Coal Mill Area
Coal Mill Area
Ball Mill
1. Check the mill internals, Diaphragm plates, Tensioning of belts, Shell line
bolts etc.,
2. Check the grinding media grading as per recommended filling. Initially mill to
be start only 50% of grinding media only. We have to slowly increase the
quantity
3. Diaphragm flow control gate, centre screen to be inspected
4. Man hole doors to be closed
5. Check the mill inlet and outlet truninon, Bearing condition, Oil flow on the
shaft, scraper arrangement, Initially drain the oil, Fill new oil. Bearing
temperature RTD fixing and commissioning. Lube oil pump pressure setting
up 3 bar. Return line Inspection, Lube oil system to be commissioned for
trunion bearings.
6. Mill girth gear inspection, Root clearance, Back lash, contact to be checked,
Lubrication system to be commissioned. Proper guarding is required for kiln
girth gear and pinion.
Drive System :
1. Ensure all the air slides boxes side doors, air gaps, Inlet and outlet
connections to be checked
2. Air slide blowers to be take train run. Check the rotation, vibration, motor
temperature Amps etc.,
3. Pipe line connection to Air slide, Air chamber to be ensured
4. Check the blower discharge valve should be open condition
5. Before starting the system. Initially one hour before warm up is required.
Keep the blower in running condition.
6. Blower filter to be cleaned
Dynamic Separator
1. Ensure the separator bolts, connecting chutes motor and gear box frame
bolts tightening etc.,
2. Check the empty motor trial, Amps, direction etc.,
3. Ensure gear box oil filling, coupling input and output guards fixing etc.,
4. Please ensure the bottom bearings RTD fixing etc.,
5. Ensure the grease pipe line for bottom bearing etc
6. Please check the separator impeller direction of rotation
7. If it is VFD slowly start with 50 RPM to 800 RPM as per drawing required RPM
(output)
8. Check the double flap valve free or not.