Question: Are offshore process / production installations included within the scope of
the PED?
Guideline related to :
Article 1 Para 2(a)
Article 1 Para 2(i)
Article 1 Para 2(n) and
current Guideline A/37
current Guideline A/27
Answer: Yes
Notes :
Well Control Equipment (including for example, BOP and driller’s choke
and kill manifolds) is excluded in line with Article 1 paragraph 2(i) (well
control equipment)
Extent of the installation: in line with the intent of the pipeline exclusion
Article 1 paragraph 2(a), the installation extends from the inboard flange
of the isolation device on the incoming process line to the inboard flange
of the isolation device on the outgoing process line.
Page 1 of 2
Ancillary Systems (such as chemical injection, air, nitrogen, etc.) are
included. For MOUs, FPSOs, FPPs, JUPPs where the ancillary systems
are take offs from the marine systems, they should be included within
PED up to their interface with the marine systems.