason’s Hammer
5.4 Blocking chisel
5.5 Mashing hammer
5.6 Masonry power saw
5.7 Level bar
5.8 Mason’s line
5.9 Steel square
5.10 Brushes
5.11 Shovels
5.12 Powered mortar mixer
5.13 Electrical drills

2. Manpower

 Carpenter
 Foreman
 Site Engineer
 surveyor
 Safety Officers
 Labor

3. Work Procedure:

3.1 All material delivered to site shall be visually inspected for straightness, finish and defects prior to use.
3.2 Setting out shall be done by the surveyor prior to proceeding with formworks.
3.3 Each type of form work for the raft, column, beam and slab shall be erected as per approved shop
drawings.
s

Project Name: R12-T07B11-BDOM Contract


( Temporary Utilities – SWRO Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

3.4 Prior to use formwork and supporting timber shall be checked for damage, surface condition and
warping.
3.5 Material shall be protected as necessary from the elements during transportation and storage.
3.6 Design calculation for slab system shall be performed and submitted to consultant for approval.
3.7 Certified and well trained manpower shall be deployed for all types of formwork erection.
3.8 Inspection shall be done by the supplier / third party prior to proceeding.
3.9 Care shall be taken to ensure that any formwork system is installed and supported correctly when
applied on site conditions may vary. Visual inspection shall be carried out by the construction
manager use for each element to ensure support provided is adequate for actual site condition. Every
leg of scaffolding should be checked for tightness, rigidity and proper bracing both ways.
3.10 Ensure that erected formwork is watertight to avoid any slurry leakage.
3.11 Ensure that sleeves and openings for all the MEP services are provided as per approved shop
drawings.
3.12 Form work shall be checked for the alignment, verticality and leveling prior to proceeding with
concrete pouring.
3.13 Inspection shall be raised for the CONSULTANT inspection and approvals before proceeding to
concrete pouring.
3.14 Striking of form work shall be in accordance with the specification tion of cast in place concrete

8. Health & Safety Management Plan:

Project specific HSE Plan covering all aspects of construction safety, environmental protection and urity
protection has been submitted to the Client for approval. This plan included:

 A dedicated Health and Safety team will be deployed to the site under the supervision of a Health and
Safety Engineer and Safety Officers. The project will be controlled as per the approved health and
Safety plan.
 It is Metito’s policy that every employee shall be provided with a healthy and safe environment in
which to work. To this end, every effort will be made and positive action taken at all times, by all
employees, to ensure healthy and safe working conditions at all company project work site and
facilities.
 The general philosophy is each person on site is responsible for safe working practice
 HSE team shall monitor, guide and train all employees’ to achieve a safe working environment by
implementing work rules to achieve these goals.
 Regular job safety analysis will be done
 Regular awareness programs will be conducted
 Special training programs
 Encourage communication from work force
 Encourage daily reminders by each supervisors
 Weekly surveillance of all rigging equipment and tools, site manpower distribution
s

Project Name: R12-T07B11-BDOM Contract


( Temporary Utilities – SWRO Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

 Fire prevention program, identify hazardous areas, material and storage, establish
 Alarms response teams, regular checks on firefighting equipment, fire watcher’s
 Training and firefighting training.
 Daily tool box meetings for supervisory and non-supervisory work force.

9. Work Schedule:

Figure 6.1 – Schedule of construction works

10. Job Safe Practice Analysis :


s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

 Job/Task Title: Formwork


PPE: (Put all the specific PPE to be used in this task )
Job/Task Title: Fixation of Formwork
Tools and Equipment: (Put all the specific Tools & Equipment to be used in this task )

Job Safe Practices Analysis HAZARDS


IN EACH STEP, WHAT COULD CAUSE CONTROLS REQUIRED TO MINIMIZE / ELIMINATE HAZARD OBSERVATION
STEP LIST ALL STEPS IN PERFORMING INJURY, LOSS, DAMAGE INTERRUPTION,
No. THIS TASK OR POLLUTION?

1.
Pre-task briefing and inspection.
Briefing and Introduction  Lack of communication
 TSTI/TBT
 Wrong information or details are
written in the PTW.
 All crew shall be given safety induction, before
 Other activities may not be cover
with the PTW. mobilizing to site.

 Does not aware of the risks  TSTI/TBT.


involved  A safe work practice shall be identified to reduce the
 Unidentified or incomplete possibilities of accident/incident.
hazards and risk information.  Ensure that all required supporting documents shall be
available as per PTW requirements.
 All the required related documents as identified to be
attached in PTW shall be reviewed and evaluated by issuer
and receiver to ensure that all hazard and risk is identified
and complete.
s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

 Lack of PPE  As a minimum PPE Use; Hard Hat, Safety Boots, Safety
Gloves, Safety Glasses, Cover all, Dust mask, Reflective
vests & Earplug
 If workers are used for compaction, proper foot protection
to be provided.
2.
Site preparation inspection of hand and electrical tools & materials
2.1 Perform physical inventory for all  Insufficient Illumination in the  Good lighting is provided to all workspaces and this is maintained
the tools and equipment to be workplace. on a regular basis. Fluorescent tubes are checked & replaced as
used.  Unorganized or poor storage of required.
materials and tools.  Proper storage and segregation of all tools & materials must be
 Area Congestion observed at all times.
 Poor housekeeping  Storage racks must be properly labeled for easy identification.
 Storage areas must not be congested of materials. Space capacity
must be strictly observed.
 Good housekeeping must always be maintained in storage and
working areas to avoid slip, trip, and fall.
 Access must always be clear and free from any obstruction.
2.2 Selecting the most appropriate  Incompetent assigned personnel.  Personnel must be competent/experienced to select appropriate
tool and equipment for the job.  Struck with a sharp and hard object. tools and equipment.
 Unorganized materials and access in  Closed supervision by the engineer, supervisor or foreman must be
the workplace. observed.
 Ensure that all workers are provided with required mandatory PPEs
such as Helmet, safety goggles, safety shoes.
 Access pathways to be kept clear from any obstruction.
 Any obstructions shall be moved and kept materials away from any
access. Keep work area free from loose tools and materials.
 Designated access shall be free from any obstruction.
2.3 Check and inspect tools condition  Lack of experienced or new workers  Only experienced and competent workers should engage in a job.
prior to use. Look for any signs of assigned to do the task.  Close supervision by the Engineer, Supervisor or Foreman must be
cracks, deformation, and any form  Ergonomic hazard (poor body observed.
of damages. positioning, repetitive movement).  Reposition a work table to eliminate a long/excessive reach and
s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

 Sharp and protruding tools. enable working in neutral postures.


 Establish systems so workers are rotated away from tasks to
minimize the duration of continual exertion, repetitive motions, and
awkward postures. Design a job rotation.
 Use appropriate hand protection to avoid hand and finger injuries.
2.4 Verify tagging for tools and  Struck with a sharp and hard object.  Ensure that all workers are provided with all the required Personal
equipment base from color code  Defective tools and equipment. protective equipment for minimum and general requirements.
matrix.  Close supervision required supervisor and foreman must be present
at the site.
 Ensure all tools are inspected properly and color code shall be
applied.
 Any defective tools found shall be removed from service, and
marked with a defective tag.
3.
Cutting and bending of steel reinforcement bars (Fabrication)
3.1 Check and inspect tools and  Inspection and maintenance not  The machine shall be inspected on a periodic basis and shall also be
equipment condition prior to use. done. visually inspected daily prior to each use.
Look for any signs of cracks,  Improper grounding of  Daily inspection record should be readily available in the fabrication
deformation, and any form of cutting/bending machine. area.
damages.  Damaged electrical cables around the  Ensure proper grounding is provided and an electrical source is
equipment. protected with GFCI.
 Unorganized materials and access.  Call the attention of certified electrician to replace damaged cables
 Area congestion. and ensure that new cable was properly arranged & managed to
prevent tripping from the users.
 Remove unnecessary materials and equipment on the affected
areas.
 Designated access shall be free from any obstruction.
 Designate a location for unloading of materials and to be stored
only on a designated storage area.
 All materials location and storage shall be barricaded and provided
with adequate signage.
3.2 Reinforcement steel shall be  Operator misuse of cutting / bending  Only trained workers on machine use shall be authorized to operate
accurately fabricated to the machine. and maintain the equipment.
s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

dimensions and shapes shown in  Incompetent personnel / Lack of  Workers should understand the purpose and function of all controls
the Contract Documents. training for cutting/bending machine on the machine, should know how to stop the equipment in an
operation. emergency, and should be trained on the safety procedures for
special set-ups.
 Operators must have an ID, certificate, or attendance showing that
he attended training about operating and usage of the machine.
3.3 Cutting and bending shall conform  Working without wearing appropriate  Ensure that all workers are provided with required mandatory PPEs
to cut and bend dimensions as Personal Protective Equipment (PPE). such as Helmet, safety goggles, safety shoes.
defined within the standard using  Operator wearing loose clothing.  Workers shall not be allowed to use loose clothing.
the best appropriate cutting and  Unured or loose machine guarding.  Ensure all guards are fitted, ure, and functional. Do not operate if
bending tool or equipment.  Improper handling of steel rods guards are missing or faulty.
 Sharp and hard edges of the machine.  Use proper lifting methods, including team lifting when necessary.
 Forceful movement, incorrect  Lift with legs, keep loads close to the body, and don’t twist while
posture, repetitive motion. picking uploads.
 High/Low Ambient Temperature.  Use mechanical lifting equipment (hand carts, trucks) to move
large, awkward loads.
 Appropriate hand protection shall be worn properly.
 An adequate supply of cold drinking water provided to the work
area.
 Establish systems so workers are rotated away from tasks to
minimize the duration of continual exertion, repetitive motions, and
awkward postures. Design a job rotation
 Heat and humidity monitoring shall be conducted in frequent time
intervals and results shall be communicated to workers (heat stress
monitoring board or flag system).
 Heat stress procedure shall be developed and implemented.
 Keep supplies of clean cool water within the work area, taking time
to drink at least two glasses of water every hour.
 Take frequent rest breaks in the shade or Air conditioning.

4.
Shifting of fabricated steel materials into the work area
4.1 Plan the lifting of materials from  Poor planning to shift materials to the  Ensure that the ongoing task was discussed or related in daily
s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

the fabrication shop to the site. toolbox meeting based from attached risk assessment.
workplace.  Lack of experienced or new workers  Follow the daily activity plan to ensure that only needed materials
assigned to do the task. will be a shift for the day.
 Only experienced and competent workers should engage in a job.
 Close supervision by the Engineer, Supervisor or Foreman must be
observed.
4.2 Asking co-workers assistance to  Miscommunication regarding the  Workers to discuss all site concerns directly to his foreman or
shift the materials to the site. assigned task. supervisor to avoid miscommunication of workers.
 Workers having conflicting  Supervisor must ensure that workers know their roles and must
roles/multiple assignments. follow their instructions without any conflict from other activities.
 Ensure that all workers attended safety induction to make sure that
they understand their roles and responsibilities.
 Close supervision by the Engineer, Supervisor or Foreman must be
observed.
4.3 Lifting the materials from the  Improper lifting of materials.  Observe proper lifting techniques (get as close to the load as
ground to scaffold structure.  Lifting light to moderate-heavy loads. possible. Try to keep your elbows and arms close to your body.
 Sharp and protruding objects Keep your back straight during the lift by tightening the stomach
 Working without wearing appropriate muscles, bending at the knees, keeping the load close and centered
Personal Protective Equipment (PPE). in front of you, and looking up and ahead).
 Working without full body harness  Use proper lifting methods, including team lifting when necessary.
having shock absorber.  Lift with legs, keep loads close to the body, and don’t twist while
picking uploads.
 Use mechanical lifting equipment (hand carts, trucks) to move
large, awkward loads.
 Ensure that all workers are having full body harness with two
lanyard.
 Appropriate hand protection shall be worn properly.
 Ensure that all workers are provided with required mandatory PPEs
such as Helmet, safety goggles , safety shoes.
4.4 Carrying the materials heading to  Improper manual handling  Observe proper handling techniques (do not twist or turn the body;
the site.  Lifting light to moderate-heavy loads. instead, move your feet to turn. Your hips, shoulders, toes, and
 Sharp objects knees should stay facing the same direction).
 Poor access in the workplace  Use mechanical lifting equipment (hand carts, trucks) to move
s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

 Extreme temperature large, awkward loads.


 Ergonomic hazard (excessive force,  Appropriate hand protection shall be worn properly.
repetitive movement).  Ensure that all workers are provided with required mandatory PPEs
such as Helmet , safety goggles , safety shoes.
 Maintain proper housekeeping and access to work area shall be
kept clear of any obstruction.
 Adequate ventilation and exhaust fan should be provided.
 Observe frequent breaks during adverse weather condition.
 Establish systems so workers are rotated away from tasks to
minimize the duration of continual exertion, repetitive motions, and
awkward postures. Design a job rotation.
4.5 Unloading the materials into the  Improper manual handling  Observe proper handling techniques (set the load down in the same
designated area at the site.  Poor housekeeping in the workplace way you picked it up but in the reverse order. Bend at the knees,
 Struck with a sharp and hard object not the hips. Keep your head up, your stomach muscles tight, and
 Area congestion do not twist your body. Keep the load as close to the body as
possible. Wait until the load is ure to release your handhold).
 Provide material handling equipment for the transport of heavy and
large materials/equipment.
 Maintain proper housekeeping and access to the work area shall be
kept clear of any obstruction.
 Designate a location for unloading of materials and to be stored
only on a designated storage area.
 All materials location and storage shall be barricaded and provided
with adequate signage.
5.
Assembly and tying of steel reinforcement
5.1 Reinforcing steel shall be  Working without wearing appropriate  Ensure that all workers are provided with required mandatory PPEs
accurately positioned as per Personal Protective Equipment (PPE). such as Helmet, safety goggles , safety shoes.
Contract Documents and  Struck with the sharp and protruding  Remove unnecessary materials and equipment on the affected
adequately supported and wired object. areas.
together to prevent displacement.  Ergonomic hazard ( poor body  Ensure all protruding steel bars shall be provided with suitable
positioning, repetitive movement). means of protection such as protective caps.
 Extreme temperature  Establish systems so workers are rotated away from tasks to
s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

 Fabricated hand tools used. minimize the duration of continual exertion, repetitive motions, and
awkward postures. Design a job rotation.
 Observe frequent breaks during adverse weather condition.
 Observe “use the right tool” during the whole activity.
 Provide proper steel fixing hand tools.
 Improvised and fabricated hand tools shall not be used
 Supervisor and Foreman shall ensure that workers are provided
with proper hand tools.
5.2 All reinforcement steel shall be  Poor supervision  Only experienced and competent workers should engage in a job.
supported or spaced off the forms  The poor condition of tools use  Defective tools should be segregated and not to be used at the site.
by concrete or metal supports.  Working without wearing appropriate  Ensure that all workers are provided with required mandatory PPEs
Personal Protective Equipment (PPE). such as Helmet , safety goggles , safety shoes.
 Struck with the sharp and protruding  Remove unnecessary materials and equipment on the affected
object. areas
 Ergonomic hazard ( poor body  Ensure all protruding steel bars shall be provided with suitable
positioning, repetitive movement). means of protection such as protective caps.
 Extreme temperature  Establish systems so workers are rotated away from tasks to
 Fabricated hand tools used minimize the duration of continual exertion, repetitive motions, and
 Incorrect manual handling/ lifting of awkward postures. Design a job rotation.
material.  Observe frequent breaks during adverse weather condition.
 Observe “use the right tool” during the whole activity.
 Provide proper steel fixing hand tools.
 Improvised and fabricated hand tools shall not be used.
 Supervisor and Foreman shall ensure that workers are provided
with proper hand tools.
 Only 20 kg allowed lifting by an individual.
 Use a buddy system if load exceed.
 Keep hands away from pinch/crash points.
5.3 Concretes which are placed on the  Improper manual handling.  Observe proper handling techniques (do not twist or turn the body;
ground, supporting concrete  Lifting light to moderate-heavy loads. instead, move your feet to turn. Your hips, shoulders, toes, and
blocks shall be used, in sufficient  Sharp and protruding objects. knees should stay facing the same direction).
numbers to support the bars  Poor access in the workplace.  Use mechanical lifting equipment (hand carts, trucks) to move
without the settlement.  Extreme temperature. large, awkward loads.
s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

 Ergonomic hazard ( excessive force,  Appropriate hand protection shall be worn properly.
repetitive movement).  Ensure all protruding steel bars shall be provided with suitable
means of protection such as protective caps.
 Maintain proper housekeeping and access to the work area shall be
kept clear of any obstruction.
 Adequate ventilation and exhaust fan should be provided.
 Observe frequent breaks during adverse weather condition.
 Establish systems so workers are rotated away from tasks to
minimize the duration of continual exertion, repetitive motions, and
awkward postures. Design a job rotation.
5.4 All concrete blocks used to space  Struck with the sharp and protruding  Ensure all protruding steel bars shall be provided with suitable
reinforcement steel off vertical object. means of protection such as protective caps.
formed surfaces shall be tied to  Ergonomic hazard (poor body  Appropriate hand protection shall be worn properly.
the steel with wire ties which are positioning, repetitive movement).  Establish systems so workers are rotated away from tasks to
embedded in the blocks.  Extreme temperature. minimize the duration of continual exertion, repetitive motions, and
 Fabricated hand tools used. awkward postures. Design a job rotation.
 Incorrect manual handling of  Observe frequent breaks during adverse weather condition.
material.  Observe “use the right tool” during the whole activity.
 Provide proper steel fixing hand tools.
 Improvised and fabricated hand tools shall not be used.
 Supervisor and Foreman shall ensure that workers are provided
with proper hand tools.
 Keep hands away from pinch/crash points.
5.5 Tie wires shall be bent away from  Sharp & protruding materials/  Ensure appropriate hand protection worn properly.
the forms in order to provide the objects.  Ensure all protruding steel bars shall be provided with suitable
specified concrete coverage.  Poor supervision. means of protection such as protective caps.
 The location shall be barricaded and provided with adequate
signage to warn other workers about the hazard present in the
work area.
 Only experienced and competent workers should engage in a job.
 Close supervision by the Engineer, Supervisor or Foreman must be
observed.
s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

6.
Cutting of ply wooden materials for formworks
6.1 Forms shall be cut with respect to  Exposure to outdoor weather.  All activities shall be stopped at high winds, EXTREME
the required shape, size and  Wood particles from ejection during TEMPERATURES & sandstorm.
conform to the established the cutting operation.  Cool drinking water must be present and accessible to all the
alignment and grade.  Contact with blades at point of workers.
operation.  Adjust work timing and exposure of the workers.
 Flying chips, wooden materials.  Provide rest shelter with shade near to the workplace.
 Airborne dust  Only trained personnel shall operate wood cutting machines.
 Pinch point  Ensure all guards are fitted, ured, and functional. Do not operate if
 Excessive noise guards are missing or faulty.
 Allow the saw blade to obtain maximum speed before making a cut.
 Use a push stick to guide the timber through saw to prevent hand
injuries.
 The machine shall be switched off when making adjustments or
maintenance.
 Immediately switch off the machine when work completed.
 Always keep hands away from the rotating blades.
 Ensure machine is equipped with an emergency stop button and
must be operational.
 Suitable ear protection, eye protection respiratory shall be worn
properly.
6.2 Lay-out and mark the plywood  Improper manual handling  Observe proper lifting techniques.
material prior to cutting.  Lifting light to moderate heavy load.  Use proper lifting methods, including team lifting when necessary.
 Awkward posture  Lift with legs, keep loads close to the body, and don’t twist while
 An incompetent worker doing the picking uploads.
task.  Appropriate hand protection shall be worn properly.
 Only experienced and competent workers should engage in a job.
 Close supervision by the Engineer, Supervisor or Foreman must be
observed.
6.3 Use the appropriate cutting tool or  Electric shock  Ensure that the machine is equipped with an emergency stop
equipment when cutting plywood  Improper grounding button that can quickly stop the machine in case of emergency.
material.  Defective electrical equipment.  Frequent inspection of the machine to ensure it is in good working
s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

 Operator misuse condition.


 Lack of training by the user  Ensure all electrical tools used are being inspected by a competent
 Slip, Trip, Fall at the same level. electrician to make sure it is safe for use.
 Hot works (cutting of forms).  Any defective items shall be removed out from service immediately.
 Electrical sources shall be equipped with GFCI protection.
 Only experienced and competent workers should engage in a job.
 All electrical cables shall be properly laid in a safe manner keeping
walkways clear of any obstruction.
 All electrical wires shall be of a double insulated material with a
suitable type of plugs. Avoid tapping bare wire into sockets.
 Provision of an adequate Fire extinguisher in the workplace.
 Remove or protect all the combustible/flammable materials in the
working area.
7.
Installation of formworks
7.1 Formwork frames should be  Poor handling of materials  Avoid excessive manual handling of heavy materials, use proper
erected progressively to ensure  Struck against sharp material during lifting methods, including team lifting when necessary.
the installers’ safety and the movement / Impalement.  Lift with legs, keep loads close to the body, and don’t twist while
stability of the overall structure.  Struck by the formwork panels picking uploads.
 Use mechanical lifting equipment (hand carts, trucks) to move
large, awkward loads.
 Appropriate hand protection shall be worn properly.
 Ensure all protruding shard object shall be guarded such as
protruding rebar to prevent impalement hazards.
7.2 Braces should be attached to the  Slip, Trip, Fall at the same level.  Necessary warning signs shall be posted barricades must be
frames as soon as practicable and  Defective hand/power tools. provided.
designated access ways should be  Electric shock  Ensure all electrical tools used are being inspected to ensure it is
indicated by using bunting or by  Flying particles and dust exposure. safe for use.
other means.  Any defective items shall be removed out from service immediately.
 Electrical sources shall be equipped with GFCI protection.
 All electrical cables shall be properly laid in a safe manner keeping
walkways clear of any obstruction.
 All electrical wires shall be of a double insulated material with a
s

Project Name: R12-T07B11-BDOM Contract ( Temporary Utilities – SWRO


Plant )
Project No.: 225191400
Method Statement for Formwork
Document Title:
Metito Document No.:
Client Document No.:

suitable type of plugs. Avoid tapping bare wire into sockets.


 Ensure appropriate PPE is used during chipping and cleaning of
formworks as blowing dust and flying concrete particles may occur.
7.3 Ensure framing, including bracing,  Site documents/design not available  Ensure that all drawings/designs, and documents available on site
is carried out in accordance with in the project. were approved by the client.
on-site design documentation and  Supervisor and workers receiving  Close supervision by the Engineer, Supervisor or Foreman must be
manufacturers’ instructions. little or no support to enable them to observed.
effectively carry out their work.  Full support from site management to ensure that the workforce is
 Supervisor and workers were stress performing efficiently and carries their job well.
due to unnecessary work demands to  The project team must have proper planning for the entire task, this
beat the deadline of the project. would prevent stressing workers and avoid delays of the project
progress.
8.
Housekeeping (clearing the work area)
8.1 Prior to housekeep, wearing  Inadequate PPE use  Special personal protective equipment must be observed like
personal protective equipment coverall clothing, rubber gloves, respiratory equipment, clear
such as safety gloves and mask goggles and etc.
must be fulfilled by the personnel
involved.
8.2 Removal of tools, equipment and  Improper handling and storage of  Tools and other materials should be properly stacked and arranged.
other excesses/ unused materials materials.  Materials should be stored only in the designated area and in the
manually. shaded area.
8.3 Disposing of waste to dedicated  Presence of waste materials.  Provide appropriate waste/trash container in the area.
waste bin/container.  Waste accumulation  Proper disposal segregation of waste / used materials.
 Install appropriate notices and signage.
8.4 Sweeping and cleaning the area.  Awkward posture performing the  Ensure awareness training provided to all affected employees with
task. correct body posture or body positioning before the actual activity.
 Conduct toolbox meeting to discuss all the hazard of the activity
 Close supervision by the Engineer, Supervisor or Foreman must be
observed.

You might also like